How To Estimate Duration Of Work In MS Project
Вставка
- Опубліковано 18 вер 2024
- This video explains how to correctly compute the duration of a task in days when given the hours of work, the number of resources and the percent allocated, assuming multiple resources are allocated for the same percentage. Create a custom field to display the total duration of tasks in Microsoft Project. Calculate the total task duration using a formula and display the duration total column in a table.
#MicrosoftProject
#taskduration
#MSProject