Please Like and Subscribe to this channel. Click the bell for notifications. Needed support can be given at this link: www.paypal.com/donate/?hosted_button_id=2BRVFKB9ER6A4
Thanks Brad for the Christmas Eve video! Merry Christmas everyone! Tunnel: @ 5:28 I feel bad for the guys who have to work today. New Megapack site: @ 8:47 (Right) Two steel beams temporarily supporting the duct-banks to the Cathode Building/Die Shop, while concrete stormwater pipe sections are inserted under them. @ 8:57 Screw piles down the middle trimmed to the correct height. Two more stacks of piles, bottom right. Speculation subject to change depending on what we see in the next few days.... The screw piles down the middle may be to support a medium voltage bus structure. Mega-vault: @ 9:42 (Behind the vault, under the fence) Appears to be 8 conduits/cable ducts in the new duct-bank being constructed. Same the ones to the west.
The fans are running at the new computer cooler & they're working on the Cybertunnel exit. Other than that it's pretty empty. Have a Great Christmas, Brad !
Please Like and Subscribe to this channel. Click the bell for notifications.
Needed support can be given at this link: www.paypal.com/donate/?hosted_button_id=2BRVFKB9ER6A4
Brad, Merry Christmas and many thanks for your ongoing efforts to keep us all informed of progress in Texas.
Thanks Brad for the Christmas Eve video! Merry Christmas everyone!
Tunnel:
@ 5:28 I feel bad for the guys who have to work today.
New Megapack site:
@ 8:47 (Right) Two steel beams temporarily supporting the duct-banks to the Cathode Building/Die Shop, while concrete stormwater pipe sections are inserted under them.
@ 8:57 Screw piles down the middle trimmed to the correct height. Two more stacks of piles, bottom right.
Speculation subject to change depending on what we see in the next few days....
The screw piles down the middle may be to support a medium voltage bus structure.
Mega-vault:
@ 9:42 (Behind the vault, under the fence) Appears to be 8 conduits/cable ducts in the new duct-bank being constructed. Same the ones to the west.
Thank you, Brad.
Thanks Brad
The fans are running at the new computer cooler & they're working on the Cybertunnel exit. Other than that it's pretty empty. Have a Great Christmas, Brad !
Really need to build a seawall along that creek,because without it River will expand/widen,even flood if not dredged
Merci👍👍
Cheers mate. Imagine it will be relatively quiet until start of 2025?
No scooters lol
That is one ugly river.
Here alone on Christmas