SAES-M-100 -- Saudi Aramco Building Code, 20 June 2016 SATIP-M-100-02 Waterproofing of Roof Slabs SAIC-M-1012 Waterproofing of Roof Slabs SAIC-M-1014 Waterproofing Surface Preparation, Waterproofing Layer Installation Inspection SAIC-M-1018 Waterproofing Final Inspection Inverted, loose laid, ballasted single ply roofs; fully adhered single ply membrane roofs and loose laid, ballasted single ply roof systems shall have a slope of less than ½ inch (13mm) vertical to 12 inches (305 mm) horizontal. The surface preparation for the roof coverings are completed in accordance with the manufacturer's recommendations (IBC Sec.1507.1) Installation of waterproofing layer shall be as per manufacturer's recommendation and IFC drawings. (IBC Sec.1507.1) Installation of fully adhered EPDM sheets over the entire area shall have a minimum thickness of 1.52mm (0.060") thk. Installation of fully adhered Modified Bitumen Membrane over the entire area shall have a minimum thickness of 5 mm (0.02") thk. Installation of fully adhered TPO (Thermoplastic PolyOlefin) or PVC (PolyVinyl Chloride) membrane over the entire area shall have a minimum thickness of 1. 52 mm thk. If PVC and TPO membrane is exposed, thickness shall be 2.0 mm & UV resistant. Ballasted roofs shall have a separation layer installed below the gravel ballast. Ballasted roofs shall have a minimum of 19 mm (¾") washed gravel placed to a minimum thickness of 50 mm (2"). Lightweight foam concrete roof screeds shall be installed per the manufacturer's instructions to the slopes and to the extent indicated on IFC Drawings. All completed flat roofs shall be subjected to a flood test for a period of no less than 24 hours. Roof flood tests shall be carried out in a manner acceptable to the Company Representative and the Saudi Aramco Inspection Department Representative (or as per SATR M-1014).
SAES-M-100 -- Saudi Aramco Building Code, 20 June 2016
SATIP-M-100-02 Waterproofing of Roof Slabs
SAIC-M-1012 Waterproofing of Roof Slabs
SAIC-M-1014 Waterproofing Surface Preparation, Waterproofing Layer Installation Inspection
SAIC-M-1018 Waterproofing Final Inspection
Inverted, loose laid, ballasted single ply roofs; fully adhered single ply membrane roofs and loose laid, ballasted single ply roof systems shall have a slope of less than ½ inch (13mm) vertical to 12 inches (305 mm) horizontal.
The surface preparation for the roof coverings are completed in accordance with the manufacturer's recommendations (IBC Sec.1507.1)
Installation of waterproofing layer shall be as per manufacturer's recommendation and IFC drawings. (IBC Sec.1507.1)
Installation of fully adhered EPDM sheets over the entire area shall have a minimum thickness of 1.52mm (0.060") thk.
Installation of fully adhered Modified Bitumen Membrane over the entire area shall have a minimum thickness of 5 mm (0.02") thk.
Installation of fully adhered TPO (Thermoplastic PolyOlefin) or PVC (PolyVinyl Chloride) membrane over the entire area shall have a minimum thickness of 1. 52 mm thk.
If PVC and TPO membrane is exposed, thickness shall be 2.0 mm & UV resistant.
Ballasted roofs shall have a separation layer installed below the gravel ballast.
Ballasted roofs shall have a minimum of 19 mm (¾") washed gravel placed to a minimum thickness of 50 mm (2").
Lightweight foam concrete roof screeds shall be installed per the manufacturer's instructions to the slopes and to the extent indicated on IFC Drawings.
All completed flat roofs shall be subjected to a flood test for a period of no less than 24 hours. Roof flood tests shall be carried out in a manner acceptable to the Company Representative and the Saudi Aramco Inspection Department Representative (or as per SATR M-1014).
@@irfanmaqsood3024 kindly check SATR-M-1014 for details.