Thanks for the informative and detailed explanation. I have a question, when we are estimating for a project Tender, in which document states the priority of documents?
Hello Ahmed, thanks for the awesome video, I just a question if the works are just a quantity addition, but the change is to affect works already complete (eg move a team down three levels cut into a wall to adjust pipes) how will the price be calculated as this task if more difficult than the SOR suggest? thank you for your time.
Thanks for watching. Regarding your question, I believe the case you discussed is an additional scope that is not part of the contract (modification of existing / completed works), and hence this is type 3 (change in quantities and rates). For these new works, define the scope - in items - and for each item put the rate. For the items that have a rate in BoQ, use it, and for the new items, establish a new rate and substantiate it. Hope that concludes the case. Note: “the completed works can be claimed under the original contract, and the modification will be claimed separately under the VO”.
It depends on what has been agreed in the contract. Some times it is agreed that if materials price increased more than a pre-agreed percentage then it becomes variation
Hi! Could you post a video about calculating costs in Gypsum works as there’s many different materials and the labour costs increases per m2 if it’s 2 layer or 3 layer boards
Thanks for the informative and detailed explanation.
I have a question, when we are estimating for a project Tender, in which document states the priority of documents?
And what if the priority of documents are not stated. Could you please clarify?
It will be a part of conditions of contract
You might need to refer to some standard form of contract like FIDIC.
You are indeed a good teacher
Thank you 😊
From Nigeria
Thanks for the informative and detailed explanation ❤
Thanks a lot for watching. All love ❤️
Thank u
بارك الله فيك و بعلمك يا مهندس معلومات قيمة جداً ❤❤❤
Thanks a lot for watching and support ❤️
Thanks for the information and explanation.
Thank you for watching and commenting 😊
Thanks.
Could you please differentiate among Claim, Variation and change with example.?
Thank you 😊. I’ll do my best
Thank you sir❤
Thank you for watching 😊
Masha Allah, and thanks for deep knowledge
Thanks for watching comment ❤️
Very useful insight. Kindly upload more such informative videos
Thank you for watching. Sure I will
Hello Ahmed, thanks for the awesome video, I just a question if the works are just a quantity addition, but the change is to affect works already complete (eg move a team down three levels cut into a wall to adjust pipes) how will the price be calculated as this task if more difficult than the SOR suggest? thank you for your time.
Thanks for watching. Regarding your question, I believe the case you discussed is an additional scope that is not part of the contract (modification of existing / completed works), and hence this is type 3 (change in quantities and rates). For these new works, define the scope - in items - and for each item put the rate. For the items that have a rate in BoQ, use it, and for the new items, establish a new rate and substantiate it. Hope that concludes the case. Note: “the completed works can be claimed under the original contract, and the modification will be claimed separately under the VO”.
Thankyou you Sir
Jazakallah khair
Thank you 😊
Good evening, Sir.
I would like to know if we can classify the increase in price of material during the cost of the project as a variation?
It depends on what has been agreed in the contract. Some times it is agreed that if materials price increased more than a pre-agreed percentage then it becomes variation
Hi! Could you post a video about calculating costs in Gypsum works as there’s many different materials and the labour costs increases per m2 if it’s 2 layer or 3 layer boards
Thank you for reaching out. I’ll try to plan for it in the upcoming videos
Thanks. Mostly, we use wood for our buildings, so do you have a course that is related to wood estimation ..
Thank you 🙏. My experience is mostly in RC structures 🥹
Thank you
Jazakallah haira ❤❤❤
Thank you ❤
Hi manager
Am Mr Johnson.
Thx
Nice meeting you 😊
How we can do the omissions
Contract quantity is a number and revised quantity is zero. The net will be in minus ☺️
PLE POST MORE USEFUL VIDEOS SIR
I will try my best.
LIKE YOU WE DON'T GET EVERY WHERE
I WOULD LIKE TO MAKE VIDEO FROM CONTRACT DOCUMENTS.
Thanks a lot ❤️. Sure, will try my best 😊
❤❤❤
😊