How to Draw a Gantt Chart - Example #1

Поділитися
Вставка
  • Опубліковано 10 гру 2023
  • This tutorial shows how to draw a Gantt chart when given a table of dependencies.
    This video shows the network diagram and critical path for the same project: • Use forward and backwa...
    This video is part of a full free course on project management.
    Links to the course are here:
    Website: www.engineer4free.com/project...
    UA-cam: • Project Management
    If you found this video helpful, then please give a 👍 and subscribe. If you're able to, please support my work on Patreon: / engineer4free
    Also follow these:
    Facebook: / engineer4free
    Instagram: / engineer4free
    Twitter: / engineer4free
    LinkedIn: / engineer4free
    Thanks for watching, I hope it helps!

КОМЕНТАРІ • 21

  • @chukwujiokestephen23
    @chukwujiokestephen23 6 місяців тому +21

    Thank you so much,what I couldn't understand in one week of attending lectures done in 5 minutes.

  • @fabriceras9562
    @fabriceras9562 6 місяців тому +7

    How convenient.....I was looking for this and this video is coincidentally 1 day old....Thanks champ

    • @Engineer4Free
      @Engineer4Free  6 місяців тому +3

      Haha nice!! Welcome to the party 🎉

  • @Lee-vc8nt
    @Lee-vc8nt 3 місяці тому

    Thank you! This helped a bunch

  • @markanthonynisperos7659
    @markanthonynisperos7659 2 місяці тому +2

    Thank you for this much appreciated❤ , i really understand it well better than the long explanation in our lectures 😩

  • @tahmidaisra2669
    @tahmidaisra2669 Місяць тому

    Thank you so much ❤

  • @noumanhassan4805
    @noumanhassan4805 3 місяці тому +1

    Thanks you so much

  • @suparna_saha
    @suparna_saha 28 днів тому

    Subscribing because he deserves❤

  • @sagarsah7536
    @sagarsah7536 2 місяці тому +1

    Thank you 🙏

  • @diannapatrick3247
    @diannapatrick3247 2 місяці тому +2

    Thank you

    • @Engineer4Free
      @Engineer4Free  2 місяці тому +1

      You're welcome thanks for watching! 😁

  • @FaustineOkoth
    @FaustineOkoth 2 місяці тому +1

    Thanks alot

    • @Engineer4Free
      @Engineer4Free  2 місяці тому +2

      You're welcome! Thanks for watching 🙂

  • @dianasakala9141
    @dianasakala9141 2 місяці тому

    Thank you.
    Can you please explain how we found the project duration?

  • @AbhinavMotha
    @AbhinavMotha 4 місяці тому

    how to know predecessor ??

  • @sarajann5493
    @sarajann5493 4 місяці тому +1

    Activity b needs 4 days and Activity c needs 2 days but we are giving them 4 days in general. Shouldn't it be 6 days?

    • @Engineer4Free
      @Engineer4Free  4 місяці тому +1

      Heyy so look at each one separately. B needs 4 days, and it can only start once A is finished, so B finishes 4 days after A finishes. Now consider C. C needs 2 days, and it can only start once A is finished, so C finishes 2 days after A finishes. There is no significant relationship between B and C, only relationships between A and B, and A and C. And the relationships are actually finish to start, so the start of the successor depends on the finish of the successor, rather than the finish to finish wording that I used above. Take a look at this video as well, it talks about the numbers in the Gantt chart and might help to clarify the idea: ua-cam.com/video/2-Zcaq2YFS8/v-deo.html 👍

    • @sarajann5493
      @sarajann5493 4 місяці тому

      thank you so much
      @@Engineer4Free