PMP Exam Questions 2024 (June) and Answers Practice Session |PMP Exam Prep | PMP for Project Manager

Поділитися
Вставка
  • Опубліковано 18 січ 2025

КОМЕНТАРІ • 70

  • @PMPwithRay
    @PMPwithRay  7 місяців тому +1

    ✅ ✅ Join my monthly UA-cam Membership Community: ua-cam.com/channels/O9Q3cPY4dKabwGrZ9rJx5Q.htmljoin
    ►►► If you are preparing for the PMP Certification in 2024, join my FREE Webinar for PMP Exam Prep: event.webinarjam.com/channel/pmpwithray2024
    ►►► 10 Tips for PMP Exam in 2024 (FREE e-book): www.pmpwithray.com/pmp-certification-exam-study-guide-for-beginners

  • @nuhaaloud8757
    @nuhaaloud8757 6 місяців тому +1

    Loved ur analytics skills

    • @PMPwithRay
      @PMPwithRay  6 місяців тому

      Thank you for watching and commenting!

  • @ihabjalal9
    @ihabjalal9 6 місяців тому +1

    I like your way of teaching..you are fluent in English and wide explanation.

    • @PMPwithRay
      @PMPwithRay  6 місяців тому

      Glad to hear that! Thank you!

  • @nsundarsrinivas9
    @nsundarsrinivas9 6 місяців тому +1

    Hi Ray, I'm happy to share that I passed the exam yesterday with AT in two domains . Thanks for all the knowledge shared w.r.t exam preparation.

    • @PMPwithRay
      @PMPwithRay  6 місяців тому +1

      Fantastic! Keep it up!

  • @jay____l
    @jay____l 5 місяців тому +3

    For question 5, the problem statement doesn't say which part the project manager should address. The concern of the customer (stakeholder) or the discontent with team members. I chose B as a result of the team discontent. However, if we are ONLY going off of the fact that the customer 'thought' I guess C makes more sense, but still messed up wording imo.

    • @WillSada
      @WillSada 3 місяці тому

      I agree, refining the wording of this question would help clarify its intent, making it easier to choose the correct option.I

    • @jay____l
      @jay____l 3 місяці тому

      @@WillSadaCorrect, I hope on the PMP exam there aren't cases like this because nobody would know unless they had the mindset of whoever wrote that specific question.

    • @Hash-e6w
      @Hash-e6w 3 місяці тому

      C is the wrong answer. Change Management Plan is about how to incorporate changes not teaching customers what change can be requested.

  • @makarandvaze5091
    @makarandvaze5091 6 місяців тому +1

    Hi Ray, very happy to inform you that I have passed my PMP with AT/AT/AT in all three domains. Thank you so much for all your videos. They are very helpful.

    • @PMPwithRay
      @PMPwithRay  6 місяців тому

      Fantastic! Many congratulations and I wish you all the very best for your career ahead!

  • @sanjayhake6872
    @sanjayhake6872 Місяць тому +1

    4/5 😊

    • @PMPwithRay
      @PMPwithRay  Місяць тому

      Thank you for watching and commenting!

  • @engahmedsabry6663
    @engahmedsabry6663 5 місяців тому +1

    Many thanks for you
    I checked many channels for preparing of my pmp but really your videos are top ones

    • @PMPwithRay
      @PMPwithRay  5 місяців тому

      Thanks and welcome! All the best for your exam :)

  • @nijammohideen128
    @nijammohideen128 2 місяці тому

    3/5 ,it seems Need to work more. This video help me a lot to do the self analysis. Thank you Ray.

    • @PMPwithRay
      @PMPwithRay  2 місяці тому

      Thank you for participating and commenting!

  • @BrightOseiBadu-yf8di
    @BrightOseiBadu-yf8di 7 місяців тому +1

    Ray, on question 4, I think performing swot analysis will help identify the opportunities and threats with the tool.
    On the chosen answer of updating the business case, can it be updated in the middle of the project?

    • @krutarthengineer
      @krutarthengineer 5 місяців тому

      In the question, it is mentioned that AI based input is proven better than historic data. So the required analysis is already done. And the question is all about how will you incorporate this in your current project. So updating business case is an option. Also the question itself saying the Agile team so changes can be accepted in the middle of the project.

  • @Ankitjaiswal-hd7pv
    @Ankitjaiswal-hd7pv 7 місяців тому +1

    Hi sir. I am currently in customer service however I want to move to customer success manager roles. Do you have any idea how I can move to customer success. Which certification is required.

    • @PMPwithRay
      @PMPwithRay  7 місяців тому +1

      Go for quality improvement certifications such as Six Sigma, TQM etc. You can then show quality improvement projects in customer success domain.

  • @RD-HLX
    @RD-HLX 3 місяці тому

    Hi Ray, how is option A a correct option for Q1 as the option is DOR and not DOD?

    • @Hash-e6w
      @Hash-e6w 3 місяці тому

      It's also incorrect. This channel seems to be dubious in explanation and concepts. I'll stay away. DOR is to validate the readiness for work to be done.

  • @shewayegurmessa8780
    @shewayegurmessa8780 3 місяці тому

    On Question #4, do the team and the product owner have the authority to update the business case? Why would they update the business case, if so? The only valid reason for me to consider updating the business case is if the project is the initiation phase right now and we need to do alternative analysis between the two options.

  • @thrinay399
    @thrinay399 7 місяців тому +1

    I think there is a confusion in your second question. Project Scope statement would not include WBS and WBS dictionary. What you are referring to is Scope Baseline. Although option A which was chosen makes sense!

  • @giangiocan6453
    @giangiocan6453 2 місяці тому +1

    I have doubts on question 2 correct answer. The scope baseline = scope statement + WBS + WBS dictionary; Scope statement does not include WBS then. Then scope statement as per PMI definition i PART of scope management plant, so the contrary of what stated. In my opinion the correct answer is B. Scope Statement

    • @Naik1997
      @Naik1997 Місяць тому

      Even I am Confused on Question #2

  • @asrathor9514
    @asrathor9514 6 місяців тому

    Thank you Ray for your tutorials!! This was the one in which i scored all correct and happy to share that i have passed my PMP today with AT in all domains..Anyone looking to strengthen the concept..Ray is one of the best!!🙂

    • @PMPwithRay
      @PMPwithRay  6 місяців тому

      Thank you for watching and participating! Glad you like my contents! Cheers!

  • @Kar-info
    @Kar-info 7 місяців тому +1

    Got 5/5, These questions are really great. Most of the questions, I got it correct by eliminating the wrong options.

    • @PMPwithRay
      @PMPwithRay  7 місяців тому

      Many thanks for watching & participating!

  • @karnick6500
    @karnick6500 6 місяців тому +2

    Following your YT. Using your simulator. Excellent explanation for all Qand A. Not able to score 5/5. In this QA Q5 the question is talking abt the concern of the team members . In that case why not option B

    • @PMPwithRay
      @PMPwithRay  6 місяців тому

      Many thanks for participating & commenting!

    • @Hash-e6w
      @Hash-e6w 3 місяці тому

      I agree that B addresses the root cause of team disconnect. I was going to follow this channel but Question # 5 explanation has turned me away. B is also reviewing with the team. Just because C has a word "review" doesn't mean it's the "right" kind of review

  • @russ4u4love
    @russ4u4love 6 місяців тому

    Hey ray am so happy and delighted to say that I have achieved the PMP certification …. Although I didn’t take any courses from you to be honest , your videos have played some role in my achievement…
    Thanks lot you very much and keep up your good work….
    Note: if you have any platform where I can leave review please advise will be happy to do.

    • @PMPwithRay
      @PMPwithRay  6 місяців тому

      Congratulations on your success! And thank you for watching and commenting!

  • @prakharsharma9756
    @prakharsharma9756 7 місяців тому

    Very Helpful Session, still not convinced by the answer of 2nd question

  • @vikashkumarmishra7661
    @vikashkumarmishra7661 6 місяців тому

    Hi Ray..Thank you for valuable lessons. M please to share that I have got AT in all three domain. I took your Mock Test on Udemy and regular follower of your monthly Q&A session which help and improve my preparation. Takeaway-PM mindset is the key. Once again many thanks for all your work and efforts..😊

    • @PMPwithRay
      @PMPwithRay  6 місяців тому

      Great job! Glad you like them!
      Thank you for watching and commenting!

  • @nijammohideen128
    @nijammohideen128 2 місяці тому

    3/5 correct. Seems need to work more

    • @PMPwithRay
      @PMPwithRay  2 місяці тому

      No worries. Thank you for watching and participating!

  • @chefl.k282
    @chefl.k282 5 місяців тому

    The matter in question 5 is about team members and not about stakeholders

    • @ley-jn6938
      @ley-jn6938 3 місяці тому

      Thats what i tought ..i chose B instead of C ..but now im not sure

  • @alenkagoldberg8207
    @alenkagoldberg8207 5 місяців тому +1

    3/5 1st & 5th were difficult

    • @PMPwithRay
      @PMPwithRay  5 місяців тому

      Thank you for participating and commenting!

  • @thrinay399
    @thrinay399 7 місяців тому

    4/5, overlooked the second question and jumped directly to the answer which lead to wrongly guessing it!

    • @PMPwithRay
      @PMPwithRay  7 місяців тому

      No worries, keep up the spirit! Thank you for participating and commenting!

  • @saeedfakhr1773
    @saeedfakhr1773 5 місяців тому

    4.5

    • @PMPwithRay
      @PMPwithRay  5 місяців тому

      Thank you for watching and participating!

  • @saman71rv
    @saman71rv 2 місяці тому

    Q2. is debatebale.

    • @PMPwithRay
      @PMPwithRay  2 місяці тому

      Thank you for participating and commenting!

  • @user-LuNga1939
    @user-LuNga1939 7 місяців тому

    4/5

    • @PMPwithRay
      @PMPwithRay  7 місяців тому

      Thank you for participating and commenting!

  • @angeliajohnson3168
    @angeliajohnson3168 7 місяців тому

    2/5

    • @PMPwithRay
      @PMPwithRay  7 місяців тому

      Thank you for participating and commenting!

  • @janisohil1628
    @janisohil1628 2 місяці тому

    Que.5:
    Ans C. is wrong !
    - Why to review with "all" stakeholders adhering ? Where the discontent within team members only!
    Ans. B would be correct where meeting with team for best value option "analysis" only, not implementing!

    • @PMPwithRay
      @PMPwithRay  2 місяці тому

      Thank you for watching and commenting!!

  • @chefl.k282
    @chefl.k282 5 місяців тому

    The second answer I don't agree with

  • @shivaninimbran5508
    @shivaninimbran5508 7 місяців тому +1

    2/5

    • @PMPwithRay
      @PMPwithRay  7 місяців тому

      Thank you for participating! Keep practising!

  • @shivajipatil8617
    @shivajipatil8617 6 місяців тому

    4/5

    • @PMPwithRay
      @PMPwithRay  6 місяців тому

      Thank you for participating and commenting!

  • @surajsinghnaruka3441
    @surajsinghnaruka3441 5 місяців тому

    3/5

    • @PMPwithRay
      @PMPwithRay  5 місяців тому

      Thank you for participating and commenting!

  • @sidharthaparida9016
    @sidharthaparida9016 7 днів тому

    4/5

    • @PMPwithRay
      @PMPwithRay  3 дні тому

      Thank you for participating and commenting!