Pune Metro Line 3: Part1 - Hinjawadi to Balewadi update | 2-Nov
Вставка
- Опубліковано 23 лис 2024
- Detailed construction update below for Line 3 stations.
Part1: Hinjawadi to Balewadi.
0:06 Megapolis circle station - Work going well
1:44 Quadron station - Advanced stage, good progress on entry-exit
3:06 Dohler station - Work going well
4:55 Infosys Phase II station - Advanced stage, roof and entry-exit work in progress
6:54 Wipro Phase II station - Good progress on entry-exit
8:44 Pall India station - Work going well, entry-exit work started
10:18 Shivaji Chowk station - Work going well, entry-exit work in progress
12:02 Hinjawadi station - Entry-exit work in progress on opposite side
14:05 Wakad Chowk station - Work going well
15:56 Balewadi Stadium station - Advanced stage, roof work and entry-exit work on opposite side
17:10 NICMAR station - Work going well, entry-exit work started
18:28 Ram Nagar station - Work going well, good progress on entry-exit
Pune Metro Line 3 connects Shivajinagar Civil Court to Hinjawadi IT Park Phase 3.
#punemetro #line3
Please like and subscribe!
Great. We are in Canada and always curious to know this metro development. thanks for update.
thanks for the update!
Good progress
Seems this part all viaduct work is completed
Yes viaduct is completed till after Balewadi High Street. Some patches remain in Baner. Check out my October video for details.
Balewadi to Hinjewadi may be first phase in April 2025 Opening. Rest will be Dec 2025.
Bro as per your knowledge what date is expected to be metro opening?
They mentioned that metro will be functional on march 24 2025
March is not possible. Oct 2025 is possible if they keep up the speed and there are no delays.
Metro station k naam, area ka naam kon dalega bhai
Its there in description and chapters