What you are trying to say is from your current slipped project go to baseline copy the baseline restore it and restore the baseline. This will create a new project now see the planned dates to be near to actuals and baseline it and start updating it
Hi.Sir Please make a video on how to match planned value and earned value and Performance percent complete? Please make a video on this also. Thank You.
Hi . If i prepare a recovery schedule on a baseline does it mean i need to update all the completed and ongoing activities one by one ? Imaging a project with 10k activities and almost 6k activities finished . How will re update all the activities if i prepare a recovery on the baseline as you said.. I hope you can help me with an answer
Hello Engineer Aasim. Very simple, export the update from the updated schedule, import again to the new baseline recovery schedule and you are all done. I will try to make one video for that step by step
Can you please make a video as case study on how to do it , Adjusting actual dates and putting in baseline is not easy . as the activity might require 10 days but in real took 1 month due to stoppage in between and shifting to another area of activity but still showing 1 month ,and activity is not needed this much time delay but still show as one month . This is happened in so many activity same way , and rescheduling baseline again is not easy .
@@PlanningengineerNet Sir When i prepared schedule i divide the villas by zonewise. And mention start and finish date of each zones. But the client asking the schedule villa by villa as wells as floorwise. Can you please help me the following doubts. 1.While preparing the detailed schedule should we show the erection only or other sub activities.such as screeding,Welding,grouting,inspection,finishing,sealant 2.What will be best relationship between two zones/ two villas. 3.While our scope is design,production,delivery & erection is it necessary to show production & delivery for all villas. 4.When the BOQ showing price for elements types how we can input cost. 5.do you have any standard daily progress reports template. Thanks in advance please help me to grow in my career .
What you are trying to say is from your current slipped project go to baseline copy the baseline restore it and restore the baseline. This will create a new project now see the planned dates to be near to actuals and baseline it and start updating it
Asalam o alikum,sir there is any vedio regarding to recover /revised schedule in which you explain this steps practically? If do please share the link
Do we adjust "Out of Sequence" activities relationships before issuing?
Yes
How did you find out the delay activities please make one video then update the progress schedule
Hi.Sir
Please make a video on how to match planned value and earned value and Performance percent complete? Please make a video on this also.
Thank You.
Hi . If i prepare a recovery schedule on a baseline does it mean i need to update all the completed and ongoing activities one by one ? Imaging a project with 10k activities and almost 6k activities finished . How will re update all the activities if i prepare a recovery on the baseline as you said.. I hope you can help me with an answer
Hello Engineer Aasim. Very simple, export the update from the updated schedule, import again to the new baseline recovery schedule and you are all done. I will try to make one video for that step by step
I made this video for you: ua-cam.com/video/gfic7eXu5bU/v-deo.html
@@PlanningengineerNet
Can you please make a video as case study on how to do it ,
Adjusting actual dates and putting in baseline is not easy .
as the activity might require 10 days but in real took 1 month due to stoppage in between and shifting to another area of activity but still showing 1 month ,and activity is not needed this much time delay but still show as one month .
This is happened in so many activity same way , and rescheduling baseline again is not easy .
Thanks alot eng.hany for your support , God bless you.
I tried this method but didnot get the output as wanted. Sir, can you do a video for this?
Hello sir
Do have any experience in precast housing projects where morethan 1000 villas.
Yes i do :)
@@PlanningengineerNet
Sir
When i prepared schedule i divide the villas by zonewise. And mention start and finish date of each zones. But the client asking the schedule villa by villa as wells as floorwise.
Can you please help me the following doubts.
1.While preparing the detailed schedule should we show the erection only or other sub activities.such as screeding,Welding,grouting,inspection,finishing,sealant
2.What will be best relationship between two zones/ two villas.
3.While our scope is design,production,delivery & erection is it necessary to show production & delivery for all villas.
4.When the BOQ showing price for elements types how we can input cost.
5.do you have any standard daily progress reports template.
Thanks in advance please help me to grow in my career .
Hello.....I did not understood, can you please show one with p6 example.
I will create a detailed video for that
@@PlanningengineerNet Thanks
Yes I tried the way u said...but the planned percentage did not match with the performances percentage complete
I like your accent sir. Which country you coming from?
I am from Egypt :)
This is theory. Practical would have been better
Only talking