PMBOK 6: Critical Path Method
Вставка
- Опубліковано 28 лип 2024
- This video talks about the most important Tool & Technique of the Develop Schedule-Critical Path Method.
✔️ Check-out our PMP Certification Program: bit.ly/314k5M4
Critical Path Method helps us in arranging the activities based on their dependency and visualization of those activities so that we can identify when the overall work is going to finish. The project comprises of many tasks, some of these can be done parallelly and some cannot be done parallelly. It is difficult to manage what can be done parallelly and what cannot be. Some mechanism is required to arrange activities based on dependencies, critical path method can help in this.
An example of four activities is taken in the video. All these activities are in Finish to Start Relationship (FS)
Here activity B & D can be done in parallel. Calculate Early Start, Early Finish & Late Start and Late Finish of all the activities. The goal of the project is figuring out when earliest the project can finish. A critical path is the longest path and characterized by zero total float on the critical path.
Use the formula Duration= EF - ES or LF - LS. In case of parallel activities, the early finish of Activity taking longer time is considered. What is Late Start & Late finish, keeping the end date of the project as Day 30, how late can the activity be started and how late can it be finished. LS and LF of last Activity are equal to its ES and EF. The float is the flexibility between LF and EF or LS and ES. In this example Activity B has the flexibility of 5 days without any impact on the overall project; the Critical Path here is ACD.
Critical paths may have positive,0, or negative total float depending on the constraints applied. Positive total float is caused when the backward pass is calculated from a schedule. Negative float analysis is a technique that helps to find possible accelerated ways of bringing a delayed schedule back on track.
Click on the link below to join our PMP online course to watch all the videos of PMBOK sixth edition
✔️ Check-out our PMP Certification Program: bit.ly/314k5M4
#PMP #iZenBridge #ProjectManagement #CriticalPathMethod
Sir, this is by far the best and simplest explanation! You are brilliant!
Glad it was helpful!, Saket does many trainings apart from PMP, he is the lead trainer for ICP-ACC, ICP-APM, ICP-BAF, SAFe, and many more. In case you need more details, please visit www.izenbridge.com/
I like the 'last man to finish eating' analogy in explaining the critical path. Great explanation, thank you
Glad it was helpful!
Hi Sir, today I had my PMP exam and had cleared it in my first attempt. I must say your videos helped me more than any other study materials.Your way of teaching and clearing the fundamentals made things easier for me while preparing for the exam. Wish you and your team all the success and please continue your good guidance.
Congratulations Krishnadas!! It is encouraging that you found value in our videos. Keep exploring iZenBridge UA-cam channel.
Great video. Helps me a lot to complete my project !
THANK YOU for simplifying this. I think it was very important for you to call out the misconception/confusion between the longest duration and the minimum project duration! Well done!
Glad it was helpful! You can explore complete PMP program here - www.izenbridge.com/pmp/online-course/\
It comes with end to end support.
Sir, you are simply the best. Thanks for amazing videos.
This was perfect! Great explanation and very entertaining! keep up the great work and Thank You for your help!!!!
Glad it helped!
Thank you very much! You explained the things so clearly!
Thanks for your kind words!!
I'm only 1/2 way through but am fully entertained and getting the lesson. Love the energy, and the eating example. We came together, we leave together, that's it (waving my hands like he did) LOL Thank you for making this!
Glad you enjoyed it! You can explore iZenBridge complete program here - www.izenbridge.com/pmp/online-course/
This is complete and comes with an end to end support.
very clear and concise explanation. Thanks!!!
Thanks, Muhammad for exploring and liking our PMP content. In continuation to it, you can also explore our video on Difference between Total Float & Free Float
ua-cam.com/video/n6YIXmUEoYA/v-deo.html
Really amazing ! Clearly explain on the topic. Thumb up for you.
Thanks for liking, Saket does many trainings apart from PMP, he is the lead trainer for ICP-ACC, ICP-APM, ICP-BAF, SAFe, and many more. In case you need more details, please visit www.izenbridge.com/
Great explanation !! Thank you!
Thanks Pramod for your kind words. Happy to know that you liked the video.
Wow this is so nicely explained. Really clear! Thank you!
Glad you enjoyed it!
You are amazing! I understand CRM very well now! Thank you so much!
Great to hear!
Thank you! Some of the other videos were going over to fast and not providing information so I finally got it after watching your video!! If I have other questions regarding other Project Management methods for my exam I'll look for more of your videos.
Thank you!! Kevahra for exploring and liking our content.
Good to know that our videos are helping you in your preparation.
To watch all the videos and complete program you can explore our online course here
www.izenbridge.com/pmp/online-course/
You can also explore our following blog on "How To Calculate Total & Free Float?"
www.izenbridge.com/blog/what-is-float-calculate-total-free-float/
Perfect explanation.
Thank you
Thank you !! Mohammed for exploring and liking our content. You can also explore our PMP content on "Earned Value Management"
ua-cam.com/video/MO6EOMd-CkA/v-deo.html
Thank you for the nice/clear explanation!
Gald you liked it!! To know more about Saket training programs, please visit - www.izenbridge.com/landing/youtube/Saket-Bansal/
Very well explained - thank you!
This is just great content. Have a nice day.
Thanks, Dirk van V for your kind words!! Keep exploring our channel for quality content.
Thank you so much. Very explicit training.
Glad it was helpful!
Excellent explanation, thanks a lot.
I am at 4:07 and could not stop my self from writing AWESOME for till now explanation....will go further..
Thanks, Prakash for your kind words!! Keep exploring.
I did the same too. This is by far the best example of critical path and cleared up my confusion just as he mentioned about longest path being earliest to finish project.
Very simple, clear and understandable explanation.. Keep it up!!
Glad you liked it!! Keep watching!! To know more iZenBridge PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
Have a test today and this might have just saved my semester!
Thank you for clear explanation
great
I've encountered the easiest explanation and my confusion is now gone and I'm at ease , I'll keep on practicing,thank you 🙏🏽🙏🏽🙏🏽🙏🏽May God bless you brother brother
Happy you found this useful.
thank you so much fir the clear explanations
Thank you!! Riva for exploring and liking our content.
You can also explore our following blog on "How To Calculate Total & Free Float?"
www.izenbridge.com/blog/what-is-float-calculate-total-free-float/
Really nice explanation. Very good
You are phenomenal my man!
Thanks for your kind words!! To know what all Saket coach, please visit- www.izenbridge.com/landing/youtube/Saket-Bansal/
sir.! Really very simple and lucid explanation for easy comprehension of this concept.! Wonderful
Thanks for liking
Best explanation of CPM in just 15 minutes!
Thanks for your kind words!! To know more about Saket training program, please visit - www.izenbridge.com/pmp/online-course/
thanks a lot . This was of great help
Thanks Ankeet, happy to know that you lied video. Keep watching them.
Sir gone thru many vedios and this one explains the concept the best. Wonderful example of dinner makes the understanding best.👍
So nice of you. We do have complete program on PMP preparation, you may want to check it out here :
www.izenbridge.com/pmp/online-course/
Very clear and perfect explanation.
Thank you!! Swapnil for exploring and liking our content.
In continuation, you can also watch the following video
"Difference between Total Float & Free Float"
ua-cam.com/video/n6YIXmUEoYA/v-deo.html
Awesome video - thank you for your time
Glad you enjoyed it! To know more about Saket training programs, please visit - www.izenbridge.com/landing/youtube/Saket-Bansal/
Brilliantly explained.
Thanks Omar for your kind words!! Keep exploring iZenBridge UA-cam Channel.
The best explanation so far!!
Glad it was helpful!
Fantastic explanation, especially the "shortest path" part
Glad it was helpful! To know more about PMP program please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support
Excellent explanation. I came here after i had some confusion reading PMBOK and all are clearly explained.
Glad it was helpful! To know more our PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
Brilliant and detailed explanation !
Glad it was helpful. To know more iZenBridge PMP program, please visit - www.izenbridge.com/
it is complete and comes with an end to end support.
Thank you, this was great and very simply.
Glad it was helpful!
really impressive way of teaching.
Thank you!! Shahab for exploring and liking our content.
You can also explore our following blog on "How To Calculate Total & Free Float?"
www.izenbridge.com/blog/what-is-float-calculate-total-free-float/
Best PMP teacher ever!!!
Great to hear! You can explore details of complete PMP program here - www.izenbridge.com/pmp/online-course/
Very useful Sir, you explained in simplest form possible, thank you
Glad you liked it !! we do have online PMP Support program in case you want to check it out : www.izenbridge.com/pmp/online-course/
Explained well.... thanks for the video
Glad it was helpful! Keep exploring iZenBridge UA-cam Channel.
Excellent explaination, Saket!
Glad you think so! To know more Saket training program please visit- www.izenbridge.com/landing/youtube/Saket-Bansal/
Thank you!
You are welcome.Keep exploring iZenBridge UA-cam Channel.
Very clear and perfect explanation... Thanks
Glad it was helpful! We do have complete program on PMP preparation, you may want to check it out here :
www.izenbridge.com/pmp/online-course/
wonderful teaching sir .. many thanks for such a simple explanation of CPM
You are most welcome
Very clear explanation!
Glad you liked it!! To know more Saket training programs, please visit - to know more about Saket training program please visit - www.izenbridge.com/landing/youtube/Saket-Bansal/
This was simple and superb !
Thank you.
Fantastic teaching!
Glad it was helpful! To know more iZenBridge PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support
Holy crap, this was excellent!
Thank you! Cheers! To know more about PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
Excellent explanation. Thank you for sharing.
Glad it was helpful!
Sir, you are doing God’s work! Thank you for this!
Thank you for your kind words
So well explained - thank you for sharing
Thank you.
very efficient and easy explanation. great job
Glad you liked it
Great explanation, cheers
Happy to know you liked it. To know more about complete PMP program, please visit -www.izenbridge.com/pmp/online-course/
good one, excellent narration.
Glad it was helpful. To know more iZenBridge PMP program, please visit - www.izenbridge.com/
it is complete and comes with an end to end support.
Good video... Helped me a lot
Thank you!! Ridhdhi for exploring and liking our content. In continuation, you can also explore the following video on "Funding Limit Reconciliation & S-Curve"
ua-cam.com/video/pPDkUS-Uvvw/v-deo.html
best explanation so far
Thanks for tour kind words!! Keep an eye to see more PMBOK6 videos, we publish them on regular basis.
Thanks friend!
Thank you!! Kevahra for exploring and liking our content.
You can also explore our following blog on "How To Calculate Total & Free Float?"
www.izenbridge.com/blog/what-is-float-calculate-total-free-float/
Brilliant presentation
Amazing explanation !!!
Glad you liked it!! Keep exploring!! To know more about iZenBridge PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
Thank you. Best explanation.
Glad it was helpful!
I really appreciate you. Thank you
Thank you
This was so helpful
thank you thank you thank you!!!!!!!
Thank you!! Arlene, for exploring and liking our content.
You can explore our complete content of PMP (Project Management Professional) Based on PMBOK6 here: www.izenbridge.com/pmp/online-course/
Thank you so much your such a good teacher
Glad you think so!
Very nice explanation. Thank you.
Glad you liked the video!! Keep exploring iZenBridge UA-cam Channel. To know more iZenBridge PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
You are just brilliant sir, You are a born teacher,
Thank you for your kind words
Wow ...great teaching !,,
Thanks for your kind words. Keep exploring iZenBridge UA-cam Channel. To know more iZenBridge PMP program, please visit - www.izenbridge.com/pmp/online-course/
You are really great its amazing you are gifted in your professional as I have been taught by the claimed PhD came out nil
Glad you liked video!! To know more about PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
you are awesome!!
Thanks Rajon, happy to know that you liked the video!!
Thankyou man, Indian men still better as a tutor then my lecturer
Glad you liked it. To know PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
Amazing best lesson Thank you
Glad it helped! You can also explore complete PMP program here - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
Excellent explanation, couldn;t be better
Glad you think so! To know what all Saket coach, please visit- www.izenbridge.com/landing/youtube/Saket-Bansal/
awesome .. nicely explained sir
Thanks for liking
Best explanation sir, love you
Thanks and welcome!! To know more Saket Bansal training programs, please visit - www.izenbridge.com/landing/youtube/Saket-Bansal/
Thank you so much
Thank you for watching.
excellent explanation
Thank you very clear
Thank you.
Sir you should really do a full PMP tutorial course here. You are amazingly talented in teaching. Thank you
Yes, Pratap we have. You can explore it here - www.izenbridge.com/pmp/online-course/
I concur! There's another video with this critical path example, but he was just rushing through the video. You're taking the time to example how each number comes into a block. Once I saw that I continued watching the video. Your explanation was very clear and concise. I hope you do teach a full video course.
Very nicely explained
Keep watching!! To know more about iZenBridge PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
Dear - Good explanation.
some confusion is cleared
Glad to hear that
v. helpfull thank you
Thank you !! Sayed, for exploring our content and liking our content. Good to know that our content was helpful to you.
In Continuation to it, you can explore our video as per PMBOK Guide sixth edition on "Earned Value Management"
ua-cam.com/video/MO6EOMd-CkA/v-deo.html
Easy explain. Like it
Thanks for liking
Very clear explanation. Thank you. Did not see a course for the CAPM on your site. Do you have any plans to offer such training?
Thank you !! El for exploring and liking our content.
We don't have an online course for CAPM, but the course content is the same for PMP and CAPM, you can consider enrolling to it.
www.izenbridge.com/pmp/online-course/
Very nice explanation👍👍👌
Thank you !! Ram for exploring and appreciating our content. You can also explore our PMP content on "Earned Value Management"
ua-cam.com/video/MO6EOMd-CkA/v-deo.html
Best explanation ever sir❤❤❤
Thanks Wajid for your kind words!! Keep exploring iZenBridge UA-cam Channel.
Sir.
Thank you 🏆. U are my hero.
So nice of you
Fantastic explanation
Glad you liked it!! keep exploring iZenBridge YoutTube Channel. To know more iZenBridge training programs, please visit - www.izenbridge.com/
Excellent explanation
Glad it was helpful!
Instead of 1 if you starts from Zero, that will be bit easier. Rest this is really informative and easy to learn..
Thanks for the feedback Vivek, to know more about Saket training courses, please visit- www.izenbridge.com/landing/youtube/Saket-Bansal/
Great Video Sir..
Thanks
Thanks a lot sir
Thank you! Cheers! To know more about PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
One of best
Thanks for your kind words Kamashah!!
Best and useful
Glad you liked it!! To know more about complete PMP program, please visit - www.izenbridge.com/pmp/online-course/
The best...
Thanks for tour kind words!! Keep an eye to see more PMBOK6 videos, we publish them on regular basis.
Super clear (Y)
Thank you !! Muanteal, for exploring and liking our content.
In Continuation to it, you can also explore our video as per PMBOK Guide sixth edition on "Earned Value Management"
ua-cam.com/video/MO6EOMd-CkA/v-deo.html
Best Lecture
Thanks for your kind words Sankar!! To know more about iZenBridge PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.