No Nothing Under ground here. The metro pillars will be on the median of service road and ORR. So the Foot over bridge was dismantled recently. Work should start sooner.
it will take another 5 years for the entire project to be completed. Airport to Hebbal with a distance of 25 kms Hebbal to Tin Facory distance is 17 kms Tin Factory to Marathahalli distance of 8 kms Marathhalli to Silkboard distance of 15 kms this project got approval in 2017 at a estimated cost of 4K Crores as on date with certain medians and fixing of arms it has come to 10,000 crores - as days go by and while it is finished it will come to 15K Crores. both State and Central are supporting the project Courtesy: kannada prabha - a unit of Indian Express Newspaper.
This package work progress is very slow compared to others. Particularly at veernapalya station they not done land occupation and barricading work. I think only this 11km package will complete by 2029.😢
Veeranapalya station already has RHS piers up to concourse level and now LHS 2 piers are cast and piling happening for the rest. Seems you are looking at a different place. the location is right next to Manyata
Waiting for the day when we will travel to airport in metro 😊👍
Thanks for the update!!!
Can you add notes about differences between this and last month's updates. Will be helpful to know the pace of progress
ok. will try and add from the next month
Hi sir is there any improvement in the removal of the power line inbetween the pillars
Bro after manyatha will the metro pass through underground to reach nagwara station
No Nothing Under ground here. The metro pillars will be on the median of service road and ORR. So the Foot over bridge was dismantled recently. Work should start sooner.
@@SunilHP k bro
it will take another 5 years for the entire project to be completed.
Airport to Hebbal with a distance of 25 kms
Hebbal to Tin Facory distance is 17 kms
Tin Factory to Marathahalli distance of 8 kms
Marathhalli to Silkboard distance of 15 kms
this project got approval in 2017 at a estimated cost of 4K Crores
as on date with certain medians and fixing of arms it has come to 10,000 crores - as days go by and while it is finished it will come to 15K Crores.
both State and Central are supporting the project
Courtesy: kannada prabha - a unit of Indian Express Newspaper.
i would like to know if you drive from airport to silkbosrd in one day and edit it over three days or you do it like segments
No. Not in a single stretch. Depending on my travels, it is always in segments.
This package work progress is very slow compared to others. Particularly at veernapalya station they not done land occupation and barricading work. I think only this 11km package will complete by 2029.😢
Veeranapalya station already has RHS piers up to concourse level and now LHS 2 piers are cast and piling happening for the rest. Seems you are looking at a different place. the location is right next to Manyata
Very slow progress. Dont see it completing for another 2 years atleast. June 2026 if I am being optimistic!! As usual thanks for the video.
The timeline for whold metro blue line is 2027