Hello, thanks for your video. I have a question. I'm trying to use strategy 41 as said above. The problem that I 'm facing is that in sales order (va01) field RqTy is not appearing. Any idea on how can I make it appear ? Thanks again !
Pls verify if strategy is assigned to material in mrp 3 view and then sales order is created, also verify in sales order procurement tab if requirement type is selected correctly according to the strategy
Hi, I am also facing the same issue. I have assigned planning strategy 41 in material master then created sales order. But I don't find any requirement type field in procurement tab.
Or you could have just used strategy group 41, which is the same thing available in standard SAP.
Correct, my intention was to show how to make a custom strategy here example I could have taken as 10 and 20
Hi Sir can we consider both stock in this so assigned and Unrestricted stock on component level
If you want to use the unrestricted stock for component then pls use collective indicator 2 in mrp 4 view of the component
Hello, thanks for your video. I have a question. I'm trying to use strategy 41 as said above. The problem that I 'm facing is that in sales order (va01) field RqTy is not appearing. Any idea on how can I make it appear ? Thanks again !
Pls verify if strategy is assigned to material in mrp 3 view and then sales order is created, also verify in sales order procurement tab if requirement type is selected correctly according to the strategy
Hi, I am also facing the same issue.
I have assigned planning strategy 41 in material master then created sales order. But I don't find any requirement type field in procurement tab.
If material was with 20, it would have created just one order with pir reduced, right?
Strategy 20 is MTO and doesn’t align to reduce PIR, neither we can enter PIR for those materials
This tutorial is not for beginners.