Pune Metro Line3: Part1 - Hinjawadi to Balewadi update | 6-Jan-25
Detailed Jan25 construction update below for Line 3 stations.
Part1: Hinjawadi to Balewadi.
0:00 Megapolis circle station - Brick and roof work in progress
1:23 Quadron station - Advanced stage, slow progress on roof, entry-exit
3:04 Dohler station - Slow progress
3:50 Infosys Phase II station - Advanced stage, slow progress on roof, entry-exit
5:34 Wipro Phase II station - Good progress on entry-exit
6:35 Pall India station - Slow progress on entry-exit
8:52 Shivaji Chowk station - Work going well, entry-exit work in progress
9:50 Hinjawadi station - Entry-exit work in progress on other side
11:35 Wakad Chowk station - Slow progress, entry-exit work started on Wakad side
12:51 Balewadi Stadium station - Good progress, final stage of roof covering started
14:02 NICMAR station - Slow progress
15:41 Ram Nagar station - Work going well, good progress on entry-exit
Pune Metro Line 3 connects Shivajinagar Civil Court to Hinjawadi IT Park Phase 3.
#punemetro #line3
Please like and subscribe!
Переглядів: 1 783

Відео

Pune Metro Line3: Part3 - Double decker flyover to Civil Court update | 14-Dec
Переглядів 2,5 тис.21 день тому
Detailed update (Dec24) below for Line 3. Part 3 - Pune University Junction (Double decker flyover) to Civil Court 0:00 Pune University station - Station arms and viaduct work started 0:33 Start of flyover (Baner side) - Metro pier and span completed, Raj Bhavan Land acquistion pending here 0:49 Baner up ramp steel girder and 2nd level metro steel girder installed 0:58 Extension of pier arm and...
Pune Metro Line3 Part 2 - Balewadi to Pune Univ update - 14 Dec
Переглядів 1,9 тис.28 днів тому
Detailed update (Dec24) below for Line 3. Part 2: Balewadi to Pune University 0:00 Start from Balewadi High Street 0:12 High Street station - Station viaduct in progress 2:11 Balewadi Phata station - Station viaduct nearly done 3:13 Two portal beams still pending 3:40 Two portal beams still pending 4:13 Portal beam still pending 4:32 Baner Gaon station - Station viaduct in progress 5:30 Baner s...
Pune Metro Line3: Part1 - Hinjawadi to Balewadi update | 7-Dec
Переглядів 6 тис.Місяць тому
Detailed Dec24 construction update below for Line 3 stations. Part1: Hinjawadi to Balewadi. 0:00 Megapolis circle station - Work going well 2:07 Quadron station - Advanced stage, good progress on roof, entry-exit 3:35 Dohler station - Work going well 5:00 Infosys Phase II station - Advanced stage, good progress on roof 6:25 Wipro Phase II station - Work going well 7:50 Pall India station - Work...
Pune Metro Line3: Part3 - Double decker flyover to Civil Court update | 15-Nov
Переглядів 4 тис.Місяць тому
Detailed update (Oct-to-Nov) below for Line 3. Part 3 - Double decker flyover to Civil Court 0:00 Pune University station 0:04 Start of flyover (Baner side) - Metro viaduct completed but road and station viaduct pending 3:24 Opposite side of flyover (towards Hinjawadi) - Good progress 5:39 Steel girder erection started in University chowk 6:00 Towards Civil Court 6:02 RBI station - Slow progres...
Pune Metro Line3: Part2 - Balewadi to Pune Univ. update | 15-Nov
Переглядів 1,7 тис.Місяць тому
Detailed update (Oct-to-Nov) below for Line 3. Part 2: Balewadi to Pune University 0:00 Start from Balewadi High Street 0:20 High Street station - Good progress 2:01 Balewadi to Baner Road curve done 2:22 Balewadi Phata station - Station viaduct work started 3:41 Two portal beams pending 4:02 Two portal beams pending 4:27 Portal beam pending 4:50 Baner Gaon station - Good progress on station vi...
Pune Metro Line 3: Part1 - Hinjawadi to Balewadi update | 2-Nov
Переглядів 5 тис.2 місяці тому
Detailed construction update below for Line 3 stations. Part1: Hinjawadi to Balewadi. 0:00 Megapolis circle 0:06 Megapolis circle station - Work going well 1:44 Quadron station - Advanced stage, good progress on entry-exit 3:06 Dohler station - Work going well 4:55 Infosys Phase II station - Advanced stage, roof and entry-exit work in progress 6:54 Wipro Phase II station - Good progress on entr...
Pune Metro Line 3: Part3 - Double decker flyover to Civil Court update | 12-Oct
Переглядів 5 тис.2 місяці тому
Detailed update (Sep-to-Oct) below for Line 3. Part 3 - Double decker flyover to Civil Court 0:00 Start of flyover (Baner side) - Metro viaduct completed but road viaduct and Pune University station arms pending 3:00 Opposite side of flyover (towards Hinjawadi) - Good progress 5:33 Towards Civil Court 5:36 RBI station - Slow progress 6:25 Agriculture college station - Some progress on station a...
Pune Metro Line 3: Part2 - Balewadi to Pune Univ. update | 12-Oct
Переглядів 3,8 тис.2 місяці тому
Detailed update (Sep-to-Oct) below for Line 3. Part 2: Balewadi to Pune University 0:00 Balewadi High Street to Baner Road viaduct curve nearly complete, fast progress 0:39 Balewadi Phata station - Work started 2:57 Launch gantry stuck due to 5 pending portal beams 4:16 Baner Gaon station - Work going well 5:12 Viaduct completed since Sep 5:36 Six viaduct spans completed 5:55 Baner station - Ve...
Pune Metro Line 3: Part1 - Hinjawadi to Balewadi update | 4-Oct
Переглядів 7 тис.3 місяці тому
Detailed construction update below for Line 3 stations. Part1: Hinjawadi to Balewadi. 0:00 Line from Metro depot 2:16 Megapolis circle station - Work going well 3:26 Quadron station - Advanced stage, roof and entry-exit work in progress 5:10 Dohler station - Work going well 7:15 Infosys Phase II station - Advanced stage, roof and entry-exit work in progress 8:47 Wipro Phase II station - Work go...
Pune Metro Line 3: Shivajinagar area update | 11-Sep
Переглядів 2,8 тис.3 місяці тому
Pune Metro Line 3: Shivajinagar area update | 11-Sep
Pune Metro Line 3: Balewadi to Pune University update | 11-Sep
Переглядів 1,6 тис.3 місяці тому
Pune Metro Line 3: Balewadi to Pune University update | 11-Sep
Pune double decker metro flyover update | 11-Sep
Переглядів 1,1 тис.3 місяці тому
Pune double decker metro flyover update | 11-Sep

КОМЕНТАРІ

  • @rahulp7313
    @rahulp7313 3 дні тому

    Tata literally disappointed with slow work

  • @prathampatel3259
    @prathampatel3259 3 дні тому

    Good Informative video

  • @Techtips200
    @Techtips200 3 дні тому

    Not going to open soon ...atleast 2026

  • @kochikamevideos2502
    @kochikamevideos2502 3 дні тому

    2 more years left .

  • @ameyaraomarathe
    @ameyaraomarathe 4 дні тому

    Small section may open in 2025. But full completion will be not before mid-2026

  • @JaiD0427
    @JaiD0427 4 дні тому

    Hope this opens in 2025🙏

  • @joyefshaikh3614
    @joyefshaikh3614 5 днів тому

    Which dash cam is used for recording?

  • @Sam.daruwala
    @Sam.daruwala 5 днів тому

    One year more min

  • @sarvodaydutta1905
    @sarvodaydutta1905 5 днів тому

    *By the third quarter of 2026, this corridor would be operational....*

  • @Metro_vid
    @Metro_vid 5 днів тому

    Happy New Year to you and hope 2025 marks the start of Line3! Relatively slow progress on Hinjawadi-Balewadi section in last one month, mainly on entry-exit, station internal work and roof structure. The entire viaduct in this section is complete but track work is in progress. Overall in this section, Roof work started 4/12 Entry-exit work at advanced stage 5/12 . Please refer chapters in the video description for more updates.

  • @solty_
    @solty_ 19 днів тому

    why are pillars being erected so far past civil court station? also how will the civil court station on line 3 connect to the larger civil court station for line 1 and 2? thank you so much for keeping track of the progress

    • @Metro_vid
      @Metro_vid 13 днів тому

      It is for the train to transition onto the other line at the end of its journey. Also there is a proposal to extend this same line to Hadapsar via Camp. For interchange with Line 1/2, there will be a 150m foot over bridge connecting the 2 stations directly.

  • @JaiD0427
    @JaiD0427 25 днів тому

    Metro Line 3, Outer Ring Road, Purandhar Airport & Mum-Pune expressway Missing link. Life's gonna be good.

  • @JaiD0427
    @JaiD0427 25 днів тому

    Almost done.

    • @Metro_vid
      @Metro_vid 25 днів тому

      Yes only station work is pending.

  • @sahilbhure7353
    @sahilbhure7353 26 днів тому

    hey! if possible keep updating about nigdi to pcmc exentension route work also

    • @Metro_vid
      @Metro_vid 26 днів тому

      Currently the work is very slow. Let's see in future. It's possible that Maha Metro may upload professional drone shots later.

    • @nikhilbhute07
      @nikhilbhute07 25 днів тому

      Abhi tak waha kuch cover karne jaisa nhi hai bro

  • @nayanprajapativlogs
    @nayanprajapativlogs 26 днів тому

    Good 👍

  • @sampen4934
    @sampen4934 26 днів тому

    They should complete Balewadi phata to Hinjawadi major civil works in next 3 months. Take 3 month trial and start metro by before monsoon july 2025. Remaining stretch, civil work by diwali 2025 and commission in early 2026. Looks feasible.

    • @Metro_vid
      @Metro_vid 26 днів тому

      Yes that should help to some extent for Hinjawadi traffic. But this being PPP, I am not sure if Puneri Metro would want to go that way.

  • @amitbhapkar3710
    @amitbhapkar3710 26 днів тому

    Very nice update

  • @shubhampawara781
    @shubhampawara781 26 днів тому

    goood coverage sir ji !

  • @Metro_vid
    @Metro_vid 26 днів тому

    Good progress in last one month in University junction and Shivajinagar area till Civil Court. But the construction is lagging in some places. Still 3 piers, 3 portal beams, 64 metro viaduct spans, 12 flyover spans are roughly pending in this section. Please refer chapters in video description for more updates.

    • @rahulp7313
      @rahulp7313 26 днів тому

      Flyover toh December 2025 ke baad hi open hoga

    • @Metro_vid
      @Metro_vid 26 днів тому

      @@rahulp7313PMRDA is now saying Mar-April for flyover and December for metro line.

    • @queserasera14
      @queserasera14 26 днів тому

      ​@@rahulp7313Flyover jald hi hoga metro bad me

    • @Hacks00145
      @Hacks00145 25 днів тому

      Thank you for the detailed updates, you are doing the govt job, which ideally they should have done Again thank you

    • @Metro_vid
      @Metro_vid 25 днів тому

      @@Hacks00145 Yes that's my intention to share the updates. Puneri Metro missed a great opportunity for publicity especially with the target IT crowd!

  • @ruchi8394
    @ruchi8394 29 днів тому

    gr8

  • @Metro_vid
    @Metro_vid 29 днів тому

    Good progress on stations in last one month. 1/4 section without piers and viaduct almost completed near Bhairavee hotel. Rest 3/4 sections are still stuck due to overhead lines or land acquistion issues. Please refer chapters in video description for more updates. Part 3: Double decker flyover to Civil Court is uploaded now.

    • @rajattrt
      @rajattrt 29 днів тому

      land acquistion issues - without this getting sorted, how can we expect the metro to run. What do we think is a realistic timeline now.

    • @rahulp7313
      @rahulp7313 29 днів тому

      ​@@rajattrtHinjawadi to wakad /balewadi stadium - December 2025 Next till pune university - June 2026 University to shivajinagar - December 2026

    • @Metro_vid
      @Metro_vid 28 днів тому

      @@rajattrt Oct -Nov 2025 is possible if works continues at fast pace since only small portion is stuck.

  • @shirishherwade6680
    @shirishherwade6680 29 днів тому

    Starting point, end point etc info can be added. Also at start can show area map. You can speak about station names also

    • @Metro_vid
      @Metro_vid 29 днів тому

      All this information is added in video description and chapters.

  • @anishverma4533
    @anishverma4533 Місяць тому

    💩 construction 😂

  • @SanjayKulkarni-k3o
    @SanjayKulkarni-k3o Місяць тому

    Nice information. Try drone if possible.

  • @Sam.daruwala
    @Sam.daruwala Місяць тому

    Drone view se actual work pata chalega

    • @rahulp7313
      @rahulp7313 Місяць тому

      Bhai uske pass nahi hai hota toh kabka kar deta. He is not professional youtuber

  • @SanjayKulkarni-k3o
    @SanjayKulkarni-k3o Місяць тому

    Nice information. Try drone view if possible

  • @ruchi8394
    @ruchi8394 Місяць тому

    very helpfull!

  • @tejaspune
    @tejaspune Місяць тому

    Can we get a drone view please from next time. I heard the tracks and third rail are also completed till Balewadi.

    • @rahulp7313
      @rahulp7313 Місяць тому

      Track work completed but 3rd rail incomplete

  • @rahulp7313
    @rahulp7313 Місяць тому

    March main mushkil hai ye strech toh diwali December main hi open hoga.

  • @Metro_vid
    @Metro_vid Місяць тому

    Good progress on Hinjawadi-Balewadi section in last one month, mainly on entry-exit stairs, station internal work and roof structure. The entire viaduct in this section is complete but track work is in progress. Please refer chapters in the video description for more updates.

    • @rahulp7313
      @rahulp7313 Місяць тому

      Dono side pe entry exit honi chahiye jo ki nahi dikh raha

    • @Metro_vid
      @Metro_vid Місяць тому

      @@rahulp7313 Yes I could only see active work on both sides at Balewadi stadium station. It is risky to open with only one side entry/exit.

  • @RohanS7172
    @RohanS7172 Місяць тому

    Is there any under ground bypass

    • @Metro_vid
      @Metro_vid Місяць тому

      Where?

    • @RohanS7172
      @RohanS7172 Місяць тому

      @@Metro_vid near Balewadi stadium

    • @Metro_vid
      @Metro_vid Місяць тому

      @@RohanS7172 It will be over ground foot over bridge. Check my latest short which shows it in more detail

  • @rahulp7313
    @rahulp7313 Місяць тому

    Wakad Metro Station ke opposite side ke entry exit pe kam abhi tak shuru nahi hua

    • @Metro_vid
      @Metro_vid Місяць тому

      Yes it will be very useful to cross highway but no progress yet beyond barricading.

  • @Metro_vid
    @Metro_vid Місяць тому

    Balewadi stadium station and entry-exit on other side of the highway, at advanced stage of completion on Hinjawadi - Shivajinagar Pune Metro Line 3. This is close to Balewadi stadium on one side and residential buildings on the other side. It should prove very useful during sports events and concerts at Balewadi stadium.

  • @shrikanthkulkarni90
    @shrikanthkulkarni90 Місяць тому

    सिव्हिल कोर्ट ला आधीच्या rout लाच जॉईन केली असती हा route तर एकच मेट्रो वनाज ते हिंजवडी धावली असती सिव्हिल कोर्टाला नवीन स्टेशन बनवण्या ऐवजी

    • @sjn2
      @sjn2 Місяць тому

      Civil court station of Line 3 is 150m away from the existing Line 1/2 station (Aqua and Purple line). There will be a foot over bridge connecting them directly.

    • @Metro_vid
      @Metro_vid Місяць тому

      Actually having all three stations in the same building at different levels would have been very convenient. But these designs were made separately. Hopefully they will make more integrated interchange stations in future

  • @shrikanthkulkarni90
    @shrikanthkulkarni90 Місяць тому

    हिंजवडी जाणाऱ्या मार्गाला पुन्हा नवीन स्टेशन बनवत आहे का सिव्हिल कोर्ट ल समजा वनाज किंवा रामवाडी कडून हिंजवडी लां जायचं झालं तर सिव्हिल कोर्ट वर ट्रेन change करायची का

  • @alpeshgaikwad2752
    @alpeshgaikwad2752 Місяць тому

    i can say it will take another 1.5 years to complete

  • @sahilsayyad3707
    @sahilsayyad3707 Місяць тому

    There is news that the metro can open up to March 2025 is it possible?

    • @rahulp7313
      @rahulp7313 Місяць тому

      Not possible.

    • @Metro_vid
      @Metro_vid Місяць тому

      No that's not possible looking at the pending work. It can open in Oct-Nov 2025. Refer my Nov videos for more updates.

  • @Metro_vid
    @Metro_vid Місяць тому

    NICMAR station shaping up on Hinjawadi - Shivajinagar Pune Metro Line 3. This is close to many Balewadi schools and colleges like NICMAR, MITCON, Moze. Also, a multimodal transport hub is proposed on the other side.

  • @Metro_vid
    @Metro_vid Місяць тому

    Baner gaon station shaping up on Hinjawadi - Shivajinagar Pune Metro Line 3. This is in the main Baner shopping area. But its quite close to the residential buildings on the other side.

  • @pranavkarlekar5940
    @pranavkarlekar5940 Місяць тому

    मागे कुठेतरी वाचलं की 70% काम झालं आहे, मला वाटतं फक्त मार्गिकेचं धरलं तर कदाचित 70% च्या जवळपास जाईल. बाकी स्थानकं आणि इतर गोष्टी बघता 2025 च्या अखेर पर्यंत हिंजवडी - वाकड पर्यंत चालू होऊ शकेल. Hope it goes faster than that. Nice video btw😊, try to make such video on the same day every month😄

  • @marotipotraje8869
    @marotipotraje8869 Місяць тому

    Another 6 months for completion ?

    • @Metro_vid
      @Metro_vid Місяць тому

      @@marotipotraje8869 Flyover should be done in 2 - 3 months. But whole line will take at least an year

    • @maheshkulkarni5982
      @maheshkulkarni5982 Місяць тому

      Who r u? Do u have knowledge about construction?

  • @PravinPawarthelords
    @PravinPawarthelords Місяць тому

    ekach number bhava

  • @harshadyelgudkar30
    @harshadyelgudkar30 Місяць тому

    Nice progress...very well covered.

  • @Metro_vid
    @Metro_vid Місяць тому

    Good progress on double decker flyover in last one month. For most of the spans, girder erection and deck slab is completed. Work is now focused on the main university chowk. Please refer chapters in the video description for more updates.

    • @Hacks00145
      @Hacks00145 Місяць тому

      Yes thank you posting

    • @bangimusaif2973
      @bangimusaif2973 Місяць тому

      Thanks. How much time it would take?

    • @Metro_vid
      @Metro_vid Місяць тому

      @@bangimusaif2973 I guess flyover should be done in 2-3 months but the whole line will take at least an year.

  • @pnthrillz
    @pnthrillz Місяць тому

    Flyover ka batao bhai

    • @Metro_vid
      @Metro_vid Місяць тому

      @@pnthrillz Check Part 3 video

  • @pnthrillz
    @pnthrillz Місяць тому

    Until they complete the flyover, there will be no relief. And it seems it will take another year

    • @Metro_vid
      @Metro_vid Місяць тому

      Flyover should be done in 2-3 months. Fast progress there