General Rules for Foundation Excavation - Slopes as per CPWD / IS Code Guideines
Вставка
- Опубліковано 20 лип 2019
- Dear Friends,
In this video i have explained the general rules, slopes considered for for footing, trenches, excavation as per IS Code / CPWD Guidelines.
4:04 For 3m depth 50cm offset to be provided above 2m from bottom, not 2m from top
Very useful
Please make more video for all .. part along with code explaination.
Good
Very good information Sir.
Nice and informative video
Your video was excellent ... Kindly provide such knowledge about hard rock/Blasting case measurements
Narayan Bless 🙏 You
Very nice Sirji
Thanks
Very nice video sir
Very good
important details explained.. thank you sir
Thanks sir
Earth work pe v koi vidio banaye plz...
Your all videos so helpful for all civil engg students.
Sir ..steel slab m kitna lgega weigh length n rate analysis bhi plz video banayein .
Or stages of construct a home with details plz ..kitne column beam kitjo bricks and or bhi jankari.
Ek ghar vnane ka pura process detail m batayein sir.
Sir if possible. .
To ek do list bnakr daal dein jo questions interview m puche jate hn private as well as govt job.
Thanks for this topic, Kindly explain us about FIDIC, RICS ROLE, STANDARD METHODS OF MEASUREMENT,
Waiting for this topics, Thanks
I will cover your topics soon, thx for comments and Support
👌👌👌👌👍
Sir, can u please do a video on roads regarding billing , how budgeting is done and BOQ preparation using DSR and DAR. Please find a way to do videos
Great job sir...
Kindly one vedio large excavation....
Sir, if we cast a slab today and then later after 3 or 7 days the cube test results positive but failed in the 21 days cube test, what will be the next step because in next 21 days there may be 2 more slabs could be concreted.
For excess depth Instead of pcc can we increase the length of column?
Hi sir, very use full information, can you upload CPWD/IScode document
Sir excavation near existing building , how will it effect the strength of footing of existing structure
bottom se ya top se
Sir please make a video on Boom Concrete Pump
Sir rate analysis pe bhi video banaiye
Working space???
Sir billing engineer k liye important clause pe video banaiye
hard rock ke excavation me slope ratio kitna hona chahiye
While claiming in the Bill, how much working space is allowed
I have already explained in video - IS 1200 Part 1
excellently explained sir can i get the safety documents to study
I would suggest ypu personally Read BOCW Act 1996, that has perfect guideline for safety measures including compliances.
Is456 ka bhi lecture banao na is1200 jaisa
Pls Sir
Dear sir,
If the excavtion of the plot the NSL in very high the height is maximum 20 ft.the excavation can be executed by with out slops.
You can give steps
Good Morning Sir, you didn't mention anything about working space?? I mean if your foundation beam is 250 x 450 and it's underneath of NGL approx 1.5meter then how wide trench we have to excavate so any Mistry can work in that particular foundation beam trench??
That video have already Made as IS 1200 Part 1
300mm working space for upto depth of 1.5 M, and beyond 1.5 that is 750mm for more
Please watch video IS 1200 Part 1
@@FactualCivilEngineering sir . IS code 1200-1992 page no. 3 written that 600mm.i didn't understand please explain
Major excavation ke liye relevant doc required, please provide
As per my boq item working space is not mentioned and for S.no. 1 excavation depth is mentioned as upto 3 meter and Sr.no.2 depth upto 3m to 4.5 meter and last 4.5m to 7 meter
Then we what will be working space for S.no 1,2 and 3
Plz suggest
Working space will be accordingly.
If depth is upto 1.5 metre than 300 mm
And if it is greater than 1.5 than it is 750mm
Sir,
Basement ki excavation ka bta dyen
Hello sir ji..sir cpwd code no. Bta dijiye slope ke liye
Sir plz talk us about how to estimate of infrastructure work like road, drain, sewage, manhole, pipe line etc... plz plz plz..... plz plz plz..... plz plz plz..... plzzzzzz sir
Sir,May you share the CPW chat.
Sir is- 1200 k bahut sare part bacha hua hi uspe bhi video banaiye
Plz share CPWD code link for downloading..
.
Working space margin RCC outer to outer building s extra working space 4 side me kitna lete hai sir k....jab JCB s Excavation kr n k bhad foundation me labour ko work space v mile work kr n ko...sir
.450 m
Brother where i can find CPWD code pdf
Download it from google, Type CPWD specs PDF
IS CODE & CPWD Pl
Sir training institute bhi h ky aap ka
No, job jarta hu
@@FactualCivilEngineering what is u r name sir can i tack training from uhh i am also junior billing engineer in highway work