Project Management: Finding the Critical Path, duration and Project Duration | Critical Path Method

Поділитися
Вставка
  • Опубліковано 4 лют 2025

КОМЕНТАРІ • 128

  • @radhikapareek2701
    @radhikapareek2701 2 роки тому +33

    Thank you so much sir ☺️ for such a easy explanation 😊.

  • @RanjanKumar-vs5ex
    @RanjanKumar-vs5ex Рік тому +15

    Tomorrow is my project management exam and I'm watching this video for first time 😃

  • @addisukorra7322
    @addisukorra7322 2 роки тому +22

    Activity No. Activity description
    Duration
    (days) Depends on
    1 Site clearance 2
    2 Excavation in foundations 6 1
    3 Foundations including plinth beam 10 2
    4 Column casting up to roof level 10 3
    5 Slab and beam of roof 21 4
    6 Earth filling and flooring 10 5FS 1 10d
    7 Brickwork 10 5FS 1 7d
    8 Doors/windows 3 7FF
    9 Plastering 10 7SS 1 7d
    10 Painting 7 9SS 1 7d
    11 Plumbing 7 7FF 1 3d
    12 Electrical works 7 11SS
    13 Handover 1 10, 11, 12

  • @akshaykayapak8209
    @akshaykayapak8209 2 роки тому +6

    nicely easily explained sir..thank you so much

  • @SharableMail
    @SharableMail 8 місяців тому +5

    very clear easy to understand thank you

  • @MAHENDRALANJHI-pe8zo
    @MAHENDRALANJHI-pe8zo Рік тому +2

    Thank you sir it is beneficial.

  • @thebesttechnical3608
    @thebesttechnical3608 Місяць тому +2

    I learned something new today! Great video

  • @HeyGoogle-i4f
    @HeyGoogle-i4f 12 днів тому

    Thank you so much so saved my day 🥰

  • @parameshnaidu5946
    @parameshnaidu5946 Рік тому +2

    Easy manner to understand everyone tq so much bro 😊

  • @Sunil_bavoor13
    @Sunil_bavoor13 2 роки тому +4

    thank you sir for explaining this tomarow I have exam PROJECT MANAGEMENT SKIIL (PMS)

  • @NairoshiKimisoi
    @NairoshiKimisoi 7 місяців тому +1

    ❤❤❤❤❤wow thanks 👍 sir, you teach well ❤❤

  • @Sisterdiya
    @Sisterdiya 6 місяців тому

    Thank You Respected Sir for teaching me so well during my examination days. You have been a blessing for all these days. Thank You Dear and Respected Sir. Thank You. God bless you and your family always. ❤️🙏✝️

  • @madhukarnaidunaidu4852
    @madhukarnaidunaidu4852 2 роки тому +1

    Thank you for the video, useful

  • @g.vofficial7624
    @g.vofficial7624 2 роки тому +3

    Thankyou so much sir good explanation 🙏

  • @harishgowda8600
    @harishgowda8600 18 днів тому

    Earliest and latest starting time are not required?

  • @learnwithb2138
    @learnwithb2138 Рік тому +1

    Thank you sir 🙏

  • @amaliaazufa5232
    @amaliaazufa5232 2 роки тому +1

    thanks for the explanations

  • @cybershrajal
    @cybershrajal 7 місяців тому +6

    We are computer science student watching this

  • @029_menaha4
    @029_menaha4 Рік тому

    Thank you for this video sir

  • @addisukorra7322
    @addisukorra7322 2 роки тому +3

    Two project activities ‘A’ and ‘B’ (B being dependent on A) have a finish-finish relationship with 8 days ‘lag’. The estimated duration for the activities are 10 days and 15 days, respectively. If activity ‘A’ is scheduled to start on the 12th day from the beginning of project, on which day can you schedule to start activity ‘B’?

  • @johnkallonyokie
    @johnkallonyokie 9 місяців тому

    Very clear and understandable thanks

  • @adabalanagavenkatavinay1485

    Super explanation sir thanku so much

  • @shiva_rocky
    @shiva_rocky 2 роки тому +2

    Sir good explanation thank u 😊

  • @alindayu
    @alindayu Рік тому +1

    Very similar to operation management: production routing planning.

  • @nikhithab4631
    @nikhithab4631 2 роки тому

    Easy way and good information sir

  • @saurabhpandey3535
    @saurabhpandey3535 2 роки тому

    Nice video 👌. Well explained.

  • @Elevateeveryday-w8t
    @Elevateeveryday-w8t Рік тому +1

    So nice ❤

  • @dularakavindu1743
    @dularakavindu1743 9 місяців тому

    Thank you so much ❤

  • @DhirendraBhujel-b5b
    @DhirendraBhujel-b5b 3 місяці тому

    Thsnks so much sir

  • @serbanstere
    @serbanstere 3 роки тому +14

    One question. Are there any restrictions regarding the intersections between arcs ? Are them allowed in this method ?

    • @universeisherestudytime8701
      @universeisherestudytime8701 11 місяців тому +1

      No intersections shouldn't be practiced ... Yes when u make it for the first time u can intersect but then you can make a neatly drawn network

  • @prajyotdeshpande6602
    @prajyotdeshpande6602 3 місяці тому +1

    How can longest path determine minimum amount of time required by project

  • @umarrashid82
    @umarrashid82 2 роки тому +10

    What happened to the slack calculations or float calculations? Arent they necessary to check the criticality and hence find the critical path ?

    • @CivilEngineeringExam
      @CivilEngineeringExam  2 роки тому +3

      i'll continue in next video

    • @mandalapumanikanta3370
      @mandalapumanikanta3370 Рік тому

      ​@@CivilEngineeringExam brother can you please tell me tution this subject per one hour daily or every three per a week please brother I very trouble to understand this subject

    • @mandalapumanikanta3370
      @mandalapumanikanta3370 Рік тому

      Please 🙏🏻 brother

  • @vinayakbadiger2063
    @vinayakbadiger2063 Рік тому +1

    Well explained

  • @n30n2d3
    @n30n2d3 5 місяців тому +2

    A for 🍎
    B for 🏀
    C for 🐈
    D for 🐕
    E for 🐘
    F for 🐠

  • @harshitmishra9852
    @harshitmishra9852 2 місяці тому

    Thanks u sir

  • @66_priyeshgurjar97
    @66_priyeshgurjar97 Рік тому

    Sir How long will it take to Complete the Project and Critical Path Duration Is same???

  • @AlbatrossInstmine
    @AlbatrossInstmine Рік тому +61

    Sir why can't we take B - F - I - H . It will be the the critical path as 4 + 5 + 12 + 22 = 43 , Hence critical path will be 43.

    • @faithkarimi147
      @faithkarimi147 Рік тому +2

      Yeah the same question am asking

    • @_lessthanzero_
      @_lessthanzero_ Рік тому +4

      Check the video again

    • @rajanbhattarai4229
      @rajanbhattarai4229 Рік тому +32

      The time duration of i is 2 not 12

    • @TechNepal8945
      @TechNepal8945 Рік тому +2

      i think this question /answer both are wrong bro there is no activity connected in loop .

    • @techgarg4250
      @techgarg4250 Рік тому

      Bhai waha 2 hai not 12 please it again

  • @abunoman1838
    @abunoman1838 Рік тому

    thanks

  • @magedrefat1658
    @magedrefat1658 Рік тому

    Very clear

  • @danielmbozi3204
    @danielmbozi3204 Рік тому

    It is so critical

  • @shaikhfaiz3450
    @shaikhfaiz3450 Рік тому

    Critical path will be same for everyone or its depends upon different people draw different kind of network draw ? Plz ans me sir or any one plz ?

  • @samuelzvirevo4481
    @samuelzvirevo4481 7 місяців тому

    am confused on activity H,,,,,to put E andJ

  • @CrimeMasterGogo900
    @CrimeMasterGogo900 Рік тому +1

    Sir Path BEIJ Is possible or not and if not than why sir plz reply

  • @danielmbozi3204
    @danielmbozi3204 Рік тому

    But the line you used classify it so short become hard for me to validate the critical path

  • @shafiqahmed3391
    @shafiqahmed3391 2 роки тому +1

    Hi. Do you do assignments? Related to construction management?

  • @vanditapatil5442
    @vanditapatil5442 2 роки тому

    How to put numbers in the circles. I wanted explanation for how to number the events correctly

  • @saravanan02
    @saravanan02 Рік тому

    Sir CE3302 Important mattum podunga sir pls

  • @ucantbeat2256
    @ucantbeat2256 2 роки тому +1

    Verry nice

  • @exploremindtech882
    @exploremindtech882 3 роки тому +1

    Nice bhai

  • @maingadave4841
    @maingadave4841 Рік тому

    A nice one but am struggling to learn the english

  • @bbrakesha4659
    @bbrakesha4659 2 роки тому

    Thinks sir

  • @DhirendraBhujel-b5b
    @DhirendraBhujel-b5b 3 місяці тому

    What is dummy activity

  • @clema3official
    @clema3official 2 місяці тому

    ❤❤❤

  • @AbhishekTiwari-kv4gq
    @AbhishekTiwari-kv4gq Рік тому

    Sir what is slack time?

    • @CivilEngineeringExam
      @CivilEngineeringExam  Рік тому

      difference between the time allocated to the task and the time it actually takes. flexible time for completion of the project

    • @AbhishekTiwari-kv4gq
      @AbhishekTiwari-kv4gq Рік тому

      @@CivilEngineeringExam Thanks sir

  • @danielkim6672
    @danielkim6672 Рік тому

    Thank u curry mucnh

  • @vengalabhaskar
    @vengalabhaskar 2 роки тому

    is it possible to explain with site activities in a construction site ?

  • @shrinishrinivas9605
    @shrinishrinivas9605 2 роки тому

    Tq sir

  • @FredzEditz00
    @FredzEditz00 5 місяців тому

    Sir its J not I
    E and J forms H
    But you said E and I

  • @tonnymakokha
    @tonnymakokha Рік тому +1

    I think the last path is supposed to be B-F-J-H and not B-F-I-H, this is because H is not precedent by I but H is preceded by J, please correct that sir.

  • @md-pind.wala3323
    @md-pind.wala3323 2 роки тому

    Good

  • @santhosh9121
    @santhosh9121 9 місяців тому

    😉😉😉

  • @sudhanshurohela
    @sudhanshurohela 2 роки тому +3

    Shortest duration ko select kyu nahi kiya

  • @neharathod3158
    @neharathod3158 Рік тому

    plz explain proprly. i cant understand

  • @bibo5649
    @bibo5649 Рік тому

    Sir activity D you are confusing us

  • @admanassas1853
    @admanassas1853 8 місяців тому

    This is a PERT chart.....

  • @akshuishighonsleep
    @akshuishighonsleep День тому

    Any hospitality students?😂

  • @sonamtenzin1255
    @sonamtenzin1255 8 місяців тому +2

    your answer is wrong for your information

  • @Prashant121_
    @Prashant121_ Рік тому

    *20 April 2023 I didn't understand. My exam is in next week*

  • @Silverwasp72
    @Silverwasp72 7 місяців тому +1

    B - E - I - J ?

    • @SanceShaji
      @SanceShaji 7 місяців тому

      Not possible since the arrow is NOT from E -> I instead it is from I->E

  • @omkarkshirsagar3337
    @omkarkshirsagar3337 Рік тому

    Hechhh (H) 😂👍

  • @Suki4r
    @Suki4r 9 місяців тому

    This is the most confusing thing for me

  • @footballcreativeeverywhere260
    @footballcreativeeverywhere260 Місяць тому

    B- E -H

  • @ivetymutabazi3514
    @ivetymutabazi3514 8 місяців тому

    It's A not Yee 😬😫

  • @aryamanutkarsh
    @aryamanutkarsh Рік тому +1

    Tch tch soo confused

  • @Snorlax_Play
    @Snorlax_Play 9 місяців тому

    Hindi mai bolo sir

  • @robertfulau4194
    @robertfulau4194 2 роки тому +1

    .

  • @xyz.1234hdgjtvbhh
    @xyz.1234hdgjtvbhh Рік тому

    Its H not hech

  • @anishbista645
    @anishbista645 2 роки тому +5

    time waste mumerical.

  • @shahneelkhan1442
    @shahneelkhan1442 Рік тому

    This is wrong

    • @Rakibul_52
      @Rakibul_52 9 місяців тому

      Are you From Bangladesh (Diu)

  • @safetyadvisorspecialist7272

    thank you sir.