Operations Management: Project Management - Crashing III

Поділитися
Вставка
  • Опубліковано 30 вер 2024
  • This problem walk-though video will demonstrate how to crash a project after determining drawing the network diagram and determining the critical paths.
    NOTE:
    From 7:09 to 10:23 there is a typo in some of the columns relating to Path 3:
    The Blue Wave 1 column should read -1=19
    The Green Wave 2 column should read -2=17
    The Orange Wave column should read -1=16
    These were actually corrected at 10:24 going forward.
    Those typos do not change the final crash results and costs.

КОМЕНТАРІ • 11

  • @itsmedohh699
    @itsmedohh699 5 місяців тому +1

    Thank you so much for the brief explanation. I got one question: is it okay if me and my friend had different number of waves to solve this problem? some will solve in 4 waves, others in 6...etc. Do all the solutions have to be identical? knowing that end results are the same.

    • @The_Business_Doctor
      @The_Business_Doctor  5 місяців тому

      Glad you liked the video. No the solution doesn’t have to be identical. There are different ways to solve them but the end result is the same.

  • @tadibshadman4939
    @tadibshadman4939 Рік тому +1

    thank you so much. This one is more clear than the other one.

  • @shevinglasgow305
    @shevinglasgow305 Рік тому

    I think he made a mistake withb Path 3. Should it not be 20-1=19 weeks?

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому

      Hi Shevin,
      Yes, you are correct, there are some typos relating to that path and at 10:24 in the video they were corrected.
      From 7:09 to 10:23 there is a typo in some of the columns relating to Path 3:
      The Blue Wave 1 column should read -1=19
      The Green Wave 2 column should read -2=17
      The Orange Wave column should read -1=16
      These were actually corrected at 10:24 going forward.
      Those typos do not change the final crash results and costs.
      Thanks for pointing this out. I provided a note in the description of the video.
      Mark

  • @Journey_of_stroke
    @Journey_of_stroke 10 місяців тому

    Hey, what should be the answer of the following question-
    The activities involved in a certain project have been identified as follows:
    Job Time
    (weeks)
    No. of Men
    required
    Precedence
    requirements
    A 5 1 -
    B 10 1 A
    C 8 2 A
    D 6 3 B,C
    E 7 1 B,C
    F 4 2 E
    G 4 2 D,F
    H 2 1 G
    a. For the above project draw the network (using the MS word line function) and
    determine the critical path.
    b. If there are three men available at any one time how long would the project take
    and how would you allocate the men to the activities?
    c. If there are no restrictions on the amount of labour available, explain how you
    would schedule the activities?

    • @The_Business_Doctor
      @The_Business_Doctor  10 місяців тому

      Sorry but I don’t have the time to answer this question. Perhaps someone is willing to help you out

  • @alejguz1552
    @alejguz1552 Рік тому

    Good Job, can you make an example in which there`s a penalty if the project is not completed in ceratin day, or can I contact you so that you can help me with a problem similar please

    • @The_Business_Doctor
      @The_Business_Doctor  Рік тому

      Hi there,
      Sorry, but I'm quite busy and don't have the time to create a video for this. I create videos as I need them and post to share.
      I'm also not available for one-on-one help.
      To deal with a penalty, you would simply treat it as an additional cost, over and above the crash cost and should be added if, after crashing, you know how many penalty days there are.
      Hope this helps.
      Mark