Critical Path Method in project management (CPM) [Hindi]

Поділитися
Вставка
  • Опубліковано 19 січ 2019
  • This video explains how to identify critical path in network diagram.
    Video contains :-
    1. Earliest occurrence time
    2. Latest allowable occurence time
    3. Earliest starting time
    4. Earliest finishing time
    5. Latest starting time
    6. Latest finishing time
    7. Forward pass computations
    8. Backward pass computations
    9. Float ( Total, Free, Independent, Interfering ) --- with reference to an activity.
    10. Slack --- with reference to an event.
    11. Critical event
    12. Critical activity
    (Subcritical Activity-- Activity having next higher float than the critical activity)
    (Supercritical Activity-- An activity having negative float is called supercritical activity)
    13. Critical path
    Email :- sandeepkgour9@gmail.com
    Facebook page :- / learnwithsandeepgour
    ........................................................
    Operations Research(OR) |
    Computer Oriented Optimization Techniques (COOT)|
    For MCA, MBA, B.tech, B.E.,B.Sc.,B.Com.,M.Com.,
    CBSE UGC NET & Other Exams
    #criticalpathmetod #cpm #float #criticalactivity #criticalevent #slack #earliesteventtime #latestallowabletime