Lec-36 Calculation of Earliest And Latest Time,Total And Free Float, Critical path | Hindi | OR
Вставка
- Опубліковано 30 тра 2020
- #calculationofearliesttime #float #criticalpath #totalfloat #freefloat #independentfloat #latesttime
Connect with me
Instagram : / i._am._arfin
LinkedIn : / arfin-parween
Twitter : / startpracticing
Email : wbstartpracticing@gmail.com
Hello ...... Today we going to learn after drawing network diagram, how we calculate earliest starting time, earliest finishing time, latest starting time, latest finishing time, earliest time for head event, latest time for tail event, total float, free float, independent float, critical path, critical activity
In project management our topic is ......
Introduction of project management
project
Phases of project
basic terms : activities, events
common Error: looping, dangling, redundancy
Rule to draw network diagram
numbering the events : Fulkerson's rule
construction of network diagram
Time analysis: Forward pass computation
Backward pass computation
calculation of float and slack
Critical Activity
critical path
CPM (critical path method)
PERT ( program evaluation and review techniques)
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. ... A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
THANK YOU FOR WATCHING
___________________________________________
Please like share comments and subscribe
___________________________________________
To watch more tutorial, press the below link
How to draw network diagram and basics of network scheduling
• Lec-35 How To Draw Net...
Travelling salesman problem
• Lec-33 Travelling Sale...
Maximization in assignment problem
• Lec-32 Maximization As...
Unbalanced Assignment Problem
• Lec-31 Unbalanced Assi...
Assignment problem for multiple solution
• Lec-30 Assignment Prob...
Assignment problem part 1
• Lec-29 Assignment Prob...
degeneracy in Transportation Problem
• Lec-27 Degeneracy in T...
modi method transportation problem using north west corner rule 2
• Lec-26 Modi Method Tra...
Modi Method Transportation Problem using Vam 1
• Lec-25 Modi Method Tra...
unbalanced transportation problem vam method,
• Lec-24 Unbalanced Tran...
vogel's approximation method transportation problem
• Lec-23 Vogel's Approxi...
least cost method transpotation problem, unbalanced table
• Lec-22 Least Cost Meth...
least cost method transportation problem, balanced table
• Lec-21 Least Cost Meth...
unbalanced transportation problem using north west corner method
• Lec-20 Unbalanced Tran...
north-west corner method transportation problem, balanced table
• Lec-19 North West Corn...
transportation problem in hindi, conversion of unbalanced table into balanced table
• Lec-18 Transportation ...
for watch more tutorials pls visit the playlist in the channel
channel: / @startpracticing
playlist of operation research
• Operation Research In ...
Playlist of Transportation Problem
• Transportation problem...
playlist of probability for engineering mathematics
• Probability (engineeri...
Playlist of Data Structure and Algorithm
• Data Structure and Alg...
My UA-cam Shorts of Operation Research
• Operation Research Shorts
CPM in operation Research, network scheduling in operation Research, network scheduling by cpm, float in cpm, total float in cpm, free float, independent float, network scheduling in operation Research In Hindi, critical path in project management, critical path , critical activity, earliest time calculation in operation Research, latest time calculation in operation Research, arfin, arfin parween, start practicing
Happy to see that in India for free cost and their efforts show in their video❤️🔥✨
Thank you ✌
thankyou so much mam for helping your operational research playlist is very helfull i have watched many videos from this playlist it was very clearly explained and i understood very easily thankyou again mam😊
Thank you mam you are an amazing teacher.Im doing my masters from Delhi school of economics and you are much better than our faculty .
thank you so much mam i have searched for many video regarding this topic but your explanation alwys seems simple and informative too
Thank you ma'am bahot sare lectures dekh lea hea phr apke teaching methodology best hea,un se...
I really like ur explanation but small suggestion is when u explain the tabular form make sure that network and table both fit in the screen so that it will be easy for us while learning
If you don't like this vedio you can watch another one...
Make table in your book for understanding 🤣☺️🤣, i lover her explanation
Lazy lady
Zwsaaxxax!'
@@bestmoviesclips7383 @ss@q
@@vineetbachhawat3462 what marks you gained in examination in this subject?
You made my day so much doubt about this.....u made it very simple
Thank you so much for explaining time analysis 🙏
I love it this is really helpfull for us thank u mam u could teach very well, I understood all the topic through watching ur videos
Excellent lectures. Thank you so much.
Maam you are Great🙏🏻. Your teaching style is very much helpful🙏🏻. Thank you so much Maam for helping us. 🙏🏻😇
Thank you mam for your simplest explanation 🤩🤩
Thanks mam
Your playlist for operations Research help me alot for preparation of this subject....Thank You
Thankyou mam for the simplest of explanation 😊
Great explanation 🙏 Thank you soo much Mam
AAP kitna ache se samjhate ho❤
thank you so much.. ii was so confused to fill Latest finish nd Latest start in table, and you have given very simple trick.. thank you .
Thanks Mam😍❤️😍🙏
I really love the explanation.. i done my study in 1day
Ur explanation is simply super....
Very brief explaining. Keep it up 👍👌
Thank you so much mam❤️❤️❤️for ur efforts 🙏🙏
Thanks Mam🥰🙏❤
Wonderful .. explanation ...you tube par asa explanation....nahi theyaa h seriously
Thank you so much...I found this very helpful. keep up the good work.
Thank you mam Love from Himachal♥
you are great ma'am....
All lectures are very useful for us...
Thank you so much ma'am
Thanks A lot. Respect from Pakistan 🇵🇰
Thnq so much mam....this is very helpful🙏🙏🙏🙏🙏
Perfect and beautiful explaination madam... Really really helpful....
Million of thanks 🙏🙏🙏🙏
Best explananation 🙏
Mind blowing explaination
Thank you mam I understood very well
This is very helpful for semester 👏
Cannot Thank You Enough Maaaaam 🙏🙏🙏
Really wonderful explanation, please do in english also so it will reach world wide.
you probably dont care but if you guys are bored like me during the covid times you can stream pretty much all the latest series on instaflixxer. Been binge watching with my girlfriend during the lockdown xD
@Adan Jayce Yea, have been watching on instaflixxer for since december myself :)
Thanks you so much mam 🙏🏻 ❤️ 😊
Thank you soooo much for providing OR VDS ,we r kindly requesting u to make vdo on min cost flow
you are best🥰🥰 thank you so much
Thank you so much ma'am 😁
Thank you ma'am...
Thanks and respect from Bangladesh
Really R/Ma'am thankU so much #____👍🏻👍🏻👍🏻👍🏻
Thank you very much madam...🙏🏻✨
Thx for helping me
u r great mam😇
thank you very much!
thank u ma'am 🙏
you made it easy
Thankyou DiDI🤗😊
I most Likely this videos
Thanks u mam 🙏🙏❣️
Amazing teaching. Respect 📈
Thank you
Thanks Maam 🥰
You are best.
Nice explanation Ma'am
Thank you so much dear mam❤
Very well taught sister
Super explanation dear
Thankyou Mam Make videos for more topics
I like this vedio thanks mam
Thanks....
Thank you so much Maam 🙏🙏🙏❤❤❤❤❤🇳🇵🇳🇵🇳🇵🇳🇵🇳🇵
Thank you maim
you r awsome
Thank you mam
best video
Really m apne bhut aache se samjhayaa... Thanku so much ☺️
Ye notes mil sakte h kya pdf form me ?
upload notes too it will be helpful @Start Practicing
thanx mam
🙏respect
good job
👍
Hi, can you tell me what we do about slack
Op good work
Super madam
😊👍👍
Can u tell in me how that 4 plus 1 = 5 days how it's can in critical path
🙏🙏🙏🙏
❤️
At 6:18 what does Ej reresent( what do we call Ej)?
Ma'am dynamic programming ka lectures uploaded kijiye please
How to download these notes
Can you also give formula for interfering float plz
16:44 What is the difference between Ej and Earliest Finishing time (EF) ?
Mam Statistical Decisions ke video upload kijiye
18:04 How is Li different from LS?
Mam book name please
👌👌👌👌👌👌👌
Thanks 🙏
which lec of project crashing
Mam if ES = Ei then why not EF = Ej ,whats the diffrence between Ef and Ej please mam explain it
Anyone ??
Ma'am Lec 35 se Lec 36 aap AOA se AON pe chali gayi.....yahi samajh mein nahi aa raha hai!
Hi Can you give us a lecture in PDF form?
Mam can total float have a negative value? 😢
Aap s kalaywathy ki book se padha rhe h
Madam, is earliest starting time of an event should be equal to latest starting time of an event???
no
pls white board me banaiye
!!!!!!!
Apne direct tax pe lectures banye he?
upar niche m bahot cofusion hota hai