PERT- Project Evaluation and Review Technique in hindi
Вставка
- Опубліковано 15 жов 2024
- This video explains project evaluation and review technique
The main objective in the analysis through PERT is to find out the completion for a particular event within specified date. The PERT approach takes into account the uncertainties.
The three time values are associated with each activity
1. Optimistic time - It is the shortest possible time in which the activity can be finished. It assumes that every thing goes very well. This is denoted by to.
2. Most likely time - It is the estimate of the normal time the activity would take. This
assumes normal delays. If a graph is plotted in the time of completion and the frequency of completion in that time period, then most likely time will represent the highest frequency of occurrence. This is denoted by tm.
3. Pessimistic time - It represents the longest time the activity could take if everything goes wrong. As in optimistic estimate, this value may be such that only one in hundred or one in twenty will take time longer than this value. This is denoted by tp
Follow on Instagram:
/ sandeepkumargour
Email :- sandeepkgour9@gmail.com
Facebook page :- / learnwithsandeepgour
........................................................
Operations Research(OR) |
Computer Oriented Optimization Techniques (COOT)|
For MCA, MBA, B.tech, B.E.,B.Sc.
CBSE UGC NET & Other Exams
#pert #project #review #technique #evaluation #management #optimistic #mostlikely #pessimistic
Thank you sir.I can't express my situation that you help me to overcome Allah bless you!
You are a saviour sir
May Allah bless you
amazing and easy way of explanation
Sir ap bht acha explain krte h... everything is clarified 🙏🏻🙏🏻🙏🏻🙏🏻
thax😊
Thanks a lot Sandeep Ji for this video. it's really helpful for the learner who is not from math's BG.
Thank you sir to explain it in a very easy language 🙏
Amazing thanku for this video it's a great help during exams
Hello Sir, Isme agar hum same sum ko AON pe karenge toh uska Diagram kaisa hoga ?? Please comment and explain
Nice explanation.... Whole things are given....
Sir, what if value of Et comes in decimal form?? Then should I calculate earliest start time & latest finish time with those decimal values only??
Please help me sir.. pls clear my doubt🙏🙏🙏
Explanation = Good
🖋️ = Excellent
Thanks a lot! Your explanation is very good.
thank you so much for appreciation..😊
Thanku so much sir 🥰 very easy way of explanation
Sir without table how can we calculate the probability???
Because in exam no table is provided 😢
Very well explained! Thanks a lot 😃😃😃
Thank You very much sir for this amazing content
😄😄😄😄
May God Bless you. You hVe helped me Alot
Thax,, keep watching my videos.
very nice sir... u r great... Thankyou so much for this😊
Hi Sir, Is there any tutorial video on Resource Allocation Problems ?
How I understand given time is optimistic, pessimistic or most likely time
Sir is there 2 types of table
Some books are adding 0.5 after finding value of (0.67) by table
By book's example value of 0.67 is 0.2514 & they add 0.5 in it
By your table value of 0.67 is 0.7486
But actual result is same as 0.5 + 0.2514 = 0.7514 closed to your result
Please clarify it
Btw thankyou for these videos❤️👑✨
it is because the table you are referring is showing only half (i.e., 50%) of the bell curve (i.e., values)
@@rajeevmehra5564 but sir that table is not helpful in case of percentage form questions
@@subaldogra3110 IM facing the same problem
Thank u sir
Watching from pakistan
wow super friends very useful your methods is easy thanks
Sir, hamare civil eng objective mein 2 se 3 q aate hain koi short video objective ko dhyan mein rakhkar bana do. Please
will those values be given in exam paper ? ( P for Z or Z for P )
either given in exam paper or you may ask to invigilator in exam room.
Bahut badhiyaa bhai... really liked alot
you are a life saver sir
Sir, need to know how can we calculate Probability if the time scenario given in the question is less than 35 days and more than 35 days for one set of activities.
If you know please reply me
sir how can i get those table values can u please tell us
sir agar z ki value -(minus) mai ayi to
You made this very easy.Thank you for such a good explaination👏
Thank you Sir for your valuable ✨ explanation and crystal 🔮 clear concept 📚 conveyance. It really helped me alot 😃.
#KEEPUPTHEGOODWORK !!!
Extraordinary, excellent
Thank you😊
Sir OR ki konsi book aap use krte h..jisse Acche se concept milte ho ar jaha me questions bhi practice or pau
1. S.D. Sharma ( esme LPP achche se dya hua h)
2. Gupta and Dhira
THAX☺️
Sir u r great teacher
Thank you so much😊
Hi Sandeep, Thanks for the video it helped me a lot. I live in London, Canada and doing project management. I want to know why did you write Z= p(x >or= 19) in between? what dose that mean? Thanks in advance.
x is variable on which we calculate probability.
fekne ki bhi hdd hoti h bhai.. london uk mei h na ki Canada mei
@@Anonymous-ho1mt your comment shows how stupid and ignorant you are. google it before you become so rude.
@@SandeepKumarGour got it . Thanks
@@Anonymous-ho1mt badhe bai London Canada me b h
Wonderful explanation ❤
Best way of teaching
Thank you☺️
Keep watching ..
Sir Ye Value kaise Find karege My Mcom is on 21 december plzz help me sir Plzzz I dont understand that plzz help me sir
Ye same question mere university exam aya . Thank u sir ji
welcome,,
@@SandeepKumarGour excuse me sir! yh AON diagram bnai h apny? q k activiy ko node k andr likha h
Sir ji is lecture me jo apne probability ki book batai hai vo mere pass nhi hai Toh mai kaise probability find out karu
Calculator nahi hai ?
@@idris110 how to solve with calculator
can someone plz provide me with the table which is used in the video?
Thank you sir!
Can you please provide the picture of both probability tables
Send your email id
thank you sir you are great...
bahut khuub sir
Amazing 👍
Hello sir kindly upload the book name in which z table value is accurately given according to values other pattern to find z value is time consuming
Operation research by gupta and hira, you may download the table from Google also
Sir can you keep the information of the book you followed for the table reference regarding probability
references books
1. Operation research by SD Sharma
2. Operation research by Gupta & Hira
Thankuuu so mch sirr❤❤❤
Sir can u pls give the table from where u r seeking probabilities
Provide your email id
very easy explained 😊🙏
Awesome👍👏.. Vedio
this kind of teacher i praise alot, kuch b faltu ki bakaiti nahi point to point padhao aur jau, na choti choti baatein smjhane me time waste karna, your method of teaching is very very awful sir, really really like your video
Thank you so much😊
Sir agar 0.9 ke hisab se dekhe to value nai mil rha h
0.8159 value h
Thank you so much sir🙏
Sir exam me table dete hai ya nai?
Aap exam me table le kr jana, or invigilator se permission le lena, agr exam centre pr hogi to wo bhi provide kr skte h
Sir, koi Indian authors wala statistics kitab suggest kijay please?
aap abhi kon si book se study kr rhe h
@@SandeepKumarGour
Sir, basically main West Bengal se hu. Yahan economics bahut tough hai, statistics k liye main N.G.Das ye ISI Kolkata ke professor hein and Gupta and Kapoor ko follow karta hu.
Well Explained Sir!
Thanks sir 👌👍
Wow amazing tnx
But S.d should be 5
where can i get the table u have used in the video??
Easily from Google
@@SandeepKumarGour I cannot find it. The table which u have used for last qn (percentage one) its not there in Google maybe
@@SandeepKumarGour please send me as soon as possiblee
Provide your email
@@SandeepKumarGour I had sent u my Gmail yesterday but unfortunately it wasn't sent or idk what happened
Thanks sir
Why you drew AON and not AOA in this Question ?
We can draw any one.
Sir plz recommend book for this
1. Operation research by S.D. SHARMA
2. operation research by GUPTA & HIRA
@@SandeepKumarGour sir where fromi i get and i have also two parts in this questions
Thank you sir
Very nice
Ye konse stream ka subject hein?
Ye " operational research " or " computer optimization techniques" subject h, ye alg alg universities me BCA, BCOM, MCOM, MSC, MCA, me rahta h
@@SandeepKumarGour samajh gaya sir
Amazing
Thank you sir
How to draw AON for this question?
watch the video..it will help you..
thax😊
ua-cam.com/video/cOG1QsgW9js/v-deo.html
7:36 divide by 6 kyu Kiya like 6 activity thi isiliye...?
Formula h
Samjha nai sir ki aap value kaise nikal rhe h
Very Good
पढ़ाने का तरीका अच्छा है
धन्यवाद।। 😊
Thankyou!!!
Thanks sir,
🙏🙏🙏
thank you so much sir.
welcome😊
Sir can I have table Link please
Can you please share it through your drive please
Provide your email, I will send to you.
Sir mai aapki two person zero sum game video nahi dekh pa ra hu plz mjjhe link send kr dijiye
Sorry brother, abhi es topic pr video upload nhi kr paya hu, koshish kruga k jldi hi upload kr du.
Thank you for your support☺️
@@SandeepKumarGour please sir jaldi hi upload kijiye mera exam hai 8 may ko
@@SandeepKumarGour sir aap bhut achha pdate hai bhut hi jayeda good job sir thank you very much
Table ki book ka namm ky hai
Nice video sir
Thax☺️
Thank u sir
Thank you
Welcome
I need some help
How we calculate Start end (E) or finish end (L) in pert method?
Watch the following video
ua-cam.com/video/kcI3KG5kn1Q/v-deo.html
@@SandeepKumarGour sir what if expected time comes greater than. Given completion time .toh z ki value kaise nikalenge. Bcz wo toh minus me aajaega(x-meu)÷sigma ...pls explain how will it come then.
Solid
Name of tp?, your voice isn't clear in the vedio
pessimistic time(tp)
@@SandeepKumarGour thanks for the fast reply sir..!
Nice
But u don't show full calculation.
Thanks
welcome and keep watching
Formula to find tp tm and to
Mean value is 34.16 days
Normal table : www.math.arizona.edu/~rsims/ma464/standardnormaltable.pdf
You can listen to the crickets in background
Good morning sar
Gud mrng
Sir whatapp no dalo, doubt puchne h kuch
I watched it in 2x.
Plz give me solution sir
Sir apka number chahiye,,,, plz sir mujhe kuch bat karna hain,,,
Issi network diagram ko A-0-N se draw kr ke dikho