Earned value analysis worked example

Поділитися
Вставка
  • Опубліковано 3 лют 2025

КОМЕНТАРІ • 198

  • @antjobert
    @antjobert 6 років тому +92

    For people taking the PMP exam and are looking for help with earned value, make these substitutions: BCWP is the same as EV. BCWS is the same as PV. ACWP is the same thing as AC. This video was great once I mentally made those changes.

  • @SoarLikeAnEagle624
    @SoarLikeAnEagle624 3 роки тому +8

    You explain it so well and make it easy to understand. I've watched this 4 times and gone from not knowing anything about Earned Value Management, to being able to teach it at a basic level. Came back to make sure I clicked like!

  • @s0steezy
    @s0steezy 2 роки тому +18

    You literally got me through my project management course this semester, I couldn't afford the book. thank you so much, you do an awesome job at explaining analysis processes and most importantly their significances

    • @Engineer4Free
      @Engineer4Free  2 роки тому +2

      Thanks for letting me know, I'm glad I could help 🙂🤗

  • @TakeLife2TheExtreme
    @TakeLife2TheExtreme 7 років тому +7

    As many of the other commenters has pointed out, you do a very good job explaining this and are very concise.

  • @FaridWY
    @FaridWY 6 років тому +192

    PMBOK 6th Edition:
    ACWP = AC
    BCWP = EV
    BCWS = PV

    • @denisdobrev3301
      @denisdobrev3301 6 років тому +4

      Very helpful, thanks!

    • @umarhanif1377
      @umarhanif1377 4 роки тому

      Thanks dude very helpful

    • @rajbpatil6404
      @rajbpatil6404 4 роки тому +1

      Thanks Bro, great video, example and explanation. But this had me puzzled, was thinking to figure this out after watching the full video. Your quick tip helped.

    • @tanveerhussain9257
      @tanveerhussain9257 3 роки тому +1

      BCWS = PV is wrong. correct is pv =BCWS-ACWP

    • @tanveerhussain9257
      @tanveerhussain9257 3 роки тому

      pv =BCWS-EV

  • @oompaloompa9000
    @oompaloompa9000 6 місяців тому

    Thank you for taking the time to make this video. My class textbook doesn't break down how it arrives at these numbers. It does a horrible job of explaining. I'm blessed that I found your video!

  • @MohamedHanad-ys8lt
    @MohamedHanad-ys8lt 2 дні тому +1

    Watching it after 9 years thank you brother

  • @janeswayne6524
    @janeswayne6524 4 роки тому +1

    I've never touched project management before. And I was confused looking at other videos and resources with formal lingo, until I found this GEM. I'm tempting to buy their hoodie right now after watching this video =))

    • @Engineer4Free
      @Engineer4Free  4 роки тому +1

      Glad I can help!! You should check out the full PM playlist that I did here: engineer4free.com/project-management =) =)

  • @lamle-tu2tt
    @lamle-tu2tt 5 років тому +1

    I am from Vietnam and I thank you for your video, it was very helpful

  • @anishsule3283
    @anishsule3283 6 років тому +1

    Ur real jewel of a person..Spending your valuable time for mine kind of people who seeks engg mnmt knowldge is a great Cause..Thanx for uploading videos and they are very simple to interpret..Love from India 🇮🇳 and Nz🇳🇿loads of respect 🙏👍

    • @Engineer4Free
      @Engineer4Free  6 років тому

      Thanks Anish! Really appreciate your comment 🙂. Love back from 🇨🇦Canada where I'm from and 🇱🇦Laos where I am.

  • @diyaz_mukhanov
    @diyaz_mukhanov 4 роки тому +3

    Thanks a lot. It became so easy after the explanation. The tables are beautiful!

    • @Engineer4Free
      @Engineer4Free  4 роки тому +1

      Great!! Glad you liked it. Check out engineer4free.com/project management if you haven't already, for the rest of the PM videos that I did!

  • @AdiLNgay
    @AdiLNgay 4 роки тому +1

    I just love the way you are able to clearly explain all these concepts! I do not know how much I have heard and read of Gant charts, yet I could never quite understand how it was put together!! and now I am just like: ddduuuhhh!! this was it? I am just in 2.45 min of the video and had to stop to make that comment! there are a few other concepts that I could not understand either but I am never disappointed when come here! you are a God sent!

    • @Engineer4Free
      @Engineer4Free  4 роки тому +1

      =) thanks for letting me know!! And glad I can help. There are more videos here too: engineer4free.com/project-management The Earned Value Analysis ones are #33 - 38

  • @alinapariyani4683
    @alinapariyani4683 3 роки тому +1

    I have given up on trying to ask my professor for help. I am just watching these instead! Thank you.

  • @motso6553
    @motso6553 5 років тому +9

    for BCWP of "Activity C" you could have said 33% of 1200= 396... I nearly got confused for a sec there but well done. It's my first time doing this and watching this video made me understand the concept so quickly. Thank you

    • @Engineer4Free
      @Engineer4Free  5 років тому +1

      Yeah sorry that's just rounding. really it's 33.3333333333333333333333333...%, but glad you got it figured out =) =).Make sure you check out engineer4free.com/project-management for all the tutorials if you haven't already!

    • @pietchavalala7351
      @pietchavalala7351 2 роки тому +1

      You saved me there...i was expecting 396... so I was really confused as to why 400...but now it's clear that it was rounded

  • @20128096
    @20128096 4 роки тому +3

    Thank you for the simple yet effective explaination!

    • @Engineer4Free
      @Engineer4Free  4 роки тому

      You're welcome, thanks for watching! You should check out the full playlist here: engineer4free.com/project-management 🤜🤛

  • @arihasan3423
    @arihasan3423 8 років тому +4

    You describe every detail, extremely good video! Thank you!

  • @a.r372
    @a.r372 6 років тому +2

    am a student who studies on her own for CIPS advanced diploma, no teacher where I am actually.. and I have been proned to this chapter which I've found a little confusing to understand or to table it out. I just want to let u know, if a question on EVA comes out, I'll succeed because of this video! Am sure of it! Thanks again for the good job, may u be bless, this is soooo helpful!

    • @Engineer4Free
      @Engineer4Free  6 років тому +2

      Hey awesome I'm glad I can help you out! Make sure you check out all of my PM videos at engineer4free.com/project-management the EVA ones are numbers 33 - 38

  • @Dimitrapet
    @Dimitrapet 5 років тому +1

    Thank you very much! All videos are well and simply explained. Greetings from Greece.

  • @tannkimhing9177
    @tannkimhing9177 6 років тому +9

    I hope this would help me with my Examination tomorrow

  • @PhanCpants
    @PhanCpants 6 років тому +2

    Thank You! This video actually made sense compared to my textbook!

    • @Engineer4Free
      @Engineer4Free  6 років тому +1

      hahaha glad I can help :p

    • @febeangulo4844
      @febeangulo4844 6 років тому +1

      @@Engineer4Free Of course it made sense haha... This guy is the master of PM. I've learned more from him than from my whole Master's degree program in Project Management hahaha

    • @gsxrguru2
      @gsxrguru2 5 років тому +1

      Very helpful video for a particular capstone! =)

  • @aewcontrol2984
    @aewcontrol2984 2 роки тому

    Perfect and to the point, very lean

  • @ahmedzayed6301
    @ahmedzayed6301 4 роки тому +1

    Thank you so much , that was so tough for me to understand before watching these videos

  • @Fzegeye
    @Fzegeye 2 місяці тому

    This is much more explanatory. Clear. Neat. Great work! So now EV is BCWP and Pv is BCWS. Right?

  • @rajatmishra1561
    @rajatmishra1561 3 роки тому +1

    best video on EV

  • @youngkim5909
    @youngkim5909 4 роки тому +2

    2:27 you can't start activity E before completing D. D is a predecessor to E. If D is behind schedule, the whole project is behind schedule.

    • @Engineer4Free
      @Engineer4Free  4 роки тому +1

      Yes. Note that on this diagram "7" represents both the end of day seven, and the beginning of day eight. If the project was on schedule, at this moment of reporting, we were expecting D to have been finished (at the end of day seven) and E to just be starting (at the beginning of day eight). The whole project will indeed finish late unless somehow a day is saved during activity E.

  • @RayOnRae95
    @RayOnRae95 9 років тому +16

    Ooh now my exam doesn't seem so hopeless!

  • @mohand088
    @mohand088 3 роки тому

    Thank you for the explanation.
    Just to clarify BCWP AKA Earned Value (EV) ; BCWS AKA Planned Value (PV)

  • @aswanichittilla8745
    @aswanichittilla8745 5 років тому +1

    Really liked the example

  • @jacqueshollands5630
    @jacqueshollands5630 Рік тому

    Excellent example

  • @theChrisCroft
    @theChrisCroft 5 років тому +1

    Does a SPI of 0.5 mean that you would predict that the whole project is going to take twice as long as planned? Can you use it to forecast finish date, at least approximately? Is that the point of SPI / what it is used for?

    • @Engineer4Free
      @Engineer4Free  5 років тому +1

      Yes, you are right in what you're thinking. Check out videos 33 - 38 here: engineer4free.com/project-management for a few more explainers on SPI etc, and some ways that you can use it to make predictions too.

    • @theChrisCroft
      @theChrisCroft 5 років тому

      @@Engineer4Free - this is great, at last I've found someone with a brain who really understands SPI! There is something that's been worrying me about SPI for a while and I really hope you can help. either I've missed something or the whole world of PM has missed something...! So, SPI is based on VALUE of work planned / performed, so the degree of lateness depends on the VALUE of what you should have done but haven't. so if the part you haven't done is something expensive (e.g, painting with gold paint) then SPI makes you looked later than if the part you haven't done is something cheap (e.g. painting with ordinary paint). That's right isn't it? But this is clearly crazy - because it shouldn't matter whether the painting I should have done but haven't is with gold or other paint, it's still the same degree of lateness. The forecast finish date should still be the same. Why should COST, or value, affect the forecast finish date? Does this question make sense? If not I can send you an example? I'd love to get to the bottom of this, I'm not a fool, I've thought about it a lot, and I think there is a flaw in the whole SPI methodology. Help me to change the world of PM thinking on this!!

  • @chakradharvangara3285
    @chakradharvangara3285 3 роки тому +1

    Very nicely explained !!

  • @jms3942
    @jms3942 5 років тому +5

    I wonder why they wrote the textbook in such a nonsense format. Great job sir

  • @jboone3745
    @jboone3745 9 років тому +2

    Great example, and thank you for this.

    • @Engineer4Free
      @Engineer4Free  9 років тому

      +Joe Cooper Thanks for the feedback! Glad to hear its making sense!

    • @jboone3745
      @jboone3745 9 років тому

      You're so welcome, I can't understand why so many people who I know have seen this, but refused to show application for your work.

  • @tsp8855
    @tsp8855 3 роки тому +1

    excellent, very well explained!

  • @kwameadjei3964
    @kwameadjei3964 Рік тому

    Well explained. Thank you

  • @eminabdullayev8959
    @eminabdullayev8959 7 років тому +2

    Great video, it would be good to add here, ETC and EAC for full picture...

  • @khalidmuhammad2798
    @khalidmuhammad2798 4 роки тому +1

    I have a quick question. On the reporting date if you are behind on some of the tasks but you have completed some of the tasks which were planned to be completed after the reporting date. Can you take credit of that work to compensate for the poor SPI or CPI on reporting date?

    • @Engineer4Free
      @Engineer4Free  4 роки тому

      Yeah it would skew it in the positive direction, where as being behind skews it in the negative direction

  • @rohangeorge3553
    @rohangeorge3553 4 роки тому +1

    Thank you, great help

  • @katlarabi-tchalaia2264
    @katlarabi-tchalaia2264 3 роки тому

    Thank you, that was very useful

  • @rizukiichirou4272
    @rizukiichirou4272 4 роки тому +1

    thanks sir, very helpful

  • @babitapitta
    @babitapitta Рік тому

    I am working on as assessment for EVA, we were given an excel sheet with calculations. Total plan for 6 months with dollar values for BCWS are given, ACWP and BCWP till September are given. In the sheet given to us rolling status is provided and calculations for SC, SPI, CV, CPI are done based on the rolling status. In your example you have not taken that rolling status, now I am confused if I should do rolling status or not. and If i should consider the calculations for BCWS till October or till only September. Please help. Please let me know if you have not understood my concern.

  • @amiyo97
    @amiyo97 7 років тому +1

    thank you sir.. you really help me so much :)
    thumbs up for you sir

    • @Engineer4Free
      @Engineer4Free  7 років тому +1

      Thanks for the comment :) glad the videos are helping!

    • @amiyo97
      @amiyo97 7 років тому

      I've been going through hours of reading lecture notes to understand earned value management.. But it took me just 10 minutes to understand this just by watching your video.. Thanks again :)

    • @Engineer4Free
      @Engineer4Free  7 років тому +1

      No worries! If you haven't already, make sure you check out engineer4free.com/project-management for the rest of the videos :)

  • @YusufKhan-sp6ii
    @YusufKhan-sp6ii 5 років тому +2

    Bcwp of activity C would be 33% of 800 or 1200? I think it should be 33% of 800 because we are calculating the performance of 7 days not 8 days,,, am I correct ? Please answer me.

    • @Engineer4Free
      @Engineer4Free  5 років тому +1

      Mmmm it should be 33% of 1,200. The reason is in the wording. The budgeted cost of work performed. One third of the work for a three day project was performed at the time when the report was taken. Ignore the cost that was actually incurred, because we are concerned with the budgeted cost. The budgeted cost of this activity is 1200 in total, or 400 for each day. The digested cost of the work that was actually performed is 1200/3=400. The budgeted cost of work performed is not the same as the actual cost of work performed, that would be 500 for activity C.

  • @RicoThomas-vj4rb
    @RicoThomas-vj4rb 8 місяців тому

    Hi I just wanted to ask if activity C was 80% done, would it’s BCWP be the same as the BCWS because by the time the report date has been reached the same amount of work has been done as the BCWS?

  • @juancarlosotero5620
    @juancarlosotero5620 7 років тому

    Really great video Thanks for your contribution. Brilliant

    • @Engineer4Free
      @Engineer4Free  7 років тому

      Thanks for writing! Make sure you check out engineer4free.com/PM for the rest of the tutorials :)

  • @shakesrear7850
    @shakesrear7850 3 роки тому

    What pen are you using kind sir? How are you able to write so accurately!?

  • @nadeemasif2406
    @nadeemasif2406 Рік тому

    Sir what is difference earned value approach, earned value analysis, and earned value Management

  • @junedshaikh2964
    @junedshaikh2964 3 роки тому +1

    For activity C, how did we determine that only 33% of work is completed..is there a tool or calculation?

    • @Engineer4Free
      @Engineer4Free  3 роки тому +2

      We are the off-site Project Manager, and the person in the field has delivered the report in the bottom left corner to us. Because we are at the end of day 7, we expect 66% of activity C to be completed based on the original Gantt chart, but they are telling us that in reality things are moving slower, and it is only 33% done.

    • @junedshaikh2964
      @junedshaikh2964 3 роки тому

      @@Engineer4Free Yes. It is says on the chart 33% complete. Also, the expected work to be completed was 66%. if the work is not completed to 66% as estimated... how do we conclude it is 33%, 40% or 10%. How did the field report or any report can calculate % of work completion unless not assumed.

  • @chris-12500
    @chris-12500 9 років тому

    Great video and well explained. Thanks

  • @Florenstiya
    @Florenstiya 8 років тому +1

    thank you! i think i will pass my exam now

  • @LawDude-hb2vt
    @LawDude-hb2vt 4 роки тому +1

    THANK YOU SO MUCH.

  • @El.mosquito.
    @El.mosquito. 4 роки тому +1

    Good video. Question: why did you record BCWP for Activity B as 1200 if the incurred cost was 1400? Who pays that 200?

    • @Engineer4Free
      @Engineer4Free  4 роки тому +1

      Thanks! Assume our project is to build a house, and that activity B is painting the walls. The painters told us that it would cost $1200 before they got started. But on day 7, we get a report back that for some reason $1200 wasn't enough, and it actually cost $1400. Like for example if the painters are our actual employees, and we pay them $100 per hour, and they thought it would take 12 hours, but it actually took them 14 hours, then we really have to pay them $1400, because that's what employers do. So we (the project owner, or manager) have to pay the extra $200. Thats just one example of why the cost of work scheduled may be different from the actual price paid for that work. Hope it clears it up!

  • @OO-lh7nt
    @OO-lh7nt 2 роки тому

    First of all thank you for your describing. Is it different by using 50-50 rule of calculation the BCWP (ev)?

  • @mohanparthasarathy1777
    @mohanparthasarathy1777 4 роки тому +1

    Great Video

  • @darkbroseph
    @darkbroseph 8 років тому +4

    Thanks a lot!... God bless!

  • @chriso7956
    @chriso7956 6 років тому +1

    Very Helpful! Thank you

    • @Engineer4Free
      @Engineer4Free  6 років тому

      You're welcome Chris! Thanks for the comment =)

  • @anthoniocassim6748
    @anthoniocassim6748 Рік тому

    Very helpful, thx a lot

  • @gnitri
    @gnitri 9 років тому +17

    Great Tutorial
    by the way Activity C BCWP = .33 * 1200 = 396

    • @karlkerr7348
      @karlkerr7348 6 років тому +1

      1/3 x 1200 = 400

    • @AndresTorres-jv6dh
      @AndresTorres-jv6dh 6 років тому +1

      the 4 lacking units, are hidden in the aproximation of 0.3333333.......

    • @sergnextdoor5213
      @sergnextdoor5213 6 років тому +1

      Agreed, i can see his perspective because he uses the # of days to conclude his EV. To be exact, its 396 because only 33% of the activity has been completed thus earning $396 USD. not 400.

  • @carsnation5860
    @carsnation5860 5 років тому +1

    Thanks that helped alot ❤️

  • @miazuo5095
    @miazuo5095 4 роки тому +2

    hi~I am wondering how to know the report day is 7?

    • @Engineer4Free
      @Engineer4Free  4 роки тому +1

      That would be given to you in a problem, as well as the level of completion of certain activities, and from there you can assess the situation.

  • @elaniece
    @elaniece 3 роки тому +1

    why didnt you fill out the rest of the chart? that was the main information i needed

    • @Engineer4Free
      @Engineer4Free  3 роки тому +1

      See videos 34 and 35 here: engineer4free.com/project-management

  • @davidh266
    @davidh266 7 років тому

    what would you do if a question says
    for example Activity budget % complete actual cost
    F 600 0 200
    so that even though the activity hasn't started 200 is spent

  • @SoNuz14
    @SoNuz14 5 років тому +1

    BCWS of activity D will be 200 instead of 400

    • @Engineer4Free
      @Engineer4Free  5 років тому +2

      Mmmm BCWS stands for “budgeted cost of work scheduled.” By the time of the report, D was scheduled to be completed. And at $200 per day, $400 of work on activity D was scheduled to be complete. So the BCWS is $400. The BCWP is $200 (which is the budgeted cost of work performed), as only $200 of budgeted work was completed by the report date.

  • @fluturaperdja8719
    @fluturaperdja8719 6 місяців тому

    why does activity B have Incurred cost of 1400 and not 1200?

  • @karlkerr7348
    @karlkerr7348 6 років тому +1

    With this example it doesnt explain where the % completes come from. What determined the task D to be 50% for example? Whats the basis of measurement of this task performance?

    • @Engineer4Free
      @Engineer4Free  6 років тому +3

      At 0:08 I mention that it is from a field report. IRL, a schedule for a project is made, then people attempt to carry it out, and sometimes it goes faster or slower or costs more or less than originally planned. Most of my PM videos revolve around planning before execution, but this video is an example of how to interpret the field results that are not determined by us, but by the actual performance of other people/circumstances. So the a person in the field reported to us that Task D was half done, and they would have their own criteria, for example, it could be as easy as they are building a wall and have half of it up, or for a more complicated task it might not be so easy, but that would entirely depend on the context. This video is just about how to take someone else's field report and interpret the status of our active project. Hope that helps clear it up.

  • @rpacook
    @rpacook 3 роки тому

    If the activity is 100% completed with a BCWS of 4, an ACWP of 6 and a planned duration of 2 days what would the BCWP be?

  • @lilaresearch3162
    @lilaresearch3162 2 роки тому

    Thanks for this video! Really helped me alot. I have one question: Why do activity C and D are expected to end on day 6?

  • @malsalihi1938
    @malsalihi1938 Рік тому

    Given a total quantity of 12000 CY of concrete to be placed, at a cost of $400/CY. At the 40% schedule point, the contractor placed $2,160,000.00 worth of concrete. What is the CV? Can you help solve this problem. Thanks

  • @arunraj_r
    @arunraj_r 5 років тому +1

    Thank you so much

  • @alfredmarx7438
    @alfredmarx7438 2 роки тому

    Well exlained

  • @Daniela-xc7ds
    @Daniela-xc7ds 3 роки тому

    Hi, can I considere Deliverables or Objectives instead “activities”? Or different projects instead activities? I mean, if I am working with a portfolio. Or should I do the maths with weighted average?

  • @eireneestellia8615
    @eireneestellia8615 2 роки тому

    Hey, this is really helpful! But, can I ask you a question? For the BCWP in the activity C, why can't we just calculate it as 33% multiply by actual cost? I'm genuinely curious and maybe miss some of details. Thank you in advance!

  • @priyankathakur5223
    @priyankathakur5223 6 років тому

    Gr8 video...it helped me a lot😍😘

  • @ashleymaddox5511
    @ashleymaddox5511 8 років тому +1

    This is a GREAT video. Is there anyway for me to save this?

    • @Engineer4Free
      @Engineer4Free  8 років тому +1

      +Ashley Maddox Thanks for the compliment! I currently don't have any options for downloading, you'll just need to favorite it on UA-cam or bookmark the website: www.engineer4free.com/project-management

  • @odelalo8492
    @odelalo8492 2 роки тому

    Hi, suppose if Activity B is only 66.6% complete, is it 3 days behind schedule from the reporting date, or do I consider it as 1 day (the unshaded part)?

  • @fcoatis
    @fcoatis 7 років тому +1

    Great video. One Question. How would I deal with the incurred cost of task C $500 in MS Project?

    • @Engineer4Free
      @Engineer4Free  7 років тому

      Hey thanks for watching and commenting. It's been too long since I used MS project so I can't remember the exact process. Sorry, good luck!

  • @yayatoure3461
    @yayatoure3461 8 років тому

    Question though. How do you deal with earn value and fixed costs and cost resource?

  • @trevorrabey736
    @trevorrabey736 6 років тому +1

    The video does not properly define what "actual % complete" is. What is the numerator and denominator? It is apparent (maybe) that "actual % complete" = actual duration/baseline duration, or actual duration/total duration, where total duration = actual duration/(actual duration + remaining duration). What happens if Task A took 3 days actual instead of 2 days? It is still finished, but is the "actual % complete" 100% (ie 3 days/3 days) or 150% complete (ie 3 days/2 days)? Well, it can't be 150%, has to be 100%.

    • @Engineer4Free
      @Engineer4Free  6 років тому +1

      This is a pretty simple model that is designed to compare anticipated results with actual results. You can check out a few other videos that I did on the topic, they are videos 33-38 here: engineer4free.com/project-management . They are all at an introductory level.

  • @salmagadal3417
    @salmagadal3417 Рік тому +1

    i need help my table contains optimistic most likely and pessimistic days + my exam is soon please help

    • @Engineer4Free
      @Engineer4Free  Рік тому +1

      See the PERT section (the last section) at engineer4free.com/project-management

  • @rasmank
    @rasmank 9 років тому

    Thanks for sharing. really helpful

    • @Engineer4Free
      @Engineer4Free  9 років тому

      Martin Karuiru Glad you found it helpful!!

  • @7usinmansour908
    @7usinmansour908 6 років тому

    thank you ,,, great work

  • @sanaahmed8464
    @sanaahmed8464 5 років тому +1

    Thanks alot

  • @dark_bull67
    @dark_bull67 10 місяців тому

    How did bcws of activity d come 400, shouldn't it be 200 if bcws of activity c is 800, you calculated c to be 2/3. So shouldn't d be 1/2 of 400

  • @pbrpb4735
    @pbrpb4735 8 років тому +1

    Hi Engineer4free, may I know what is the whiteboard tool you are using. Is it something to WizIQ. Thanks in advance.

    • @Engineer4Free
      @Engineer4Free  8 років тому

      Hey, you can find a full list of the software/hardware that I use at www.engineer4free.com/tools

    • @pbrpb4735
      @pbrpb4735 8 років тому

      Thanks but actually wanted to know the tool for recording video screen

    • @pbrpb4735
      @pbrpb4735 8 років тому

      Got it! Camatasia. Thanks.

    • @pbrpb4735
      @pbrpb4735 8 років тому

      hi, how did you get the table up the screen. I dont find options. Or is it available only in subscription version.

    • @Engineer4Free
      @Engineer4Free  8 років тому +3

      I didn't use any subscription software to make this video. Sketchbook Express came free with the tablet, and Camtasia for Mac was a one time purchase. I just made the tables in Google Docs, took screenshots and pasted them into the drawing program.

  • @rajivdahal9260
    @rajivdahal9260 3 роки тому

    Thanks

  • @angelikaa5500
    @angelikaa5500 6 років тому

    Hi, which theory literature peer review you used or is it OK to share ,if you know? Need for my writting module. Thanks

    • @Engineer4Free
      @Engineer4Free  6 років тому

      The method used in this video was taught to me by a professor teaching project management at the undergraduate level in a Canadian university several years ago.

  • @sergnextdoor5213
    @sergnextdoor5213 6 років тому +2

    so I have my CAPM from PMI and looking for an internship in project management. Any help in landing one? anybody want to give me a chance?

  • @xsauce3858
    @xsauce3858 6 років тому

    over budget or under budget ?

    • @Engineer4Free
      @Engineer4Free  6 років тому +1

      10:26 this project is over budget and behind schedule

  • @dice856
    @dice856 8 років тому

    Thank you

  • @Satyammishra-bf4ty
    @Satyammishra-bf4ty 9 років тому

    thankyou...:) great work

  • @renzy407
    @renzy407 9 років тому

    helpful. well explained. :)

  • @Daniela-xc7ds
    @Daniela-xc7ds 3 роки тому +1

    In the real life, What are the possible reasons for C had incurred Cost of $500? Instead of 400.

    • @Engineer4Free
      @Engineer4Free  3 роки тому +2

      Ummm, could be absolutely anything, because this is a generic activity with no information whatsoever. If Activity C was "building a fence", but a tree fell on the fence during construction and smashed some pieces, and they had to buy more. For example.

  • @andujarjj
    @andujarjj 6 років тому

    PLEASE MAKE MORE VIDEOS!

    • @Engineer4Free
      @Engineer4Free  6 років тому

      Hey Jei thanks for the comment. More are in the works

  • @taherbakry4174
    @taherbakry4174 5 років тому +1

    Where is the (Earned Value) Value?

    • @gummymansg
      @gummymansg 5 років тому +1

      Earned Value (EV) is the Budgeted Cost of Work Performed (BCWP)

    • @Engineer4Free
      @Engineer4Free  5 років тому +1

      Thanks Matthew!

    • @gummymansg
      @gummymansg 5 років тому

      @@Engineer4Free You are most welcome. I have shared your video with my project management students after my class as additional materials. Thanks for making EVM simple to understand.

  • @saeedtalib8358
    @saeedtalib8358 8 років тому

    taking BCWS of activivity c is 800.. why not its completion percentage is 66%... Same case for activity D... having confusion just in thses two activities,,,,,,

    • @karlkerr7348
      @karlkerr7348 6 років тому

      % completes are physical % complete not duration % complete.

  • @CecilDSouza
    @CecilDSouza 8 років тому

    This was explained well but the pace of speaking was a bit too fast. Also, you have failed to use the terms PV and EV apart from BCWS and BCWP which is important as not everybody uses the latter.

  • @pranaychauli233
    @pranaychauli233 Рік тому

    How BCWS for Activity D is 400 when 50% work is completed. Total budget 400. 50% work completed so ACWP is 200.

  • @drabdussalamshibani5572
    @drabdussalamshibani5572 8 років тому

    Activity C BCWP ???????????

    • @ChumePeterNhanombe
      @ChumePeterNhanombe 8 років тому

      +Abdussalam Shibani its 3 days * 33% = 0.99, one day practically, so cost per day for activity C is 400

  • @belayyimenutube1330
    @belayyimenutube1330 7 років тому +1

    exellent

  • @sunnywoo2268
    @sunnywoo2268 5 років тому

    EAC=BAC/CPI so what is BAC ,and how to calculate it ????? BAC BAC``````

    • @Engineer4Free
      @Engineer4Free  5 років тому

      Estimate at completion (EAC) = Budget at completion (BAC) / Cost performance index (CPI). These are used for forecasting, not reporting. Very similar thought process though. Just rather than knowing the actual money spent at the end, you are using knowledge from past performance to estimate how much money will actually be spent at the end. If you google EAC=BAC/CPI a few decent resources pop up.