    In this video Thumb rules for labours in construction, labour productivity is explained. Approximate Labour ratio of various trades in building construction is also shown.
    In this video we will give you various thumb rules, labour productivity per day (8hours). These are general thumb rules, actual figures may vary according to the local conditions of the place where work is carried out. Hope you found it helpful.
    The first step to increase productivity in construction is to understand the thumb rules of labour productivity.
    Labour productivity in construction refers to how fast a project can be built, and how much it costs to build. These are critical factors that influence the cost and duration of any particular construction project. In this video I have explained some of the thumb rules for labour productivity i.e Labour production ratio's for various trades in building construction.
    For Thumb rules series previous videos Please click the link below
    Thumb rules in construction
    • Thumb Rules In Constru...
    Thumb rules for concrete, steel, RCC Work • Thumb rules for Concre...
    Thumb rules for shuttering works
    • Thumb Rules For Shutte...
    Please watch my other videos on my channel.
    / knowledgehubllt
    Please watch, like & share my videos.
    Don’t forget to subscribe my channel.
    Please join our Facebook Group
    / 472006393930839
    Also visit my Blog on
    civilersedge.blogspot.com/
    Follow me on:
    / mukundvvk
    / knowledgehubllt
    Knowledgehubllt?s=08
    t.me/KnowledgeHubllt
    #civil
    #civilengineering
    #civilknowledge
    #civilengineeringknowledge
    #kh
    #knowledgehubllt
    #knowledgehublltcivil
    #knowledgehubcivil
    #khcivil
    #khllt
    #khlltcivil
    Note- NOTE: ALL THE IMAGES/PICTURES SHOWN IN THE VIDEO BELONGS TO THE RESPECTED OWNERS AND NOT ME...
    I AM NOT THE OWNER OF ANY PICTURES SHOWED IN THE VIDEO
    ---------------------------------------------------------------------------------------------------------
    Copyright Disclaimer Under Section 107 of the Copyright Act 1976, allowance is made for "fair use" for purposes such as criticism, comment, news reporting, teaching, scholarship, and research. Fair use is a use permitted by copyright statute that might otherwise be infringing. Non-profit, educational or personal use tips the balance in the favor of fair use.

КОМЕНТАРІ • 48

  • @neerainbhandari1764
    @neerainbhandari1764 29 днів тому +1

    Very nice..... work oriented 🎉🎉🎉

  • @sinchannaik_0146
    @sinchannaik_0146 3 роки тому +1

    Informative👌👌

  • @amolkulkarni1112
    @amolkulkarni1112 3 роки тому +2

    Well done

  • @sunilmamaguli9921
    @sunilmamaguli9921 3 роки тому +3

    Amazed knowledge u have friend.God bless u for ur endless efforts.🙏🙌🙏🙌👍👍🌺🌹💐💐

  • @IYTUSER
    @IYTUSER 3 роки тому +3

    Great info

  • @tusharnaik6912
    @tusharnaik6912 3 роки тому +1

    Good.
    In depth analysis on labor 👍👍👍👍👍 prodivity

  • @kailashlohar8609
    @kailashlohar8609 3 роки тому +1

    Nice information 👌👍

  • @theprashant9707
    @theprashant9707 4 місяці тому +1

    Sir RCC work jese 4 lane flyover m scaffolding or steel Shuttering labour productivity including staging and steel bta dijiye please

  • @MadanSingh-un9ym
    @MadanSingh-un9ym Рік тому

    Project palaning construction video

  • @siddiqkhan914
    @siddiqkhan914 2 роки тому +1

    Thanks Sir for sharing your knowledge.
    Kindly let me know this thumb rules are from your experience or you refer to some standard also you not mention for electrical and plumbing works productivity.

    • @KnowledgeHubllt
      @KnowledgeHubllt  2 роки тому

      Thank you. Thumbrules I have mentioned are as per standard practice..I will post the video on Tumbrules for electrical & plumbing soon..

    • @siddiqkhan914
      @siddiqkhan914 2 роки тому +1

      @@KnowledgeHubllt Thank you sir for your reply. I will be waiting for you videos on electrical and plumbing thumb rules

    • @KnowledgeHubllt
      @KnowledgeHubllt  2 роки тому

      Ok sir

  • @ratanaher9115
    @ratanaher9115 Рік тому +1

    Please make video on Post tensioning slab

  • @ramanandayanad5221
    @ramanandayanad5221 Місяць тому +1

    How only 1.25 sqm work of 4.5" brick work can be done ie only comes to 13.45 sft it's too less productivity to be checked again please reply

  • @MadaraUchiha-vv6qf
    @MadaraUchiha-vv6qf 2 роки тому +1

    Sir im a new subscriber here..can you give me example Problem..using your thumb rule labor ratio..thanks😊

  • @sumitkchaudhari
    @sumitkchaudhari 2 роки тому +2

    Sir, I have doubt. For 200thk AAC blockwork productivity is more (10sqm) than compared to 100-150thk AAC blockwork masony. Not able to understand its logic. Kindly clarify.

    • @sumitkchaudhari
      @sumitkchaudhari 2 роки тому +1

      for 100-150 thk AAC blockwork, productivity is told as 8sqm

    • @KnowledgeHubllt
      @KnowledgeHubllt  2 роки тому

      For 100 mm thick blockwork binders Or patali beams are required after every 1m height...

  • @zeeshanaliquazi8606
    @zeeshanaliquazi8606 2 роки тому +1

    I observed that Bathroom flooring gives less productivity than room flooring, because of less work space, desired slope towards trap. 2) Painting work productivity taken very high..pls confirm...3) Waterproofing productivity taken very less..

  • @AmitRajput-tf6xs
    @AmitRajput-tf6xs Рік тому +1

    Sir agar 1 ton steel cutting and binding karwana ho to kitna Mason and labour lagega ek din me

  • @amalraj7466
    @amalraj7466 2 роки тому +1

    Sir , gulf construction labor productivity pls explain, their woman workers are not , pls rply

  • @devrajsinghmarwadi4679
    @devrajsinghmarwadi4679 2 роки тому +1

    सरिया fitter एंड कारपेंटर एक दिन में कितना productvity होता है ।
    Fitter कितना______ kg
    कारपेंटर _____sqm

    • @KnowledgeHubllt
      @KnowledgeHubllt  2 роки тому

      Already mentioned in video please watch full video

    • @devrajsinghmarwadi4679
      @devrajsinghmarwadi4679 2 роки тому +1

      @@KnowledgeHubllt sariya fitter+Helper = 200kg.
      Shuttering work- 5 sqm.
      Low nhi he. Work productivity.

    • @KnowledgeHubllt
      @KnowledgeHubllt  2 роки тому +1

      It is a standard labour productivity, which may change based on labour efficiency..

  • @surendrasingh-oh3qc
    @surendrasingh-oh3qc Рік тому +1

    sir concrete ki labour productivity nahi di.

  • @amalraj7466
    @amalraj7466 2 роки тому

    Sir , it is not do practically, I know I am civil field ,it is not possible for practically 😄

  • @rohidare
    @rohidare Рік тому +1

    Source of your presentation??

    • @KnowledgeHubllt
      @KnowledgeHubllt  Рік тому

      Practical

    • @rohidare
      @rohidare Рік тому

      @@KnowledgeHubllt ok.. But boss the fact is that no one in the market agrees to this information and contractor may incurr losses.
      Moreover, cpwd recommendations are somewhat contrasting from your figures..

    • @KnowledgeHubllt
      @KnowledgeHubllt  Рік тому

      It depends upon efficiency of workers. It may change as per efficiency of workers. Like skilled , semiskilled.... It's as per practical experience for reference. Theoretically it may be different.

  • @samncool1
    @samncool1 Рік тому

    Sound quality not good