Tutorial - How to create a planned percentage (% Planned) field in Microsoft Projects.

Поділитися
Вставка
  • Опубліковано 3 лис 2024

КОМЕНТАРІ • 73

  • @abdellahfaouzi1412
    @abdellahfaouzi1412 8 місяців тому +1

    Thank you so much you saved my life !!!! I subscribed to your channel .
    For those who found the problem of the appearance of zero (0) for all values, you must check that you saved baseline of your project.

    • @JCleRouxx
      @JCleRouxx  5 місяців тому

      That's great news! Thanks for the additional tip.

  • @adrianmondolo
    @adrianmondolo Рік тому +1

    you are the love of my life!! you explained this really easy and slow. I couldn't ask for more. Thank you sooooo much! 🥰

    • @JCleRouxx
      @JCleRouxx  Рік тому

      🤣 Great to hear. You'll have to get past my wife first though!

  • @jonnyland7
    @jonnyland7 11 місяців тому +2

    Great! it solved my problem in a big project!

  • @morganshongwe6501
    @morganshongwe6501 Рік тому

    Wow Thanks JC this really worked, ive been strugling

    • @JCleRouxx
      @JCleRouxx  Рік тому

      Aah Morgan, great news. I've also had my fair share of struggling with this %-complete column.

  • @fr9nki46
    @fr9nki46 2 місяці тому

    Hi JC, great video! Will definitely adjust my calculation. But have you ever taken your calculation and added a weighting factor? I need to weight the schedule based on cost as some tasks duration doent justify the overall weighting against the project. PLEASE I require your help

  • @arny82
    @arny82 2 місяці тому

    This is just brilliant thank you. I am getting a few errors on summary tasks, any idea why? I have followed your guide step by step. I noticed the summary tasks that display errors are the one which I have added some blank fields underneath them...your help is much appreciated

  • @ShadiEdalatian
    @ShadiEdalatian Рік тому

    Thank you. the video was great.

    • @JCleRouxx
      @JCleRouxx  5 місяців тому

      Thanks man! So happy you found it valuable.

  • @bryanvillondo5227
    @bryanvillondo5227 Місяць тому

    Sir JC, is your formula the same as getting the weighted percentage per scope of work with the formula "total cost of the certain scope divided by the total cost of the project?" Thanks in advance for your response!

  • @IreshaWickramasingh1
    @IreshaWickramasingh1 3 місяці тому +1

    Hi JC, Thank you so much for sharing this and it is very helpful. I'm taking the planned percentage by updating the baseline program to the status date and then pasting it as text into the updated project file. I've tried to apply your advice, but the manually calculated planned value I derived by updating the baseline program to the status date differs from the calculated value you taught me. For example, my manually calculated percentage is 39%, but when I use the calculation method you provided, it becomes 42%. Do you have any guesses about what might be going wrong?

    • @JCleRouxx
      @JCleRouxx  3 місяці тому

      Difficult one, there could be various reasons. Perhaps in the way you update the baseline programme. Do you use % complete or remaining duration in your update?

    • @IreshaWickramasingh1
      @IreshaWickramasingh1 2 місяці тому

      @@JCleRouxx I used % complete

  • @benpienaar2310
    @benpienaar2310 Рік тому +1

    Thank you Kobus! Almost all of my headings and tasks calculates the % planned perfectly except a few Headings that shows ERRORS. Any advice?

    • @GilbertoMartinez-f2u
      @GilbertoMartinez-f2u Рік тому +1

      Did you set the baseline?

    • @benpienaar2310
      @benpienaar2310 Рік тому

      @@GilbertoMartinez-f2u That helped! Thank you!

    • @nimarafienejad6466
      @nimarafienejad6466 9 місяців тому

      I faced the same issue and after few hours noted that those Task lines added to schedule after setting the Baseline. maybe this is your issue as well?

  • @olalekanadeyemi249
    @olalekanadeyemi249 2 місяці тому

    I'm wondering how to get the cumulative planned % complete. Thanks

  • @shaileshmodhia7600
    @shaileshmodhia7600 Рік тому +1

    Sir nice explained. However formulas used in customised columns could not be seen. Will u provide the formulas

    • @JCleRouxx
      @JCleRouxx  Рік тому

      You can find the formulas here - lerouxconsulting.com/ms-project-for-construction-articles-and-resources/creating-a-planned-percentage-complete-field-in-microsoft-project

  • @salt1093
    @salt1093 Місяць тому

    Hi JC - I have one error in the Baseline Duration Total column at a task which was added after the baseline was set. I am currently on baseline 5. The project currently has 2208 activity lines. Some have been deleted (removed from scope) and this specific one task added - which is showing the error. Baseline Days Completed shows a number (411). The 'Planned Completion Value' column also shows an error - I assume this is due to the error in the 'Baseline Duration Total' column. Can you please help me resolve this, is there a way?

  • @milner267
    @milner267 4 місяці тому

    Thanks JC.
    for clarity, I saw you sped through the part where you'd have to baseline the newly added tasks. would that baseline activity have to be done every single time a new task is added?

    • @JCleRouxx
      @JCleRouxx  3 місяці тому +1

      Yes, you need the baseline as part of the formula to indicate the planned value. So if you add tasks, you have to baseline again before you obtain the planned % value.

    • @milner267
      @milner267 3 місяці тому

      @@JCleRouxx thanks a lot JC. Any concerns regarding the fact that the client bday have an approved baseline, out wood want to track also, the items which were not part of an initial baseline? I can see that raising stakeholders' eyebrows, re-Baselining every time, especially as MSP records the date BL'd

  • @ozlembugan1784
    @ozlembugan1784 2 місяці тому

    Hi again :) I wanna ask that; Can we show these columns (% planned and % complete) in a S-chart to compare them?

    • @JCleRouxx
      @JCleRouxx  2 місяці тому

      Yes you can but it takes a bit of work. You would need to shift your timenow date through the months of the project and then export those monthly planned % values to Excel.

    • @ozlembugan1784
      @ozlembugan1784 Місяць тому

      @@JCleRouxx Are you gonna share a video about this topic?

  • @milner267
    @milner267 10 місяців тому

    Thanks so much for sharing. a question for you: is there a way to show this as either an "S-curve" within the report tab, or within task usage?

    • @milner267
      @milner267 7 місяців тому

      Hi JC, still interested in this topic. is it possible to see within task usage? because while it is possible to see at at a status data, what was planned, key stakeholders would want to know what that curve would look like. any help would be appreciated

  • @dunyojustice4050
    @dunyojustice4050 Рік тому +1

    Please how can have access to the software I'm interested

  • @ozlembugan1784
    @ozlembugan1784 3 місяці тому

    Hi JC. Thanks for the tutorial. I tried to apply this on my project and I encountered an error. MS project doesn't allow me to write the part 0,0.01, which is in formula below. It says "The formula contains a syntax error or contains a reference to an unrecognized field or function name." What else can I use?
    IIf([Duration]=0,0.01,ProjDateDiff([Baseline Estimated Start],[Baseline Estimated Finish])/60/8)

    • @JCleRouxx
      @JCleRouxx  3 місяці тому

      Maybe your windows setting requires a point instead of the comma? Maybe try that and see if it works?

    • @JCleRouxx
      @JCleRouxx  3 місяці тому

      Also check, your formula is missing the last bracket... IIf([Duration]=0,0.01,ProjDateDiff([Baseline Estimated Start],[Baseline Estimated Finish]))

    • @ozlembugan1784
      @ozlembugan1784 2 місяці тому +1

      @@JCleRouxx I wrote it this way "IIf([Duration]=0;0,01;ProjDateDiff([Baseline Estimated Start],[Baseline Estimated Finish])/60/8)". The formula accepted. Thank you for your help.

  • @timothylim-x8x
    @timothylim-x8x 9 місяців тому

    Hi, can i get some help.
    Actually i just need to show my target % vs actual %
    I've been searching 100 videos, and none have done so. is microsoft project unable to do such simple task? im abit frustrated

  • @JuanPerez-hb5kb
    @JuanPerez-hb5kb Рік тому

    Hi JC, I am JC as well. I really liked the tutorial on the correct way to show Planned %. I do have a question, does MS Project have Labor Units? I have not seen this

    • @JCleRouxx
      @JCleRouxx  Рік тому

      Hi JC! . MS Project can only show labor units in "manhours". You can certainly export the data and then convert it if you like.

  • @adrianmondolo
    @adrianmondolo Рік тому +1

    Hi! I have a question. Is there any way to change the actual status date? in order to open the project and have the time to create a report with the status of one week ago for example.

    • @JCleRouxx
      @JCleRouxx  Рік тому

      You will have to set the status date on the Project tab each time.

  • @weamibrahem4736
    @weamibrahem4736 11 місяців тому

    Very interested.. Can we get the formula that you used

    • @JCleRouxx
      @JCleRouxx  5 місяців тому

      You can find the formula here - bit.ly/3KxKyI2

  • @aseyeaflakpui3859
    @aseyeaflakpui3859 Рік тому

    Hi JC, Thank you for this video.
    I am facing a challenge here.
    I followed all the steps but I am getting 100% for all activities including the ones yet to start.
    What could be the problem?

    • @aseyeaflakpui3859
      @aseyeaflakpui3859 Рік тому +1

      I think I've found what the problem is.
      I hadn't set my status date.
      Thank you

  • @susuchen4638
    @susuchen4638 Рік тому

    Hello JC; I watched your video about the pROJECT, i want ask you how you make the sheet with dependencies and delayed shecedule,

    • @JCleRouxx
      @JCleRouxx  Рік тому

      Hi Susu. You can simply add those fields in your view to have the same sheet. To do the update requires a more complex process which is a bit cumbersome to explain here. Have a look at our other videos or consider the course where this is explained in detailed, step-by-step.

  • @TheEugenezandberg
    @TheEugenezandberg Рік тому

    Awesome vid ! Only problem is that I keep getting a syntax error when using your formula .. I even tried to "retype" the highlighted error but to no avail :(
    Any advice ?

    • @JCleRouxx
      @JCleRouxx  Рік тому

      Hi Eugene, difficult to tell without looking at the input. It may just be a misplaced space or bracket causing the issue?

    • @TheEugenezandberg
      @TheEugenezandberg Рік тому

      @@JCleRouxx I was very careful to follow the exact sintex and spacing but still doesn't work

  • @roldanduarteholguin7102
    @roldanduarteholguin7102 6 місяців тому

    Export the Azure, Chat GPT, Revit, Plant 3D, Civil 3D, Inventor, ENGI file of the Building or Refinery to Excel, prepare Budget 1 and export it to COBRA. Prepare Budget 2 and export it to Microsoft Project. Solve the problems of Overallocated Resources, Planning Problems, prepare the Budget 3 with which the construction of the Building or the Refinery is going to be quoted.

  • @anshulkushwaha4350
    @anshulkushwaha4350 3 місяці тому

    can we also use it to create a planned percentage based on late dates?

    • @JCleRouxx
      @JCleRouxx  3 місяці тому

      I think you will be able to, I'll have a look.

  • @honeystarism
    @honeystarism Рік тому

    Hi, thank you for this tutorial. I tried following the steps, but some of the tasks are #ERROR. Is this caused by the duration, as some of my tasks are in weeks and months. Can you help? Thank you.

    • @nimarafienejad6466
      @nimarafienejad6466 9 місяців тому

      I faced the same issue and after few hours noted that those Task lines added to schedule after setting the Baseline. maybe this is your issue as well?

  • @Shahadaleqiel
    @Shahadaleqiel Рік тому +1

    Hi, I face an issue we are behind schedule and the summary task shows we are ahead, that incorrect. so I follow the same as you did but I got an error in the summary task. how can I fix that? thanks in advance!

    • @JCleRouxx
      @JCleRouxx  Рік тому

      Hi Shahad. There can be many reasons for this. It could be that some of the tasks below the summary task is not included in Baseline, or that a Baseline does not exist for certain tasks. Also check that the status date is correctly set, check for any manual schedule tasks.

    • @Shahadaleqiel
      @Shahadaleqiel Рік тому

      @@JCleRouxx can you please help me with that I tried to fix the issues for 2 months if you can give me your email so we can discuss these issues it will be much appreciated! this task Is much important to me

    • @Shahadaleqiel
      @Shahadaleqiel Рік тому

      Hi, when I followed up on the steps, I got 1 for all activities in the Updated % planned? so the planned percentages change to 100% based on the Updated % planned column those are issues I face now .. can you help with that?

  • @SteveMcQueen-m1k
    @SteveMcQueen-m1k Рік тому

    The deeper you get into the subtasks, the less accurate it becomes. Level 1 +- 1%, level 2 from %1 to 2%, level 3 up to 3%. i use the formula set at your link page. did i set something wrong?

    • @JCleRouxx
      @JCleRouxx  Рік тому

      Interesting. The formula gives me solid accuracy even in lower levels. Just double check if you've set the summary settings correctly?

  • @gayatrilshinde1560
    @gayatrilshinde1560 Рік тому

    is we have column name baseline estimated start and finish date or we have to use baselinestart and finish date

    • @JCleRouxx
      @JCleRouxx  Рік тому

      Use the Baseline Estimated Start and Baseline Estimated Finish in the formula. These are standard fields in MSP already.

  • @FarazKhan-bn8rn
    @FarazKhan-bn8rn 3 місяці тому +1

    I am still wondering why you need such complex formulas when you can just add a cost to an activity and use the earned value field to get the plan and actual % 😅😅😅😅😅😅😅😅😅😅😅

    • @JCleRouxx
      @JCleRouxx  3 місяці тому +2

      True! 😅 However, the formula can be saved and applied to all projects and therefore you have a quick way of comparing planned vs actual without having to cost load your schedule each time.

    • @katybunja8566
      @katybunja8566 Місяць тому

      how to get actual and plan percentage based on cost?

  • @Johanswnpl
    @Johanswnpl 7 місяців тому +1

    Faaaaaanks !!

    • @JCleRouxx
      @JCleRouxx  5 місяців тому

      You're weeeeelcome! 😊😊

  • @shivsaurabh5922
    @shivsaurabh5922 5 місяців тому

    Your starting assumption is wrong. % complete in msp means ( % planned complete) and we have to customise formula for % actual complete

    • @JCleRouxx
      @JCleRouxx  5 місяців тому

      Not sure what you base this on. % complete is only populated once you start adding actual values to the schedule.

    • @shivsaurabh5922
      @shivsaurabh5922 5 місяців тому

      @@JCleRouxx correct, my mistake