VIDEOMANUAL SACE Tmax T7M Shunt opening, closing and undervoltage release - SOR ,SCR, UVR

Поділитися
Вставка
  • Опубліковано 9 лис 2024
  • Videomanual shunt opening, closing and undervoltage release for Tmax T7M - SOR , SCR, UVR. For more information, please visit new.abb.com/low...

КОМЕНТАРІ • 12

  • @juandagali
    @juandagali 11 місяців тому

    Excelente este canal hacía falta localizarlo

  • @babulkumardalai8604
    @babulkumardalai8604 2 роки тому

    L alaram indication is blinking what is the problem?

  • @erwinsarabia1993
    @erwinsarabia1993 4 роки тому

    very informative.

  • @rotimiopeyemi8644
    @rotimiopeyemi8644 Рік тому

    How can I get trip contact

  • @বাংলাআমারমাতৃভাষা

    which point for which coil?

    • @tayyrenn
      @tayyrenn 5 років тому +1

      From what I found, D1/D2 are for the UVR, C1/C2 for the SCR, and C11/C12 for the SOR

  • @maurafs
    @maurafs 3 роки тому

    Excuse me. Does anyone know what the position of the closing coil is: C1-C2; C12-C13 or D1-D2

    • @larsonfraud4156
      @larsonfraud4156 3 роки тому +1

      For a Tmax T7, the ABB drawings show C1-C2 are the closing coil connections

    • @congvan9556
      @congvan9556 3 роки тому

      @@larsonfraud4156 how about trip coil ( from trip unit ), do you know

    • @larsonfraud4156
      @larsonfraud4156 3 роки тому +1

      @@congvan9556 C11-C12 are connections for the (shunt) trip coil

    • @congvan9556
      @congvan9556 3 роки тому

      @@larsonfraud4156 tks bro