Resource Allocation from Excel to Primavera P6 | Resource assignment from Excel to Primavera P6 Tips

Поділитися
Вставка
  • Опубліковано 6 вер 2024
  • #Softedemy,#PrimaveraP6,#Resourceallocation
    In this tutorial, let us learn to Resource Allocation from Excel to Primavera P6 | Resource assignment from Excel to Primavera P6 Tips
    Previous Videos
    1. Save print Settings | using Import and Export | Primavera P6 layout Files | Plf | Solutions | Tricks
    • Save print Settings | ...
    2. Update Progress using Activity Steps | Create Template | Performance Percent | Primavera P6 | Tips |
    • Update Progress using ...
    3. How to Maintain an Activity Change Log | Primavera P6 | UDFs | Activity Steps | Delay log | Hacks
    • How to Maintain an Act...
    4. How to set Default Activity IDs numbering | Modify Activity Suffix and Prefix | Primavera P6 | Tip |
    • How to set Default Act...
    5. How To Renumber Activity IDs For All Activities In An Ascending Order In Primavera P6 | Tips
    • How To Renumber Activi...
    6. How to Change Activity IDs by Export and Import | Primavera P6 Simple Easy and Fast Method | Tips |
    • How to Change Activity...
    7. Primavera P6 Difference Between Activity Calendar and Resource Calendar | Change Calendar | Tips
    • Primavera P6 Differenc...
    8. What are activity types relationship and their role in Primavera P6 | Easy Complete Tutorial |
    • What are activity type...
    9. Import Project Expense cost in Primavera P6 from Excel file | Load Expense in Project | load Actuals
    • Import Project Expense...
    10. Export and Import Primavera P6 Project with Baseline in XML Format | Multi projects in single file |
    • Export and Import Prim...
    11. Explained Difference Between XML and XER File while Importing and Exporting from Primavera P6
    • Explained difference B...
    12. How to Convert WBS to Activity Code in Primavera P6 | Using Excel | Easy Fast Trick | Large Schedule
    • How to Convert WBS to ...
    13. Easy Creating WBS and activities in Primavera P6 | Help of Excel and MPP | Import XML and MPX Format
    • Easy Creating WBS and ...
    14. How to Remove Actual from Updated Project in Primavera P6 | Remove Progress | Change Activity Status
    • How to Remove Actual f...
    15. Explain Difference between Delete and Dissolve Activity in Primavera P6
    • Explain Difference bet...
    16. How To Remove Relationships From Multiple Activities In Primavera P6 | Remove Predecessor Successors
    • How To Remove Relation...
    17. What are dangling logic in Project Schedules in Primavera P6 | Resolve dangling logic and Activity |
    • What are dangling logi...
    18. How to find or detect lag and dangling logic in Project Schedule of Primavera P6 by using Excel tips
    • How to find or detect ...
    19. How to build lookahead in primavera p6 | Lookahead Schedule | Layout | Plan | Filter | Tips Tricks
    • How to build lookahead...
    20. How to Highlight Activities Using Filters And Spotlight Feature In Primavera P6 | Tips and Tricks
    • How to Highlight Activ...
    21. How to fix Log File Can't Be Created Error in Primavera P6 during Scheduling | Problem Solution |
    • How to fix Log File Ca...
    22. How to Change Password in Primavera P6 | Recover Password | Reset Password | Tips and Tricks | SQL
    • How to Change Password...
    23. How to Assign or to Remove Multiple Resources From Multiple or all Activities in Primavera P6 | Tips
    • How to Assign or to Re...
    24. Difference Between Retained logic and Progress Override in Primavera P6 | Progress Update | schedule
    • Difference Between Ret...
    25. How to Track Find Detect Out of Sequence Activities in Primavera P6 | Filter | Schedule log | Tips
    • How to Track Find Dete...
    26. How to Create Custom Selection of Activities by using Filter to Print in Primavera P6 | Tips Tricks
    • How to Create Custom S...
    27. Print or display Highlighted Activities Gantt Chart different bars by apply Filter in Primavera P6
    • Print or display Highl...
    28. Suspend and resume activity in Primavera P6 adding delay events for Extension of Time | Tips tricks
    • Suspend and resume act...
    29. Calculate and assign estimated weights from Excel to Primavera P6
    • Calculate and assign e...
    30. How to fix deadlines of the project in Primavera P6 | without use constraints | Expected finish | P6
    • How to fix deadlines o...
    31. How to use progress line to monitor activities performance in Primavera P6| Show delays graphically
    • How to use progress li...
    32. Explained Critical and Near Critical Activities differences in Primavera P6 | Total Float | P6
    • Explained Critical and...
    Contact Details
    Email for Contact: Softedemy@gmail.com
    Facebook Group Link: tinyurl.com/yz...
    LinkedIn Page: tinyurl.com/ke...

КОМЕНТАРІ • 59

  • @Hagosea75
    @Hagosea75 4 місяці тому +1

    The best tutorial I've ever seen

  • @akhtarali-qv3en
    @akhtarali-qv3en 3 роки тому

    Thanks for your valuable information 👍

  • @SoftEdemy
    @SoftEdemy  3 роки тому

    For any query contact us on our email : info@softedemy.com

  • @davidgray5764
    @davidgray5764 4 місяці тому

    How can I import the monthly budget profile for activities? The budget monthly spend comes in excel from the subcontractor for each activity (500). I need to import it as it takes too long to manually change it. Is there a way to do this?

    • @SoftEdemy
      @SoftEdemy  4 місяці тому

      Use P6 23.12 , copy and paste direct resource assignments.
      Watch our video on P6 23.12 new features. I have explained how to do it.

    • @davidgray5764
      @davidgray5764 4 місяці тому

      @@SoftEdemy Excellent! Thank you for such a prompt reply. I have just watched the video. This is a really excellent new capability for planners that are working at client level and are not generating budgets from within P6, but need to add them to their schedule. It would be good to do a video just on this new capability.

    • @SoftEdemy
      @SoftEdemy  4 місяці тому

      @davidgray5764 currently very busy. I will create video on this later.
      But you can understand how to use it from video.

  • @SS-Shadow
    @SS-Shadow 3 роки тому +2

    👌👍👍

    • @SoftEdemy
      @SoftEdemy  3 роки тому

      Thanks for your Comment

  • @BaraRaed
    @BaraRaed 2 місяці тому

    How do you prepare the excel sheet in colors ?

    • @SoftEdemy
      @SoftEdemy  2 місяці тому

      Please check below link video
      ua-cam.com/video/uBhP_2jKTJE/v-deo.htmlsi=wYxt7NP1OxembbyP

  • @youssefj7396
    @youssefj7396 Рік тому

    thank you sir for this awesome explanation it has worked for me, but in case we have an activity with two resources with different budgeted unit ( EX : activity duration 2 days - Project manager 6h/day and labor 8h/day ) how could we do that in excel, or we have to do it manually in P6

    • @SoftEdemy
      @SoftEdemy  Рік тому

      No you can do it on excel. Just add duplicate the activity with different resource name

    • @youssefj7396
      @youssefj7396 Рік тому

      @@SoftEdemy thank you sir

    • @SoftEdemy
      @SoftEdemy  Рік тому

      @@youssefj7396 welcome

  • @mahesht4162
    @mahesht4162 4 місяці тому

    Ok sir

  • @ahsanrana3804
    @ahsanrana3804 Рік тому

    Sir you told in the video that if you want to calculate bugeted video for example if we have 100 cm concrete then you have to calulate Budget unit = Boq Value /Productivity rate. Will you please tell me what is productivity rate Thanks.your videos are awsome

    • @SoftEdemy
      @SoftEdemy  Рік тому +1

      Get productivity rates from the company or get it as per your experience. You can download productivity from Google.

    • @ahsanrana3804
      @ahsanrana3804 Рік тому

      Sir thanks for the answer but actually i mean what is productivity rate is there any defination of productivity rate?

    • @ahsanrana3804
      @ahsanrana3804 Рік тому

      One more thing Sir i am waiting for your new videos. It has been 2 months gone you have not uploaded new video. Thanka

    • @SoftEdemy
      @SoftEdemy  Рік тому +1

      @@ahsanrana3804 the amount of you done in unit Time

    • @ahsanrana3804
      @ahsanrana3804 Рік тому

      Thanks for reply Sir

  • @edpm7213
    @edpm7213 2 роки тому

    I followed your steps, however it failed to import. It shows "foreign key not identified" . What will be the possible reasons .
    TIA

    • @SoftEdemy
      @SoftEdemy  2 роки тому

      Sorry for the late response.Can you tell me which steps did you follow to resolve the issues and also can you tell me when this error appeared? It may be possible you have created the resource that you have assigned. or you have incorporated the wrong resource iD in the column. If you are facing still the same issue you can contact me at my Whatsapp wa.link/36dp7i

  • @zhangyong5397
    @zhangyong5397 2 роки тому

    Hello,Why during importing, the list of project is not displayed in « selected project »?

    • @SoftEdemy
      @SoftEdemy  2 роки тому

      if you are importing a project which already exist with same Project ID and name.than during import it ask that do you want to update existing project.In that case if you have selected update existing project than it will be shown only the match project.if you select create new project than their will be new project added in the eps.but projects will be not shown.Because the excel file you are importing have specific data source.Which is related to specific project and it only integrated to that project. Excel import cannot to be done to different project.thats why only the project relevant to the excel data will be displayed and can be changed .I hope you got the answer.

  • @Mahrash
    @Mahrash 3 роки тому

    My brother thanks for the above video can you share the project file for practice

    • @SoftEdemy
      @SoftEdemy  3 роки тому +1

      Send Request Email on Softedemy@gmail.com also mention the video link with name.Thanks

  • @dastak4724
    @dastak4724 2 роки тому

    Good

    • @SoftEdemy
      @SoftEdemy  2 роки тому +1

      Thanks Dastak .its may me one word for you. But this word releases our hard work stress and motivate us to work harder for all our viewer. The most important is our viewer's feedback. You have taken the responsibility for feedback. thanks for your comments

    • @dastak4724
      @dastak4724 2 роки тому

      @@SoftEdemy really I appreciate your efforts. I am waqas.

  • @hendawyragabelashry553
    @hendawyragabelashry553 3 роки тому

    thanks bro . could you plz share these materials

    • @SoftEdemy
      @SoftEdemy  3 роки тому

      Send Request Email on Softedemy@gmail.com also mention the video link with name.Thanks

  • @toppakistan6129
    @toppakistan6129 2 місяці тому

    How did you create Resource Assignment Excel Template?

    • @SoftEdemy
      @SoftEdemy  2 місяці тому

      From productivity rates and BOQ check other videos at our channel

    • @toppakistan6129
      @toppakistan6129 2 місяці тому

      Thank you
      Kindly mention columns header in excel.
      Regards

    • @SoftEdemy
      @SoftEdemy  2 місяці тому

      @toppakistan6129 already mentioned.
      The video is related to resource allocation using excel.
      It's not about how to create resource loading sheet.
      Their are other videos that explain how to create a resource loading sheet.
      Also please listen clearly what has been explained in the topic title.
      All the video's are strict to their title names.

  • @mahesht4162
    @mahesht4162 4 місяці тому

    Sir, How to edit the Resource Assignment area. I want to change the manpower. For example Activity 1 - 3 months duration. Month 1 - 6 painter, Month 2 - 8 painter, Month 3 - 8 painter I need to edit this much.
    But in primavera automatically it is changed for example M 1 - 4 days, M 2 - 6 days, M 3 - 7 days like this

    • @SoftEdemy
      @SoftEdemy  4 місяці тому

      Change spreadsheet into budget units and remove any intervals.
      Than you can edit by double click in a cell.

    • @mahesht4162
      @mahesht4162 4 місяці тому

      Sir actually I am a beginner, can you explain one more time. Which spread sheet and how to remove intervals. Please sir

    • @SoftEdemy
      @SoftEdemy  4 місяці тому

      @mahesht4162 go to resource assignment. On right side their is spreadsheet. Right to change spreadsheet columns to budgeted units and also intervals as spreadsheet intervals in same options

    • @mahesht4162
      @mahesht4162 4 місяці тому

      ​@@SoftEdemy I changed budgeted units

    • @mahesht4162
      @mahesht4162 4 місяці тому

      It is in month intervals