Update P6 Schedules Easier with Excel [How To]

Поділитися
Вставка
  • Опубліковано 2 гру 2024

КОМЕНТАРІ •

  • @PlanAcademy
    @PlanAcademy  4 місяці тому +4

    Get the FREE Excel Update Template in the description! And COMMENT to let us know what other P6 Videos you would like us to make.

  • @shivamsunny329
    @shivamsunny329 4 місяці тому +2

    Bro you nailed it.... Love from india.🎉.🎉🎉

  • @evanwakelin7944
    @evanwakelin7944 4 місяці тому +1

    Thanks Faraz! Glad you are making videos now!

  • @reginaldibenne6875
    @reginaldibenne6875 2 місяці тому +1

    make video on how to create Manhour S-curve and Histogram in Excel with P6 Data

  • @muhammadshoaib2833
    @muhammadshoaib2833 4 місяці тому

    Very well explained, appreciated.
    My suggestion to focus mostly on field related topics
    Like how to prepare the change log during updating the program, 3 weeks lookahead, how to inform PM for the delay activities , something like flags.
    Recovery schedule
    EOT claims and revised schedule

  • @syednoormohiuddin3125
    @syednoormohiuddin3125 4 місяці тому

    superb explanation in a easy method thanks i hope to learn more from him and I impressed and subscribed

  • @shijukoshy7649
    @shijukoshy7649 2 місяці тому

    Nice presentation

  • @jemsheerpalasseriparasseri9817
    @jemsheerpalasseriparasseri9817 4 місяці тому

    Nice Presentation. Keep going. All the best dear.

  • @noorbanushaikh8969
    @noorbanushaikh8969 3 місяці тому

    Keep up the good work

  • @mjestvofficial7792
    @mjestvofficial7792 4 місяці тому +1

    Thanks for the tutorial Sir

  • @khyun125-o6j
    @khyun125-o6j 4 місяці тому +1

    I got the free template on mail. Ty.

  • @khanazeem1414
    @khanazeem1414 3 місяці тому

    Good work

  • @Eggpossseeddd
    @Eggpossseeddd 4 місяці тому

    It works only if the percentage complete type is Duration.
    If it's physical you must update Unit percent compete as well along with Actual regular units / Actual units too.

    • @reginaldibenne6875
      @reginaldibenne6875 4 місяці тому

      you mean you can't update from Excel when the % complete Type is
      "Physical"?

    • @PlanAcademy
      @PlanAcademy  4 місяці тому

      @@reginaldibenne6875 You can see in the video that my activity's % complete type is physical.

  • @azamKhan-pp8xi
    @azamKhan-pp8xi 4 місяці тому +1

    Amazing

  • @HassanAhmed-nc7kc
    @HassanAhmed-nc7kc 3 місяці тому

    VERY GOOD VEDIO

  • @shakeelahmedhussain5208
    @shakeelahmedhussain5208 4 місяці тому

    Make a complete video on EOT

  • @afzaalali4521
    @afzaalali4521 3 місяці тому

    Hello Faraz and Michael,
    Can you please help me in solving this issue.
    After putting the actual dates, when I exported back excel file into P6, all 100% competed activities in the update period are not taking the actual start and actual finish dates.
    100% completed activities are taking plan start and plan finish date.
    In progress activities are ok.

    • @PlanAcademy
      @PlanAcademy  3 місяці тому

      If you follow the steps with the correct formatting and data, the date should usually import successfully. Please double-check the data you've imported and pay close attention to every detail during the process.

  • @saud83mech
    @saud83mech 4 місяці тому

    How Can I contact You Faraz? I need some advance level training

    • @PlanAcademy
      @PlanAcademy  4 місяці тому

      you can contact us at info@planacademy.com

  • @arlanresoco2196
    @arlanresoco2196 4 місяці тому

    GOOD

  • @reginaldibenne6875
    @reginaldibenne6875 2 місяці тому

    You don't need to add the REMAINING DURATION because P6 will automatically calculate it

    • @PlanAcademy
      @PlanAcademy  2 місяці тому

      When the % Complete type field is set to "Physical" in P6, it will not automatically calculate the Remaining Duration. Therefore, you must manually enter the Remaining Duration.