How to draw a Gantt chart with more complicated predecessors

Поділитися
Вставка
  • Опубліковано 4 жов 2024
  • Check out www.engineer4fr... for more free engineering tutorials and math lessons!
    Project Management Tutorial: How to draw a Gantt chart with more complicated predecessors.
    Please support my work:
    PATREON | / engineer4free
    Every dollar is seriously appreciated and enables me to continue making more tutorials

КОМЕНТАРІ • 99

  • @ScoobySnacks1809
    @ScoobySnacks1809 Рік тому +10

    You kept it simple, so much better than any other video I’ve watched

  • @Adam1llion
    @Adam1llion 6 років тому +46

    This is the greatest video I have found to explain this stupid chart. Thank you!!!

    • @Engineer4Free
      @Engineer4Free  6 років тому +1

      haha thanks!! Do check out engineer4free.com/project-management for all of the other videos that I made on this stuff if you haven't already!

    • @Dennis-jg9en
      @Dennis-jg9en Рік тому +1

      Stupid but very helpful in business

  • @weekendresearcher
    @weekendresearcher 4 роки тому +11

    The channel is a hidden gem,👍💯

  • @miaafro7126
    @miaafro7126 7 років тому +9

    Thank God I've found your channel!!! I have my PM exam in one week and I had never understood these charts and diagrams. Let's hope I ace my exam this time!

    • @Engineer4Free
      @Engineer4Free  7 років тому +1

      +Mia Afro glad you found it! Make sure you check out the whole playlist on YT or the site engineer4free.com/project-management :)

  • @robertonunez3276
    @robertonunez3276 9 років тому +5

    Thank you very much for your videos, by far the most useful ones videos I've seen on here.

  • @brendaelodie722
    @brendaelodie722 5 років тому +5

    Thanks very much ☺️. Your channel has improved my notes in project management. I'm very grateful 😊😁

    • @Engineer4Free
      @Engineer4Free  5 років тому +2

      That's awesome Brenda! Glad I could help 🙂

  • @JoffreymusicCover
    @JoffreymusicCover Рік тому +1

    thank you brother..simple but very undertsandable explanation

  • @lolatalkstoomuch6114
    @lolatalkstoomuch6114 2 роки тому +2

    Thank you SO much ! You really know how to simplify it for us "laymen" 🥺

  • @gasparmargwe5341
    @gasparmargwe5341 4 роки тому +1

    Thank you bro!! For this example because has made me more critical on this Gantt chart drawing's!!!!

  • @ChineyeEjiofor
    @ChineyeEjiofor 3 дні тому

    Great tut , thank you

  • @patiencemuthama
    @patiencemuthama 3 роки тому +1

    Glad I found this channel 😃!!

  • @tdf8751
    @tdf8751 4 роки тому +1

    thank you very much for the video,i was really having a hard time with my teacher

    • @Engineer4Free
      @Engineer4Free  4 роки тому

      Hey glad I can help. If you haven't already, check out all the PM videos I did at engineer4free.com/project management 🤙🤙

  • @masihtayeb5473
    @masihtayeb5473 5 років тому +1

    thank you it is really useful and also very easy for learning

    • @Engineer4Free
      @Engineer4Free  5 років тому

      Awesome glad to hear it! Make sure you check out the rest of the PM videos I did at engineer4free.com/project-management if you haven't already =) =)

  • @charlievitor7598
    @charlievitor7598 3 роки тому +1

    Thank for this I fully understand

  • @AZAMOTG
    @AZAMOTG 5 років тому +2

    so much love for u bro

  • @kevinsheasby6240
    @kevinsheasby6240 3 роки тому

    Thank you for the useful video. Practical explanation is always better.

  • @anonytv9223
    @anonytv9223 2 роки тому

    Can't be more grateful 👍

  • @mofokeng87
    @mofokeng87 4 роки тому +1

    Best video ever ♥️❤️🙏 I understood in 2 minutes

    • @Engineer4Free
      @Engineer4Free  4 роки тому

      Amazing!! Thanks for leaving the comment 😁😁

  • @Nthabi031
    @Nthabi031 6 місяців тому

    you are the BEST sir😇

  • @its_ahk
    @its_ahk 10 місяців тому +1

    Lots of love from Pakistan🥰

  • @fay9980
    @fay9980 6 місяців тому

    Thank you man you da best🤩

  • @fplpulse7910
    @fplpulse7910 Рік тому

    Thank you

  • @sahandkhaleghparast56
    @sahandkhaleghparast56 8 місяців тому +1

    Critical paths?
    Delay deys of non critical days?
    Where are the responses for them

    • @Engineer4Free
      @Engineer4Free  8 місяців тому +1

      See engineer4free.com/project-management and start at the beginning of the playlist 👌

  • @Npvp98
    @Npvp98 Рік тому

    Amazing explanation sir.thank you sir. 🗿🗿😍🤟😀😀😀

  • @AJ-et3vf
    @AJ-et3vf 2 роки тому

    Awesome video! Thank you!

  • @zariefmalek8450
    @zariefmalek8450 Рік тому

    thank you very much bro

  • @lilya5892
    @lilya5892 Рік тому

    So what is the duration of the project? The best time and the worst time?

  • @harinair7014
    @harinair7014 6 років тому +1

    thanks a lot man did a great job!! how about u goin for nother video of other charts like timeline chart or PERT chart and blah

    • @Engineer4Free
      @Engineer4Free  6 років тому

      Thanks Hari. Check out engineer4free.com/project-management for the whole playlist of PM videos that I made. I cover a lot of other topics, including 8 videos on PERT.

  • @Godsentjenica
    @Godsentjenica 10 місяців тому +1

    I love you man❤

  • @christinewayua9493
    @christinewayua9493 5 років тому +1

    very useful

  • @Suzanne-uv3cm
    @Suzanne-uv3cm 11 місяців тому +1

    How to Know the critical path,Time duration of thé project

  • @amyclancy5009
    @amyclancy5009 9 місяців тому

    Hey if an activity has 2 predecessors for example if D’s predecessors where B,C how would you plot it ?

  • @somasoue
    @somasoue 6 років тому

    you are really wonderful lecture

  • @khuloodalhossani4690
    @khuloodalhossani4690 8 років тому

    helped me for final , thanks a lot

    • @Engineer4Free
      @Engineer4Free  8 років тому

      +Khulood Alhossani Awesome thanks for letting me know! Feel free to check out all the Project Management tutorials I made here: www.engineer4free.com/project-management :)

  • @rahatpranto9459
    @rahatpranto9459 5 років тому +1

    What happens when there are several predecessor for a single activity?

    • @Engineer4Free
      @Engineer4Free  5 років тому

      You take the largest Early Finish of all predecessors as the Early Start of the successor. I recommend taking an hour or so to watch videos 1-9 here: engineer4free.com/project-management

  • @usrakhan975
    @usrakhan975 2 роки тому

    plz teach how to draw rhem on a software like MS project

  • @manishameghraj3448
    @manishameghraj3448 4 роки тому +1

    Can I know how you are adding numbers in duration column

    • @Engineer4Free
      @Engineer4Free  4 роки тому +1

      Hey, I recommend taking the time to watch the first few sections of engineer4free.com/project-management to get familiar with the basics here

  • @offlinefreakz759
    @offlinefreakz759 7 років тому

    helped a lot.

  • @muktarahmedmohamed7275
    @muktarahmedmohamed7275 4 роки тому +1

    Thanks a lot it is really helpful. Could you please tell the software you are using the video for drawing?

    • @Engineer4Free
      @Engineer4Free  4 роки тому

      Glad to hear it! I've got a full list of all the harware and software that is use to make the videos here: engineer4free.com/tools 👌

  • @sivatharshan
    @sivatharshan 6 років тому +1

    that,s a nice video and the critical path is 11 days?? am i right?

    • @Engineer4Free
      @Engineer4Free  6 років тому

      Thanks, and yup it would be 11 days!

  • @jakejohn1966
    @jakejohn1966 3 роки тому +1

    im looking for multiple predecessors, i cant even find one online, could you please help?

    • @Engineer4Free
      @Engineer4Free  3 роки тому +1

      Did you check this video? ua-cam.com/video/4oDLMs11Exs/v-deo.html Activity G has multiple predecessors, and so does Activity H. Then this video: ua-cam.com/video/qTErIV6OqLg/v-deo.html has the same general form, but more complicated relationships with lag. Hope it helps!

  • @lucutes2936
    @lucutes2936 Рік тому

    can you do it with effort and resources needed columns?

  • @leonne_
    @leonne_ 2 роки тому

    Is the duration(days) given already? Or you have to compute to get it?

  • @momento3619
    @momento3619 4 роки тому +1

    what if an activity depends on 2 predecessors

    • @Engineer4Free
      @Engineer4Free  4 роки тому

      You need to select the larger value (early finish) from the two predecessors as the start (early start) of the successor. See videos 4 - 9 here: engineer4free.com/project-management 👌

  • @MdFaizan-th5yf
    @MdFaizan-th5yf 7 місяців тому +1

    If there are two predecessor ? 😊

    • @Engineer4Free
      @Engineer4Free  7 місяців тому +1

      You can see that situation for some activities in this video: ua-cam.com/video/EvmIJ51NsOg/v-deo.html cheers 👌

  • @ziheanyong9430
    @ziheanyong9430 Рік тому

    What if there is two predecessor

  • @mohsinshaikh1407
    @mohsinshaikh1407 7 років тому

    How to make project release ? any example video please share here

  • @Abrar_Ahmed05
    @Abrar_Ahmed05 3 роки тому

    HOW TO CREATE THESE KIND OF GANTT CHART ON EXCEL ??? I HAVE MORE THAN 1 PREDECESSORS SUCH AS FOR ACTIVITY E I HAVE G,H

  • @NIKHILSHARMA-ni5uo
    @NIKHILSHARMA-ni5uo 5 місяців тому

    Tq sir🙏

  • @wayliws
    @wayliws Рік тому

    what if its d-e?

  • @tejask4889
    @tejask4889 8 років тому

    Thanks :)

    • @Engineer4Free
      @Engineer4Free  8 років тому

      +tejas k Glad to help! You can find all 45 project management tutorials I made here if you have more to learn www.engineer4free.com/project-management.html :)

  • @giginasser4934
    @giginasser4934 4 роки тому +1

    merci

  • @Kanwarpalsachdeva
    @Kanwarpalsachdeva 7 років тому

    what if one of the task is dependent on 2 different tasks. How do you chose the start point then

    • @Engineer4Free
      @Engineer4Free  7 років тому

      Video 7 here: engineer4free.com/project-management covers multiple predecessors. I do recommend watching at least videos 1-9 though to get some more context and practise.

  • @kondasaiprakash8837
    @kondasaiprakash8837 4 роки тому +2

    what if they give more dependencies (2 or more) for each activity pls can u tell

    • @Engineer4Free
      @Engineer4Free  4 роки тому +1

      If an activity has multiple predecessors, you must select the ES that is the latest of the options

  • @howardamosa8897
    @howardamosa8897 2 роки тому

    anyone know any software to do gantt charts?

  • @Nightmixable
    @Nightmixable 8 років тому

    What about a video where there's multiple predecessors, would you mind showing~?

    • @Engineer4Free
      @Engineer4Free  8 років тому

      Hey, check out this tutorial: www.engineer4free.com/4/use-forward-and-backward-pass-to-determine-project-duration-and-critical-path Activity G and Activity H have multiple predecessors. There's no Gantt chart in the video, but there is a PDM network diagram that shows ES & EF which can are just the left and right ends (respectively) of a bar in a Gantt chart.

    • @Nightmixable
      @Nightmixable 8 років тому

      Thank you so much.

  • @dmal6202
    @dmal6202 7 років тому

    How do you end up with a total of 11 days, If the total duration when added is 22 days?

    • @Engineer4Free
      @Engineer4Free  7 років тому

      The sum of all activities is a meaningless number unless they all happen consecutively, for example, B can only start once A is done, C can only start once B is done, D can only start once C is done, and so on.... Imagine an example with 4 activities (A,B,C,D) that are each 5 days long, if the table of dependencies showed that D can start once C is done, C can start once B is done, B can start once A is done, and A is the beginning of the project, then the project duration would be 20 days like you're suggesting. Now if the table of dependencies said instead that D AND C can start when B is done, B can start when A is done, and A is the beginning of the project, then the project duration would only be 15 days, with activities C and D running at the same time, with both finishing at the same time, at the end of the project. The activity relationships stated in the table of dependencies are key to creating the gantt chart which then reveals the project duration. I'd recommend watching video #1 here: engineer4free.com/project-management and then exploring further into the videos after!

    • @abdulmoizahmer9770
      @abdulmoizahmer9770 7 років тому

      how did u know that your duration axis will go upto 11

    • @Engineer4Free
      @Engineer4Free  7 років тому +2

      ABDULMOIZ AHMER I made up the example and checked it before I made this video, so in order to not waste space on the screen I just made the Gantt chart area the appropriate size. I could have guessed and made the space 15 days long and then just not used some of it... doesn't matter!

    • @abdulmoizahmer9770
      @abdulmoizahmer9770 7 років тому

      ok thanks

    • @chrisduffy1985
      @chrisduffy1985 5 років тому

      Engineer4Free in this example, could it be said that Activities A-B-D-H make up this projects critical path?

  • @ferguscheah
    @ferguscheah 7 років тому

    hello do you have tutorials on how to draw this on microsoft excel?

    • @Engineer4Free
      @Engineer4Free  7 років тому

      Not currently, sorry about that. You can find all of my PM videos at engineer4free.com/project-management

  • @deastro0
    @deastro0 6 місяців тому

    deym its cool

  • @bethiamukatha3766
    @bethiamukatha3766 Рік тому

    Tqq

  • @JayanthJayanth-gz4xi
    @JayanthJayanth-gz4xi 6 місяців тому

  • @oplalopal5332
    @oplalopal5332 Рік тому

    👍👍👍👍👍👍