Primavera P6 Tutorial: How to update Primavera P6 schedule from Excel

Поділитися
Вставка
  • Опубліковано 15 вер 2024

КОМЕНТАРІ • 27

  • @mahansor8295
    @mahansor8295 4 роки тому

    Hi , thanks , very informative.
    I've got a question, how can we assign a virtual resource to all activity as a weight factor to see the project's s-curve, I mean wee preserve the current resources and cost, just add this virtual resource and see the result without affecting these two types of resources on eachother. Please don't hesitate if you need any further information, kind regards.

    • @dptutorials
      @dptutorials  4 роки тому

      Good question!, you can connect me at dptutorials15@gmail.com to understand this question better. Will share my contact number to discuss this.

    • @mahansor8295
      @mahansor8295 4 роки тому

      @@dptutorials Hi, I've sent email to you. Thanks.

  • @blainecote8134
    @blainecote8134 11 місяців тому +1

    Very informative and clear and precise thank you

  • @natalieduquesnay3497
    @natalieduquesnay3497 2 роки тому +1

    thank you, the tutorial helpful and easy to follow

  • @alexbond3953
    @alexbond3953 Рік тому +1

    Good work thank you 🙏

  • @askdprosmediatv9353
    @askdprosmediatv9353 3 роки тому +1

    Very helpful.

  • @Adityasinghstockmarketedu
    @Adityasinghstockmarketedu Рік тому

    very much onformatic

  • @arijitchatterjee3163
    @arijitchatterjee3163 2 роки тому

    Hi Sir .. many thanks... could you please show how to update both progress & actual & remaining units.. I mean what are the things we need to update in a resource loaded schedule and how to perform it from excel ?

  • @kiranshetty6620
    @kiranshetty6620 4 роки тому +1

    Can you make a video on quick Resource Assignment to a very lengthy Program with Budgeted Units

    • @dptutorials
      @dptutorials  4 роки тому

      please check this video if it serves your purpose: ua-cam.com/video/R8zdv1Jvyvw/v-deo.html
      If your question is different, please let me know to publish a video on that topic accordingly.

  • @MDSN1994
    @MDSN1994 4 роки тому

    Thanks
    if the remaining duration is not updated, does it works properly?

    • @dptutorials
      @dptutorials  4 роки тому +1

      No, You have to update the remaining duration

  • @zeyaulhaque7790
    @zeyaulhaque7790 2 роки тому

    Sir, What is difference between excel and p6? We can plan in excel

    • @dptutorials
      @dptutorials  2 роки тому

      Yes, you can plan in excel as well but with the Primavera, you can do wonders.

    • @zeyaulhaque7790
      @zeyaulhaque7790 2 роки тому

      One small project plan in P6

  • @functionspro6376
    @functionspro6376 3 роки тому

    For Physical Progress (%), still you need to update it in Primavera.

  • @austinnepolianpereira1912
    @austinnepolianpereira1912 2 роки тому

    How to add in progress percentage

    • @dptutorials
      @dptutorials  2 роки тому

      % of progress gets automatically gets updated based on actual duration for the duration type activities and manually for the physical % type activities. Will definitely try to post a video on this.