Bored Piling Job Safety Analysis (JSA)

Поділитися
Вставка
  • Опубліковано 1 гру 2020
  • After Watching This Video You Will Be Able to Prepare JSA for Bored Piling
    Click Here To Download JSA - www.safetymgmtstudy.com/2022/...
    JSA No:
    JOB TITLE: Piling & Concreting Works for the construction of Foundations/Building
    S.NO
    JOB STEP
    HAZARDS
    CONSEQUENCES
    CONTROL MEASURES
    1
    Mobilization of equipment & Materials
    Involvement of unskilled personnel
    Personal injury/Accident
    Trained & skilled staff to be authorized for working
    Ensure JSA briefing & Daily TBT to all workforce prior to commence activity
    Unauthorised/ uninspected equipment/tools at site
    Failure of equipments & tools.
    Only inspected Equipments/Tools must be allowed at work site
    Use right tools for right job
    Slip, Trip & fall
    Slip and trip can result musculoskeletal injuries & Fractures.
    Take care of overhead structure/pipe racks
    Keep access/walk ways always clear from any obstruction
    Inclement weather condition
    Workers can hit by Piling machine, equipment and get injured due to fog.
    Stop work in case of any inclement weather conditions ( fog etc.)
    Restrict movement of heavy vehicles/equipments in fog
    2
    Piling
    Uncertified piling Machine & Operator,
    Collapse of tripod,
    Piling equipment/machine failure.
    Workers can injure by tripod.
    Pile machine & its operator should be certified
    Stand the tripod properly, tripod to be fixed on ground properly.
    Keep away all unauthorized people during movement of heavy vehicle/equipments
    Be careful of nearby live areas
    Ensure Close HSE monitoring /supervision
    Improper barricade
    Entry of unauthorised person.
    Fall of person in Pile.
    Barricade the working area properly
    Sling broken, load drop
    Fatal/injury due to load drop.
    Ensure proper & inspected accessories being used for drilling
    Ensure that drilling bit is properly fixed with locking pins
    Keep away during drilling operation
    working area should properly barricaded
    Noise
    Can cause deafness & psychological imbalance.
    Provide Ear Plug
    Slip, Trip & fall
    Slip and trip can result musculoskeletal injuries & Fractures
    Ensure proper stacking of all materials at site
    Keep access/walk ways always clear from any obstruction
    Ensure proper housekeeping of workplace all the time
    Inclement weather condition
    Workers can hit by Piling machine, equipment and get injured due to fog.
    Stop work in case of any inclement weather conditions (Rain, storm, fog etc.)
    Restrict movement of heavy vehicles/equipments in rain/fog
    Fire & explosion
    Loss of life & Burn due to fire.
    Ensure availability of inspected fire extinguishers at site
    3
    Lowering of Steel Cage structure
    Personnel hand injury while handling with steel
    People under suspended load
    Unbalancing of load
    Personal injury.
    Hit by suspended load which can result in injury.
    Ensure Involvement of skilled labour
    Ensure use of proper PPE’s
    Area should be properly barricaded during lifting operations
    Poor Housekeeping.
    Poor housekeeping can create unhygienic work place which can leads to growth of insects.
    Ensure proper stacking of all materials at work site
    Maintain good housekeeping all the time
    4
    Concreting of Piling
    Inappropriate PPE’s/Tools during concrete work
    Slip of tools can injure workmen due to inappropriate ppe and tools.
    Use of appropriate PPE’s during concrete
    Ensure use of inspected tools for the right job
    Availability of fresh water at site
    First aid box should be in place at site
    Skin contact with concrete or other chemicals
    Skin contact with concrete can cause blisters, dead or hardened skin.
    5
    Working at night shift hours
    Poor visibility at night hours
    Tripping of workers due to Poor visibility
    Ensure proper lighting.