PERT Analysis|| programme evaluation review technique || problem 1 || CPM || network analysis

Поділитися
Вставка
  • Опубліковано 14 жов 2024

КОМЕНТАРІ • 8

  • @moodycanko2565
    @moodycanko2565 Рік тому +4

    Am happy you are sharing your knowledge worldwide ,thank you so much, watching it from Kenya ❤

  • @syedabdulhannan4827
    @syedabdulhannan4827 5 місяців тому +1

    Thank you. You showed everything that is asked for PERT

  • @swetha3749
    @swetha3749 10 місяців тому +1

    Well understood ma'am. But i think there is a small change needed @ 11:51 for (3-6). Isn't it (3+5+24)/6 ma'am? so the answer should be 7 there.

    • @nourhane8800
      @nourhane8800 7 місяців тому +1

      The answer should be 7

  • @lubnaaaz01
    @lubnaaaz01 11 місяців тому

    Ma'am, I have a question about the construction of the initial network diagram. In the rough diagram, you connected node 3 to node 6, but in the final, more refined network diagram, you did not establish a connection between node 3 and node 6. Could you please explain the reason for this difference?

  • @sirshaganguly7706
    @sirshaganguly7706 5 місяців тому

    Do we sum the individual SDs along the CP to find the expected SD of CP or just find out the sqrt. of the expected variance of the CP to find the expected SD of CP?