How to assign Project Weightages in Primavera p6

Поділитися
Вставка
  • Опубліковано 2 лис 2024

КОМЕНТАРІ • 24

  • @shahruledree
    @shahruledree 2 роки тому +2

    Thanks, really appreciated

  • @billytubes
    @billytubes Місяць тому

    Hi Waqas,
    I dont have a cost loaded programme, can we use weightage and a fake cost resource to prsent s cruve and generate spi/cpi. ?

  • @saudpm40
    @saudpm40 Місяць тому +1

    Whats the benefit of using weighted sheet ? Is it linked with EVM?

    • @engrwaqas
      @engrwaqas  Місяць тому +1

      Yes , If your project progress measurement is based on such WTgs then yes it will create EVMs trends

  • @AtifKhan-we7rt
    @AtifKhan-we7rt 2 роки тому +1

    Good Presentation, But I believe it doesn't work for Weightage having value 0.001% as Primavera considers 0.00 value only. You have to enter it Manually is the best practice and more control.....Appreciate your work!

  • @faisalgulzar4538
    @faisalgulzar4538 Рік тому +2

    Sir, even if you export data with "Rs" or "d" symbol, it can easily be separated into 2 columns using the data tab in excel.

  • @reginaldibenne6875
    @reginaldibenne6875 8 місяців тому

    Nice presentation.🙏 I noticed after importing back the schedule, the weightage % go back to 0.2, 0.3, 0.89 just to say. ie the percentage did not multiples in those values. What's the cause, sir?

  • @nithinkokkula5866
    @nithinkokkula5866 2 роки тому +1

    Sir thnks for awesome video . Sir pls solve my query , after weightage is assign and when we enter actuals how to get project actual progress values against schedules ones

    • @engrwaqas
      @engrwaqas  2 роки тому

      Thanks

    • @minhazali4090
      @minhazali4090 Рік тому

      Schedule values are derived from baseline. Actual is derived from updated schedule as physical progress or earned value

  • @sarbelandkhan7830
    @sarbelandkhan7830 4 місяці тому

    If all the amounts are entered into the P6 along with WBS, then why it cannot calculate the weightages by itself? Its just dividing individual costs by the cumulative project cost.

  • @carlodigma819
    @carlodigma819 8 місяців тому

    Hi, I have one Query I tried it but, when exporting P6 to excel the out come the activities are not in order. I tried to use the define and inter all percentages in all activities automatic wbs was filled with total wt. %, but when i Share the xer file to the client the outcome with them not the same value of Wt. % please guide Thanks

    • @engrwaqas
      @engrwaqas  8 місяців тому

      Whatsapp +92 3114396983

  • @carlodigma819
    @carlodigma819 8 місяців тому

    Not coming when i export to p6 value are difference

  • @madanmoharana77
    @madanmoharana77 2 роки тому +3

    wrong way of presenting ...it will not work in real time project. cost based weightage is not working most of the time & in update time your method also not work.

  • @muhammadusmananwar8992
    @muhammadusmananwar8992 Рік тому +1

    how we can calculate weightage % if cost is not loaded?

  • @carlodigma819
    @carlodigma819 9 місяців тому

    The wbs not tally the percentage.