Your guide to contract variation and the procedure to do it with a variation example

Поділитися
Вставка
  • Опубліковано 23 гру 2024

КОМЕНТАРІ • 42

  • @vinods2655
    @vinods2655 Місяць тому

    Thanks for the informative and detailed explanation.
    I have a question, when we are estimating for a project Tender, in which document states the priority of documents?

    • @vinods2655
      @vinods2655 Місяць тому

      And what if the priority of documents are not stated. Could you please clarify?

    • @CEPQS
      @CEPQS  Місяць тому +1

      It will be a part of conditions of contract

    • @CEPQS
      @CEPQS  Місяць тому +1

      You might need to refer to some standard form of contract like FIDIC.

  • @ThapeloMangole
    @ThapeloMangole Місяць тому

    You are indeed a good teacher

    • @CEPQS
      @CEPQS  Місяць тому

      Thank you 😊

  • @daberechukwumiracle7562
    @daberechukwumiracle7562 Місяць тому

    From Nigeria
    Thanks for the informative and detailed explanation ❤

    • @CEPQS
      @CEPQS  Місяць тому

      Thanks a lot for watching. All love ❤️

  • @M.ri77
    @M.ri77 Місяць тому

    Thank u
    بارك الله فيك و بعلمك يا مهندس معلومات قيمة جداً ❤❤❤

    • @CEPQS
      @CEPQS  Місяць тому

      Thanks a lot for watching and support ❤️

  • @mskmea
    @mskmea Місяць тому

    Thanks for the information and explanation.

    • @CEPQS
      @CEPQS  Місяць тому

      Thank you for watching and commenting 😊

  • @BilalKhan60
    @BilalKhan60 22 дні тому

    Thanks.
    Could you please differentiate among Claim, Variation and change with example.?

    • @CEPQS
      @CEPQS  22 дні тому

      Thank you 😊. I’ll do my best

  • @ayeshishara2353
    @ayeshishara2353 23 дні тому

    Thank you sir❤

    • @CEPQS
      @CEPQS  23 дні тому +1

      Thank you for watching 😊

  • @fayazmuhammad2505
    @fayazmuhammad2505 Місяць тому

    Masha Allah, and thanks for deep knowledge

    • @CEPQS
      @CEPQS  Місяць тому

      Thanks for watching comment ❤️

  • @Engr.abidislam
    @Engr.abidislam Місяць тому

    Very useful insight. Kindly upload more such informative videos

    • @CEPQS
      @CEPQS  Місяць тому

      Thank you for watching. Sure I will

  • @tylerhawkins2769
    @tylerhawkins2769 Місяць тому

    Hello Ahmed, thanks for the awesome video, I just a question if the works are just a quantity addition, but the change is to affect works already complete (eg move a team down three levels cut into a wall to adjust pipes) how will the price be calculated as this task if more difficult than the SOR suggest? thank you for your time.

    • @CEPQS
      @CEPQS  Місяць тому

      Thanks for watching. Regarding your question, I believe the case you discussed is an additional scope that is not part of the contract (modification of existing / completed works), and hence this is type 3 (change in quantities and rates). For these new works, define the scope - in items - and for each item put the rate. For the items that have a rate in BoQ, use it, and for the new items, establish a new rate and substantiate it. Hope that concludes the case. Note: “the completed works can be claimed under the original contract, and the modification will be claimed separately under the VO”.

  • @Gototop777
    @Gototop777 Місяць тому

    Thankyou you Sir
    Jazakallah khair

    • @CEPQS
      @CEPQS  Місяць тому +1

      Thank you 😊

  • @oluwaseunoguntuga5280
    @oluwaseunoguntuga5280 Місяць тому

    Good evening, Sir.
    I would like to know if we can classify the increase in price of material during the cost of the project as a variation?

    • @CEPQS
      @CEPQS  Місяць тому

      It depends on what has been agreed in the contract. Some times it is agreed that if materials price increased more than a pre-agreed percentage then it becomes variation

  • @BiroleP88
    @BiroleP88 Місяць тому

    Hi! Could you post a video about calculating costs in Gypsum works as there’s many different materials and the labour costs increases per m2 if it’s 2 layer or 3 layer boards

    • @CEPQS
      @CEPQS  Місяць тому +2

      Thank you for reaching out. I’ll try to plan for it in the upcoming videos

  • @shaakiromar7311
    @shaakiromar7311 Місяць тому

    Thanks. Mostly, we use wood for our buildings, so do you have a course that is related to wood estimation ..

    • @CEPQS
      @CEPQS  Місяць тому

      Thank you 🙏. My experience is mostly in RC structures 🥹

  • @slaveOfAllah1013
    @slaveOfAllah1013 Місяць тому

    Thank you
    Jazakallah haira ❤❤❤

    • @CEPQS
      @CEPQS  Місяць тому

      Thank you ❤

  • @lofongojohnson
    @lofongojohnson 27 днів тому

    Hi manager
    Am Mr Johnson.
    Thx

    • @CEPQS
      @CEPQS  27 днів тому

      Nice meeting you 😊

  • @priyankaevon2853
    @priyankaevon2853 24 дні тому

    How we can do the omissions

    • @CEPQS
      @CEPQS  24 дні тому +1

      Contract quantity is a number and revised quantity is zero. The net will be in minus ☺️

  • @MohammedAseem-p5u
    @MohammedAseem-p5u Місяць тому

    PLE POST MORE USEFUL VIDEOS SIR

    • @CEPQS
      @CEPQS  Місяць тому

      I will try my best.

  • @engmubarakhaji6259
    @engmubarakhaji6259 Місяць тому

    LIKE YOU WE DON'T GET EVERY WHERE
    I WOULD LIKE TO MAKE VIDEO FROM CONTRACT DOCUMENTS.

    • @CEPQS
      @CEPQS  Місяць тому

      Thanks a lot ❤️. Sure, will try my best 😊

  • @vinods2655
    @vinods2655 Місяць тому

    ❤❤❤

    • @CEPQS
      @CEPQS  Місяць тому

      😊