PMP Exam Questions 2024 (March) and Answers Practice Session| PMP Exam Prep |PMP for Project Manager

Поділитися
Вставка
  • Опубліковано 31 гру 2024

КОМЕНТАРІ • 90

  • @LetsThinkAgainn
    @LetsThinkAgainn 9 місяців тому +7

    Hi Ray thank you so much for making all these videos and giving such an important knowledge. Ive passed my PMP exam in first attempt on 24th March 2024. Your content has been so invaluable. Thank you. I have already recommended your channel to so many people within my network.

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Thanks for watching and commenting!

    • @rebeccapatterson9125
      @rebeccapatterson9125 8 місяців тому

      Congratulations! I’m preparing for my boot camp training next week. Did you complete the exam in person or online?

    • @LetsThinkAgainn
      @LetsThinkAgainn 8 місяців тому

      @@rebeccapatterson9125 online.

  • @giangiocan6453
    @giangiocan6453 Місяць тому +1

    Question 4. The question states that some KEY requirements impact the legislation, so even performing a MVP these elements most probably will not be eliminated from the features. It results impractical.

    • @PMPwithRay
      @PMPwithRay  Місяць тому

      Thank you for watching and commenting!

  • @KaushikGhoshPrivate
    @KaushikGhoshPrivate 6 місяців тому +1

    5/5. Thank you Ray!!!

    • @PMPwithRay
      @PMPwithRay  5 місяців тому

      Thank you for participating and commenting!

  • @anilvadapalli
    @anilvadapalli 4 місяці тому

    5/5. Thank you Ray.! boosted confidence

  • @wasjustjoeking
    @wasjustjoeking 6 місяців тому

    4/5, Have my exam in a week! These questions were tough. Thanks for covering some tough questions, really helps nail down the mindset

    • @PMPwithRay
      @PMPwithRay  6 місяців тому

      Great job! Keep it up! Thank you for watching and participating!

  • @temitopeojiebun1390
    @temitopeojiebun1390 3 місяці тому +2

    these questions are tough.it requires lot of thinking through.i had 3/5.

    • @PMPwithRay
      @PMPwithRay  3 місяці тому

      Nice try. The questions are in line with the difficulty level you will experience in your PMP exam.

  • @cammyc3671
    @cammyc3671 9 місяців тому +1

    Great video!

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Glad you enjoyed it! Thanks for watching and commenting!

  • @alagendraramasamy8538
    @alagendraramasamy8538 6 місяців тому

    👍3/5. Well explained.

    • @PMPwithRay
      @PMPwithRay  6 місяців тому

      Thank you for watching and participating!

  • @travel_with_zafran8187
    @travel_with_zafran8187 7 місяців тому +1

    Hey Rai! Just wanted to drop you a thank you note for providing such an amazing content, I was just having a plan of doing PMP and wanted to check the contents but across your video which gave me an insight about the exam questions.

    • @PMPwithRay
      @PMPwithRay  7 місяців тому

      Glad I could help! Many thanks for your comment :)

  • @favouraghedosaWNCC
    @favouraghedosaWNCC 2 місяці тому

    Wow Excellent teaching... I'm new here

    • @PMPwithRay
      @PMPwithRay  2 місяці тому +1

      Thank you for watching and commenting!

  • @shahildays2985
    @shahildays2985 7 місяців тому +1

    For Ques #01, When scope baseline fixed in planning phase without assess and change control procedure how we include the missed scope?? It should be D

    • @PMPwithRay
      @PMPwithRay  7 місяців тому

      Hi, the correct answer as per PMI standards is as per the answer explanation in the video

  • @tayooyeleke5290
    @tayooyeleke5290 7 місяців тому +1

    Thanks Ray. Scored 3/5

    • @PMPwithRay
      @PMPwithRay  7 місяців тому

      Thank you for participating and commenting!

  • @vijayasrinivas8704
    @vijayasrinivas8704 9 місяців тому

    Very clear explanation, thank u

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Thanks for watching and commenting!

    • @vijayasrinivas8704
      @vijayasrinivas8704 9 місяців тому +1

      @@PMPwithRay I am working and I attended a Pmp training and have gained 35 pdu. Still preparing for exam, but finding it difficult allocate time to study with office work and being a mom of 2 kids. Please suggest me a plan that may help me prepare and pass the exam in next 30 days. Ur inputs will be very helpful for me. According to me I am 50 ℅ prepared.

    • @PMPwithRay
      @PMPwithRay  8 місяців тому

      Hi, probably these videos will help you:
      1. How to fast track your exam prep: ua-cam.com/video/FmgLbA7cRs8/v-deo.html
      2. How to build a study plan: ua-cam.com/video/FslEa9e2Qmc/v-deo.html

    • @PMPwithRay
      @PMPwithRay  8 місяців тому

      Hi, probably these videos will help you:
      1. How to fast track your exam prep: ua-cam.com/video/FmgLbA7cRs8/v-deo.html
      2. How to build a study plan: ua-cam.com/video/FslEa9e2Qmc/v-deo.html

  • @venkatramanms3891
    @venkatramanms3891 8 місяців тому

    Great explaination to understand the process steps

    • @PMPwithRay
      @PMPwithRay  8 місяців тому

      Thank you for watching and commenting!

  • @shameembasha7576
    @shameembasha7576 7 місяців тому +1

    5/5 i answered correctly.

    • @PMPwithRay
      @PMPwithRay  7 місяців тому

      Thank you for watching and participating!

  • @RaktimDebnath-w1h
    @RaktimDebnath-w1h 9 місяців тому +1

    For Q1. How can we add missed scope in the WBS in execution phase without the Change Management process is being followed? Scope is already baselined.

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Hello. Yes, PICC needs to be followed. The question is not saying that it should be avoided.

    • @nidhisangam3450
      @nidhisangam3450 8 місяців тому

      But we have to select PICC if option is there ...

  • @qwamelhanks5238
    @qwamelhanks5238 8 місяців тому +1

    For Q2--I thought that cost baselines are fixed. Don't we use cost baselines to do EVM and compare to actual costs? So if we keep changing it, isn't it mute? I chose C, management reserves, because the graph seems to show that costs are higher than we anticipated and so we will need to tap into management reserves to cover these unknown popups.

    • @PMPwithRay
      @PMPwithRay  8 місяців тому

      Cost baselines are fixed until changed via the PICC process.

  • @khizarkhalid6577
    @khizarkhalid6577 9 місяців тому +1

    Sir can you explain the first question? How can we just blindly add the missing part in the wbs without having stakeholders involvement? And also CCB process should be followed. Please explain this so i can clear this confusion.
    Moreover M&C is performed throughout the lifecycle including planning as well.

    • @PMPwithRay
      @PMPwithRay  8 місяців тому

      Hi, option A is not asking you to add the requirements blindly. I would advise you to re-watch the answer explanation section for this part.

    • @BryantInManila
      @BryantInManila Місяць тому

      I'm confused as well. If there's an indication that this is an Agile project, then C would have made sense. C is not applicable in a Predictive approach

  • @azharbashir8208
    @azharbashir8208 9 місяців тому

    3/5....very informative session!

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Thanks for participating and commenting!

  • @krisdahoo3824
    @krisdahoo3824 8 місяців тому

    Thanks Ray, great video with great explanations. Thanks again.

    • @PMPwithRay
      @PMPwithRay  8 місяців тому

      Glad you enjoyed it! Thank you for participating and commenting!

  • @mohitmalviya4343
    @mohitmalviya4343 9 місяців тому

    I got 5/5 correct, thanks Ray.

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Thanks for participating and commenting!

  • @DeepakJha-rk6gz
    @DeepakJha-rk6gz 9 місяців тому

    Very Nice sir

  • @donalddabson
    @donalddabson 9 місяців тому

    I scored 4 questions correctly. Thank you Ray

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Thanks for participating and commenting!

  • @Alshanewr
    @Alshanewr 9 місяців тому

    Thank you ray for your perfect questions and answers, please if you can help in solving the following question:
    A project manager works in a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time. As a project manager, what should you do next?
    1- Meet with the team member and work on a development plan for them to avoid missed deliverables in the future.
    2- Hold a team meeting to discuss team member commitments and communications.
    3- Give the team member a formal warning for the negative impact due to failure to deliver and not meet deadlines.
    4- Record the issue, then refocus the team's efforts on delivering the next set of deliverables.

    • @SHOUBHIKDAS24
      @SHOUBHIKDAS24 9 місяців тому +2

      Option 2

    • @mathewphilip3979
      @mathewphilip3979 9 місяців тому +1

      Ans: 1- Meet with the team member and work on a development plan for them to avoid missed deliverables in the future.

  • @heemanshuk4608
    @heemanshuk4608 9 місяців тому

    Thanks a Lot NiL , Got 4 out of 5 , Important is 1st one was wrong but understood the logic . Will do the Practice QnA for earlier months also

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Thanks for watching and commenting!

  • @sansthitachannel324
    @sansthitachannel324 6 місяців тому

    For Q 5, The client is very clear about the product requirements..Why can't they go forward with a waterfall approach where they will launch the website at a time with all features..
    Customer would also like to have all the options before investing.
    Kindly explain..

  • @priyankajain-nv9qu
    @priyankajain-nv9qu 9 місяців тому +1

    hi Ray, thanks for the video, just wanted to check if we have multiple correct answers in exam? so in case i select opt D in Q1, will i get marks for that?

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Hello, there is no partial marking for multi-select Q's. You need to get all the options correct to get full marks.

  • @laxmisagarrout3225
    @laxmisagarrout3225 9 місяців тому

    For question 1: Execution and monitoring & controlling happens parallelly in a project. So, considering the same can't A be the best answer ? Also for C, don't we need a change request to add the missed scope items in WBS ?

    • @heemanshuk4608
      @heemanshuk4608 9 місяців тому

      pls see this para from Rita M--"Not all changes require change requests, but change requests are generated from many processes if they require a
      change to the project management plan or the performance measurement baseline. The three main categories into which
      changes fall are corrective action, preventive action, and defect repair."

    • @zethalal007
      @zethalal007 9 місяців тому +1

      @@heemanshuk4608 He is taking about key deliverables missed out, changes that doesn't require changes are related to specs, features or internal processes which comes under configuration management plan. Answer is A.

    • @azharbashir8208
      @azharbashir8208 9 місяців тому

      I also agree for that...A is the right answer as per my understandings

  • @Sandeep_Bhalothia
    @Sandeep_Bhalothia 3 місяці тому +1

    Q1: I selected option-A but I see you choose option C, when I searched same on ChatGPT; it showed option D as correct and when I searched same on google, it is showed option- A. Still don’t know which one is most accurate. Anyways thanks for your videos. Appreciate it.

    • @PMPwithRay
      @PMPwithRay  2 місяці тому

      Please ask Chat GPT and/or Google to give the rationale behind their suggested answers :) I am happy to debate it.

    • @versatilemanager
      @versatilemanager 2 місяці тому

      I agree, Option A sounds better answer. Validate scope should not be perceived from a process perspective. If it is processed, then we should add it to WBS, execute and then validate. But here in this case it says to check suitability to understand if it fits. Adding it to wbs and calculating would be the reactive answer because maybe it is not possible even to add it to WBS back since execution happened. And C would require CCB as well. D also might be an issue but it only includes expert judgment, so I eliminate it since we are not including other stakeholders to the decision making.

    • @amandeepchandhok7166
      @amandeepchandhok7166 Місяць тому

      @@versatilemanager, @PMPwithRay , i also support the option A as the best choice, also when execute and monitor and control go hand in hand, hence option A is making more sense. Option C means that we are changing the Project Scope without even putting that into the CCB, remember Scope baseline cannot be changed unless there is a CCB approval. Further the Scope Baselines = Scope Statement + WBS + WBS dictonary.

  • @SivaSelvam-dy9vs
    @SivaSelvam-dy9vs 9 місяців тому

    i got 3 out of 5 thanks for this video

    • @PMPwithRay
      @PMPwithRay  8 місяців тому

      Thank you for participating and commenting!

  • @ahmedimam9945
    @ahmedimam9945 9 місяців тому +1

    if you have Simulator would you please to send me the link-Thq

  • @WillRogers-zg8me
    @WillRogers-zg8me 7 місяців тому +1

    4/5

    • @PMPwithRay
      @PMPwithRay  7 місяців тому

      Thank you for watching and participating!

  • @kapilgoyal7170
    @kapilgoyal7170 9 місяців тому

    4 out of 5

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Thanks for participating and commenting!

  • @ihabjalal9
    @ihabjalal9 4 місяці тому

    2/5

  • @Exotic_Ride
    @Exotic_Ride 9 місяців тому

    Got 4 out of 5

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Thanks for watching and participating!

  • @nidhisangam3450
    @nidhisangam3450 8 місяців тому

    4/5.....

    • @PMPwithRay
      @PMPwithRay  8 місяців тому

      Thank you for participating and commenting!

  • @gouravpandey9363
    @gouravpandey9363 8 місяців тому

    2/5

    • @PMPwithRay
      @PMPwithRay  8 місяців тому

      Thank you for participating and commenting!

  • @sunkerlasrinivasarao702
    @sunkerlasrinivasarao702 2 місяці тому

    4

    • @PMPwithRay
      @PMPwithRay  Місяць тому

      Thank you for watching and commenting!!

  • @engahmedsabry6663
    @engahmedsabry6663 5 місяців тому

    3/5😢

    • @PMPwithRay
      @PMPwithRay  5 місяців тому

      Thank you for watching and commenting!

  • @SHOUBHIKDAS24
    @SHOUBHIKDAS24 9 місяців тому

    4 out of 5

    • @PMPwithRay
      @PMPwithRay  9 місяців тому

      Thank you for participating and commenting!