Critical Path of a Project with Multiple Finishing Activities
Вставка
- Опубліковано 28 січ 2024
- This tutorial shows how to draw the network diagram and find the critical path of a project when there are multiple finishing/final activities. In this scenario, you must use the latest EF as the LF of all. This video is part of a full free course on project management.
Links to the course are here:
Website: www.engineer4free.com/project...
UA-cam: • Project Management
If you found this video helpful, then please give a 👍 and subscribe. If you're able to, please support my work on Patreon: / engineer4free
Also follow these:
Facebook: / engineer4free
Instagram: / engineer4free
Twitter: / engineer4free
LinkedIn: / engineer4free
Thanks for watching, I hope it helps!
I have an exam in like an hour you’ve made this so simple. Thank you
Hope it went well 🤜🤛
As a finish tradesmen, I have always had CPM forced on me. Now I know now the schedule was off by weeks before I started. Great video's you have. I certainly understand it more now.
Thanks you made my life easy I was never taught this but I have an exam tomorrow
Can you please do more hydraulics videos? Specifically, something that could help with problems like
"If the piston and water are accelerated upward. What will be the pressure at a depth of 2 ft in the water column "
Your other videos were so helpful I would love more!
Sher gut❤