Project Management: Crashing a Project

Поділитися
Вставка
  • Опубліковано 29 лис 2024

КОМЕНТАРІ • 81

  • @brittanykoskie9361
    @brittanykoskie9361 10 місяців тому +9

    This went hand in hand with a homework problem I was struggling with. Thank you for your detailed explanation!

  • @zakiapayab7240
    @zakiapayab7240 10 місяців тому +4

    I just watched this well explained video. Step by step solution to the end was very interesting.

  • @et4918
    @et4918 Рік тому +6

    Thanks I cearly understand how to crashing a project. In fact, I think you teach better than my school's professer even English is not my mother tongue haha. Well teaching !!!!!

  • @cerenaltntas4546
    @cerenaltntas4546 10 місяців тому +2

    Helal olsun kardeşim sana sayende dersi gecicem

  • @ranjanghosh4321
    @ranjanghosh4321 Рік тому

    Its very well defined. One question. While crashing you need to prioritise by longest path first, 4:50 but after that we need to prioritise either the burst/merge node or simple node. Here answer would be same but still for other problems it may differ.

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому +1

      Yes, depending on the problem and parameters there can be more than one combination of crashing activities

  • @OrganicAlumination
    @OrganicAlumination Рік тому +2

    I really need this because online classes and these charts and the DNA strand map .... I hate how lost I can be.

  • @adityabagayatkar1947
    @adityabagayatkar1947 7 місяців тому +1

    Thank you for the explanation. Just One question. Why don't we crash A and E further ? we only consider A and E's crash week as 1

    • @The_Business_Doctor
      @The_Business_Doctor  5 місяців тому

      A can be crashed by only 1 week (from 4 to 3). After that, there are two critical paths, so even if you crash E, you can't crash the path with A any more so you would be wasting your money to crash E.

  • @SearaboKgekoane
    @SearaboKgekoane Рік тому +1

    Well explained, thank you

  • @SystemsProjectEngineer
    @SystemsProjectEngineer 2 роки тому +2

    Very well done.

    • @The_Business_Doctor
      @The_Business_Doctor  2 роки тому +1

      Thank you! If you haven’t already, please consider subscribing!

  • @sphesihlepaya4848
    @sphesihlepaya4848 Місяць тому

    Hi, whilst you made a mistake on crash cost per week on B. Does it affect things? since you wrote 400 instead of 600

    • @The_Business_Doctor
      @The_Business_Doctor  29 днів тому

      I did make a mistake there and the crash cost of B should be $600 instead of $400 but it doesn’t affect the final solution since B never gets crashed.
      Thanks for pointing out the error and hope this helps.

  • @HamzaScuderia
    @HamzaScuderia 10 місяців тому

    Hi,
    if there was a scenario that at the end of crashing A-D-G and B-E-G paths (where both = 9 weeks) were you to find that the C-F path also contains 9 weeks (in which case all 3 paths are now critical paths), how would you go about it? Will you now reduce F as well as reduce E (from the B-E-G path) or is that not possible? Thanks

    • @The_Business_Doctor
      @The_Business_Doctor  10 місяців тому

      If the critical paths are all 9 weeks, if you had the ability to crash activities you would have to crash an activity on EACH path so they all get reduced. You can’t crash F by one week (making C-F 8 weeks) and leave ADG and BEG at 9 weeks. The challenge is to be able to balance all of the critical paths.
      Hope this helps.

  • @outofshadows2598
    @outofshadows2598 2 роки тому +1

    Very well explained

  • @lokmanhakim8576
    @lokmanhakim8576 6 місяців тому

    Hi sir, may i ask - how do we get the Crash Time Values (in column 2) ?
    Also must the Duration Unit be standardized to weeks? or can it be any other time unit (i.e. man-days)?

    • @The_Business_Doctor
      @The_Business_Doctor  5 місяців тому +1

      Hi there. The crash time values are provided, so there are no calculations required. You can use any unit you like: days, weeks, months, etc..
      Hope this helps.
      Mark

  • @damadumdum
    @damadumdum Місяць тому

    so when finding the fastest duration, we stop crashing when the critical path has been fully crashed?

    • @The_Business_Doctor
      @The_Business_Doctor  Місяць тому

      I’m not sure what you mean by the “fastest duration”. Perhaps you mean the shortest possible time and that would be determined when you have crashed all paths and you might end up with more than one critical path. When you have multiple critical paths a you must be able to crash each by the same time to keep crashing to get to the shortest possible or project completion time (duration).

  • @yeesenghoo6711
    @yeesenghoo6711 10 місяців тому

    Why activity A and activity E can only reduced by 1 weeks, but both activities have crash time limits up to 3 weeks

    • @The_Business_Doctor
      @The_Business_Doctor  10 місяців тому

      Just because an activity can continue to be crashed doesn’t make it should be because there can be other critical paths that have to be balanced so continuing to crash A and E won’t reduce the project time any further. You must carefully observe when other paths become critical and then try to crash activities line on all the path risk or find activities on each path that can be crashed by the same time to keep the path times balanced.

    • @tinotendakanyemba7948
      @tinotendakanyemba7948 7 місяців тому

      Hello Sir, So do you mean that every time we crash separate activities when we have 2 critical paths like we did for E and A we just crash once for both because in this case we had crash time limit of 3 weeks which we could do for both A and E to leave us with 7 not 9 weeks but we just crashed 1 week not 3

  • @user-dp2ln7yv3z
    @user-dp2ln7yv3z Рік тому +1

    When crashing G, if the max crash for G is 2 weeks, why aren’t we subtracting 1 week from each critical path to get a 11 week critical path?

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому +4

      Hi there. If you go to 8:20 in the video, you can see that G is crashed by 2 weeks getting down to 10 weeks. If you're asking why it wasn't crashed earlier, that's because D was less expensive.
      Hope this helps.
      Mark

  • @maramben4618
    @maramben4618 2 роки тому +1

    why can't we crash more of B and E I don't clearly understand the reason ?

    • @The_Business_Doctor
      @The_Business_Doctor  2 роки тому +2

      Hi Maram,
      If you look at the summary at around 10:00 in the video, you'll see that after crashing to 7 weeks, both paths A-D-G and B-E-G are critical at 9 weeks. While you could spend money to crash B and E and get below 9 weeks you would be wasting the money because you cannot crash any more on A-D-G so it would still be 9 weeks. At this point you have more than one critical path and to be able to continue crashing, you must be able to crash activities on both paths otherwise you cannot proceed.
      Hope this helps.
      Mark

  • @SS-pn7ss
    @SS-pn7ss 8 місяців тому +1

    Thank you so much

  • @kennethkayeramos2858
    @kennethkayeramos2858 Рік тому

    Hello sir. I have a question, the difference between normal time and crash time is the counts of crash?

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому

      Yes. If the normal time is 10 days and the crash time is 8 days then the activity can be crashed by 2 days

  • @FABRlCE
    @FABRlCE Рік тому

    column 6, 2nd difference is incorrect though, right?

    • @The_Business_Doctor
      @The_Business_Doctor  11 місяців тому

      Hi there. Yes there is a typo there. Someone else had noted that before in a previous post which I confirmed. It doesn’t change the answer, however.

    • @FABRlCE
      @FABRlCE 11 місяців тому +1

      @@The_Business_Doctor super 💯

  • @serenitytercias2012
    @serenitytercias2012 2 місяці тому

    hi what if you are not provided normal cost

    • @The_Business_Doctor
      @The_Business_Doctor  2 місяці тому

      Hi there,
      Well if you don’t know the normal cost you have to then be told the incremental cost to crash otherwise you can’t solve the problem.
      Hope this helps.
      Mark

  • @noorasilahizatie4979
    @noorasilahizatie4979 Рік тому

    Hello sir, one question. When you crash E by 1 week, why you also minus the ADG path because theres no E in that path.

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому +1

      Hi there. At some point you can end up with more than one critical path, so when you crash A, that reduced the time along A-D-G, but then B-E-G must also be reduced. You might be thinking of the part in the video where just before I take the time of B-E-G I took 1 off A-D-G -- that's because I missed updating my little crash table. Hope this helps.
      Mark

  • @AmirB-yc3yp
    @AmirB-yc3yp 11 місяців тому

    hi may i know the textbook you refer for the exercise. thanks!

    • @The_Business_Doctor
      @The_Business_Doctor  11 місяців тому

      Hi there,
      The textbook for that one is:
      Operations Management: Sustainability and Supply Chain Management, Third Canadian Edition by Hweizer, Render, Munson, and Griffin ISBN 978-0-13-483807-6
      Hope this helps.
      Mark

  • @na50r24
    @na50r24 11 місяців тому

    Wait a second:
    4:05
    The critical path is ADG?
    But you only did the forward pass, didn't you? Is that sufficient enough to determine the critical path?
    What about the backward pass?

    • @The_Business_Doctor
      @The_Business_Doctor  11 місяців тому +2

      You only need to do a forward pass as long as you go through all the paths. The longest path is the critical path. You really only need to the the backward pass to determine what the slack for an activity is. All activities in the critical path will have zero slack but the other ones need the backward pass to determine the slack.
      Hope this helps!

  • @tehdavidshow
    @tehdavidshow Рік тому

    I have an example from my homework that is throwing me off. For activity D, the normal duration is 1 (day) and the crash is 3 (days). if I take the crash and subtract the normal duration I get -2 which doesn't seem right. Any advice on how to do that properly? All the rest of the activities have the crash duration smaller than the normal duration.

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому

      Hi David,
      Well that is an interesting one. I suspect it might be a typo. I suggest you confirm with your instructor on that one.
      Mark

  • @joudham
    @joudham Рік тому

    why are the last two crashings for A and E considered 1 week together?

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому

      Hi Joud. This is because at some point there is more than 1 critical path and to reduce the time by one week either 1 task that is common to both paths must be crashed or 1 task on each path must be crashed. In this case if you crashes A only that path would be reduced by one week but the path E is on will not.
      Hope this helps
      Mark

    • @kathestrella-ju8bc
      @kathestrella-ju8bc Рік тому

      @@The_Business_Doctor why isn't E multiplied by 3 weeks?

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому

      @@kathestrella-ju8bc If you crash E by more than 1 week without crashing another activity an a different path, you would be wasting your money because the project time will not be reduced. Hope this helps.

  • @olo1135
    @olo1135 Рік тому

    why we stop at 7 weeks and why did not go further why dont you tried to reduce E or B more

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому

      Hi Olo,
      You can't go any further because the remaining activities that could still be crashed are not on the critical path. So you COULD pay money to complete them in a shorter time period, but it won't reduce the total project time, so you would be wasting your money. A valid reason for paying extra to free up the resources to complete those activities earlier might be to allocate the resources to another project.
      Hope this helps.
      Mark

  • @sanajan8491
    @sanajan8491 9 місяців тому

    Why are we crashing D by just 1 week when we can crash it by 4 weeks?

    • @The_Business_Doctor
      @The_Business_Doctor  9 місяців тому

      If you crash D the project time will not be reduced because at least one other path is still critical. You have to crash activities on each critical path by the same amount for the project time to reduce. We try to crash activities that are common to multiple critical paths to save crash cost but that’s not always possible.

  • @yunggoth8505
    @yunggoth8505 2 роки тому +1

    Could you tell me the name of the book please?

    • @The_Business_Doctor
      @The_Business_Doctor  2 роки тому +2

      The textbook for that course was Heizer, J., Render, B., Munson, C., & Griffin, P. (2020) Operations Management (3rd Canadian edition)

  • @jyotinegi7413
    @jyotinegi7413 2 роки тому

    when crashing a project do we have to concentrate on task with least expensive gradient or path with least slack?

    • @The_Business_Doctor
      @The_Business_Doctor  2 роки тому +5

      Hello Jyoti,
      You have be very careful with crashing. You would concentrate on the lest expensive crash cost that is ON the critical path (i.e. The path with zero slack). As you crash activities, the critical paths will change (you might end up with multiple critical paths) and you might have to move to a different path to find the next viable activity to crash. Ideally, you can crash a single activity that is on multiple critical paths.
      Crashing an activity just because it is the least expensive but isn't on the critical path is a waste of money because it won't reduce the project completion time.
      Hope this helps.
      Mark

  • @joeyanneitorralba5861
    @joeyanneitorralba5861 Рік тому

    Hi! I would like some help in a project management problem. Can i send it via email?

  • @riskaoktaviani1816
    @riskaoktaviani1816 Рік тому

    i think max crash is 8 weeks not 7 weeks
    because total max crash is $1600

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому

      Hi Riska, the maximum this project can be crashed is by 7 weeks to end up at a 9 week project time. The solution is correct.
      Mark

    • @PoeEdogawa
      @PoeEdogawa 8 місяців тому

      @@The_Business_Doctor Hello sir, can you explain why (in detail)? I'm so sorry, I'm still a little bit confused. Thank you in advance

  • @zain4494
    @zain4494 2 роки тому

    thanks bro

    • @The_Business_Doctor
      @The_Business_Doctor  2 роки тому

      You're welcome, Zain! If you like the videos, please consider subscribing!

  • @moyou5405
    @moyou5405 7 місяців тому

    I still think your speed is way too fast

  • @aronkovacs9604
    @aronkovacs9604 Рік тому

    why the monkey bits is this called Crashing? :/

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому

      Good question! We'll have to ask the Project Management Gods about that one.

  • @sabelozondo7179
    @sabelozondo7179 2 роки тому

    Kindly drop your email, please. I need help with project management activities.

    • @The_Business_Doctor
      @The_Business_Doctor  2 роки тому +1

      Hi Sabelo, you are free to email me at mark@strategema.ca to let me know what you are looking for.