Critical Path Method with Dummy Activity | CPM Network | Critical Path | Total Floats & Free Floats
Вставка
- Опубліковано 6 жов 2024
- Here is the video about CPM (Critical Path Method with Dummy activity)
In that we have seen how to construct CPM network, how to determine the critical path and project completion time, calculation of Total float and Free float.
To Download PDF: drive.google.c...
Link for ► • CPM - Critical Path Me...
Link for ► • Playlist [Operation Re...
Follow Us On😃:
===============================
Instagram: / kauserwise_official
LinkedIn: / kauser-wise-a422b231a
===============================
►Main Channel: / @kauserwise
►KauserwiseQT: / @kauserwiseqt
►Kauserwiseaccounts: / @kauserwiseaccounting
►Kauserwise Tamil: / @kauserwisetamil
===============================
👇List of Subjects and it's Play List in English👇
Link for ► • Playlist FM Financial ...
Link for ► • Playlist [Financial ac...
Link for ► • Playlist [Corporate ac...
Link for ► • Playlist [Cost and Man...
Link for ► • Playlist [Operation Re...
Link for ► • Playlist Statistics vi...
Thanks
kauserwise®
I cant thank you more ma'am, only with your help I passed quantitative techniques in my MBA. Thank you so much.
No words to say about your lecture mam, you're my role model because in my early high school days I had one maths mam and higher secondary level another one mam and my UG and PG Two mam and one Sir But Now you are also my Best(GURU in Tamil) Teacher. Now I'm also Professor I'll teach your OR video to my students.Thankyou so much madam......
மிக அழகாக புரியும்படியாக இருந்தது. நான் படித்தது தமிழ் மீடியம் ஆனாலும் நன்றாக புரிகிறது உங்கள் பணி தொடர வாழ்த்துக்கள்.
நன்றி
@@kauserwise neenga tamizha
I bow to you on how simple you made these lectures to me
am thanking to kauser wise i was civil engineer and i started Master of cpm so i visited these lessons last months and it helped me more. thank you kauser. you really amazing, educated and professional. i would like to be your student. greeting you from Somalia.
Thank you for your comment, All the best....
Mam, the way you teach, leave no room for doubts. Thank you very much.
Very good and easy to understand. Thank you.
You explained everything very deeply also your method of teaching is awesome, You cleared all the points related to the topic, thank you so much for this effort!
Thank you
Soothing handwriting and nice presentation mam. I'm so happy that I saw this channel. THANKYOU SO MUCH..
Since 11th standard I'm learning from you now I'm pursuing CA and bcom. Grateful :)
This video is helpful even in 2021 with supperb explanation ....
What makes the video perfect is before solving any problem using any formula at first you are explaining the formula definition then formula and next usage which makes to remember the flow of the problem and the concepts too ...
And with your simple english and detailed explanation adds more value to the video ...
THANKS FOR THE VIDEO ...
LOTS OF LOVE AND CARE FROM HYDERABAD ...
Thank you mam your classes have been a great relief during lockdown
Thank you madam, your lectures helped me to clear exam in short inverval of time
You're actually the best in lecturing 👏 I just love your lecture ❤️. Thank you
Thanks you so much from the bottom of my heart mom ❤❤
Mam! Thank you! You helped me in clearing all my doubts within an hour. You're one of perfect lecturer
Nice explanation ma'am I was confusing with these topics but after listening to your lecture it's completely Clear for me THANKS YOU ma'am 🙏❤️
Thank you so much for all of these videos, you literally saved me. I couldn't understand a thing before watching your videos and now I'm good :)
Thank you so much ma'am for all these lectures, they are life savers for us students, specially in this lockdown. Thank you!
I had completed my MBA and I thank you for helping me out in financial and cost accounting topics.
Its been 3 years and suddenly your video of journal entries clicked in my mind(i dont know how) but i went searching you on UA-cam but i was not able to recollect your channel name.
so there was a video having thumbnail similar to what i was searching and i got that but to my utter surprise it was your video but there was only one of it..
But luckily I got your channels name from there only.
I am happy now.
Thank you from the bottom of my heart as your video had helped me and my batch mates immensely.
Keep teaching Madam
Thanks once again!!
**and name of that fake channel is "amjed anver" he has uploaded your teaching video and got 66k views on the same.**
Hi madam, the way you are explaining the things are very clear in this video. I am doing CMA Final. This video helps me a lot to know the CPM Network. Thank you for the amazing video.
Thank you so much mum😭🙏♥️♥️God bless you.
Your teaching style is great. Thank you
I love your lecturing method mam , I enjoy your videos continue great work. Currently am doing project planning , ,,, wow am enjoying your lectures
Absolutely very good teaching madam. So steady and clear it is. Excellent madam👍.
Thank you.
Thank you so much to your channel🙏🙏🙏Your are helping students a lot in learning this subject. I'm really feeling thankful to you & your videos. That has helped me a lot in getting good Mark's in my semester result. I really felt so doubtfull before watching your videos because in my college they didn't explained this shortcut methods. After watching your videos I got confidence to write my exam & got good grade in that. Thank you so much🙏🙏🙏 I definitely suggest each & every student to use this platform👏👏
I don't know what to say but thanks for explaining in such a beautiful manner!!
Aditya can u clear my doubt which is
In connection network why there is joining of J and I activity which is the last node 8
Mam can u put a video for comparative balance sheet..common size balance sheet...common size income statement in management accounting........and job sheet,batch costing,contract costing in costing......your all videos are superb mam...very usefull for me..thankyou mam
I am from jammu kashmir and prepare for competitive exam this is very helpful THANKS MAM
Excellent madam to teach in clear manner
HAPPY TEACHER'S DAY ma'am
THANK YOU SO MUCH ma'am FOR ALL YOUR BLESSINGS.
🙏🏻🙏🏻🙏🏻🤗🙏🏻🙏🏻🙏🏻
Thank you Dear
mam aapne bohot easy way se samjha diya .....thank you
Thank you so much ma'am your explanation was very helpful for me ...
You have explained this so beautifully thank you.
Very clear explanation and presentation , was long but worth it
In this lecture you showed dummy activity pointing from node three to node two..but as per I know arrow should always show smaller node number to greater one. Can you please elaborate on this?
My only hope your lectures mam♥️when I don't get operation research at all.
Heartfully thank you so much mam❤️..really great lecturing skills mam..I hope be happy if where you are🥺
Mam do videos on these topics
1) Account current
2) Average due to date calculation
3)Sale of goods on approval or return basis
4)Bill of exchange endorsement and other various conditions
great you are the assets of education sector maam
Thank you...
Pls do schedule 3 final accounts, your lectures are very helpful
thank you so much for your teaching with clear explanation
Thank you very much mam❤so glad i found this channel❤✨simple and easy to study ✨
Mam can you upload another dummy problem 🙂one more time because this dummy type of network problem is very hard to understand
Thank you 😊 Surely I will try to upload👍
@@kauserwise Thank you mam ❤️😀
This same question was asked by university in last year,, thank you
Which university
thnq so much mam
may you be happy always❤
Thank you
Thanku very much mam clear explanation 🎉🎉
Thank you mam this vdo helps me a lot🙏🙏
Good explanation madam ...i had clear all my doubts about draw a network diagram
Ma'am ap bot acha padhate ho.mujhe ache se smj aa jataa h ma'am ap plz PERT ki problem solve krne ki video bna do.
Pls see this Playlist I have already uploaded [Operation Research video collections]Kauserwise: ua-cam.com/play/PLabr9RWfBcnoLyXr4Y7MzmHSu3bDjLvhu.html
Thank you ma'am
Amazing teaching with easiest and clear method
Sir thank you it's good teach
very well explained madam. Thanks a lot
Thank you so much mam clear explanation easy to understand🙂👍
Your videos helps alot......
Thank you sooooo much..
Nice teacher, impressive method, conceptual clarity
Thanks for your valuable teaching time for us,i have seen your youtube videos related to OR subject,you thought us with clearing all doubts such a perfection never seen and with such clarity,Thank you once again mam🙏🙏
#Worth watching
Great confusion in dummy activity cleared.
Hi Perumal ,can u clear my doubt which is
In connection network why there is joining of J and I activity which is the last node 8
According to my professor, we don't consider dummy activity in calculation, whom to believe or there is something to know about somewhere I will consider it somewhere not?
Thanks alot Kauserwise....
Thanks I understand well
(7)12/12 and (8) 22/22 why it is not critical activity
God bless you Ma'am....
Thank you mam kindly explain about inventory models with problem that will be more helpful
Thank you mam for this great video
Thank you very much,
Wonderful explain for useful mam tq 👍
Hello ma’am! I’ve been following your channel for sometime now & I needed your help in solving OR related problem. Can you please help me? I’ve my exam on 25th of August
Due to lockdown we didn’t have proper classes. Please consider this! Thank You🙏🏻
too helpful, thnkew mam
Thank you so much mam🌻🎈🎈
Thanks very much ma'am
Please it will be of help as well
If u teach about Time series Analysis and Price Index number
Thanks so much for ur help so far
Hello madam can you please upload a video of inventory model , simulation , waiting model , probability for mba students . Your videos are very useful for us .
Mam please do video in business taxation and income tax 2...
Very professional !!!!!
Very useful and informative mam
Hello Mam Please Upload the video about Queing theory
your videos Are Very Much Help Full To me.
Thank you 🌟💯
Tq so much ma'am
Mam please solve a problem on sequencing
You lecture well Ma'am. Please can you upload a video on RANKING OF ACTIVITIES? THANKS
Mam in this video ur take the big or large problem plz update direct problem like activity (1-2).(1-4) and duration in a day
Great lesson
Thank you mam
How about the arrow for the -> 2 or should it be ->3?
Thanku so munch mam..
Awesome Teachings
i like your blue pencil very cool
Why node B consider for EST ??
For activity -3 (through dummy activity )
EST- EST NODE 2+ dummy ??
Please tell
Mam please upload video advanced corporate accounting, advanced cost accounting...
madam you showed a dummy activity pointing from node three to node two..and also node 6 was pointing to node 7,other sources state that an arrow should always show a smaller node number pointing to a greater one. Can you please elaborate on this?if any 1 can explain this to me i will really appreciate it
Should we go for dummy line while calculating ESJ if the B is greater than A
Mam please upload video for Redemption of preference shares and Final accounts of companies
Mam please add bank accounts profit and loss / balance sheet in corporate accounting mam
Ma'am shld the diagram be the same shape as shown are that can vary based on individual we hv exam ton i request you to please reply 🙏
Hi mam pls teach us leverage chapter & also resource levelling in CPM . It will be very useful for all .
outstanding
Please upload video on statistics of MA economics on hypothesis testing Z,x2,T&f distribution. Please reply
Mam ! in the prblm u have started the activity c from node 2 , I'm getting confused with this part , actually there are two possibilities as we can start from node 3 also.But why you choose node 2 as starting for activity c.If we can start from any of those 2 ways, we will get the same end result ? pls clarify mam. PLEASE
Yes, mam, please clarify this
Madam please explain goal programming concept and replacement problems
Mam which playlist should I watch for construction managements. Within 2 days i have university exam.
Thank u so much mam