    1. No entry gate exist as per layout, during rainy season it will be all mud Street. OC will be rejected as the current construction is not as per original layout. 5 months since OC applied, will it take another 4 years for OC. Case is going on for the main entry and its a disputed property and will take another 3 years minimum for it to be resolved.
    2. Will take years for possession.
    3. Delayed by a year even after considering 6 month extension for Covid and 2 months construction ban for pollution.
    4. Shopping center under construction.
    6. As per affordable housing policy if the builder is not able to deliver the project in 4 years , the government should have undertaken the project and also forfeit 15% security deposited with government.
    7. The delays in multiple projects will make this affordable housing policy a failure where people have paid 100% amount years back, paying EMI, paying rent but builders are enjoying interest on peoples money.
    8. DTCP should take some strict action.
    9. The original date as per builder for possession was July-August 2019.
    10. Close to railway track with alot of criminal activity.
    11. People want to see at throw away prices but there are no buyers. Not even selling at the base price.