Dear Mr. Hani Ismail What if we are sub-contracting and the productivity depends on the type of contract in that scenario what is the best way to deal with productivity?
Dear engineer Hani, It will be very helpful if you make one video , where you explain UAE productive rate of ...KPI. Block,plaster.concrete, reinforcement, tile's.. Thanks. I have one data sheet which is based on UAE productive rate almost 10 year data collection.but it's not working when I apply it on site
@@crackrex1727 but what if our assumptions is beyond the capacity of contractors ? I am talking if we are in a client side and we want to estimate duration for a project or activity and we know only the quantity of works without knowing the resource info ?
@@khalidkhan-fs4jt who is knowing the availability of resources, that's why you should to arrange that with the Project manager who has the authority to use company resources
Very useful video . What if you did resource loaded and want to change it again by simple trick changine productivity rates in primavera ? Kindly share csi productivity rates . As you said in the video ,kindly share your software productivity .
link to download the presentation: planningengineer.net/productivity-rates-for-construction-projects/
Super explained sir in simple terms
Keep up the good work.
Nice and detailed presentation, resources curves, levelling and loading to Primavera are also useful.
Thank you very much for this video.And please make a course on historical data of Productivity rate.
Thanks in advance 🎉
Əlhəmdulilləh.Cəzəkəllahu xayran
Very useful sir keep going
Very useful
Glad you think so!
Hi sir, it will be very useful if you can make one video which explains the UAE productivity rates.
Will try
Assalam wailaekum sir
Please make a video on MSP in full details
Walikumsalam
yes we need
Sir prepare on infrastructural project.
What about the engineering work, how can I assume the resources and estimate the productivity, I couldn't find any information for this part of work.
Asalam O alikum Sir do you have Infra productivity rates sheet ALLAH will reward you for such kind of help.
need to know how to make historical data and smart sheets
I want to learn cost estimate with BOQ items, please suggest your course
Dear Mr. Hani Ismail What if we are sub-contracting and the productivity depends on the type of contract in that scenario what is the best way to deal with productivity?
Could you define productivities for Small bore piping and large piping , piping support ? how many member for 1 team? Please advise.
We can also divide 300/2.5 = 120 hrs
Dear engineer Hani,
It will be very helpful if you make one video , where you explain UAE productive rate of ...KPI.
Block,plaster.concrete, reinforcement, tile's..
Thanks.
I have one data sheet which is based on UAE productive rate almost 10 year data collection.but it's not working when I apply it on site
Dear sir
Can you share your productivity experience in UAE like block,plaster,painter,reinforcement,tiles.
What if we have only quantity available and no info of the crew size or resources info how we can calculate the duration ?
You will assume, or you should set with construction manager
@@crackrex1727 but what if our assumptions is beyond the capacity of contractors ? I am talking if we are in a client side and we want to estimate duration for a project or activity and we know only the quantity of works without knowing the resource info ?
@@khalidkhan-fs4jt who is knowing the availability of resources, that's why you should to arrange that with the Project manager who has the authority to use company resources
Very useful video .
What if you did resource loaded and want to change it again by simple trick changine productivity rates in primavera ?
Kindly share csi productivity rates .
As you said in the video ,kindly share your software productivity .
Hi Mr.Hany do have any experience in precast industry & it's productivity rate. If you have interest shall we discuss further.
I don’t have productivity rates , how to solve the getting productivity rates
Sir
MSP how to sum a total duration of project