MS Project 8 - Tracking Task Progress and Variance

Поділитися
Вставка
  • Опубліковано 8 січ 2025

КОМЕНТАРІ • 14

  • @elegantuseducation2421
    @elegantuseducation2421 Рік тому +3

    Thank you for making this process less complex. I enjoyed it

  • @nibirchowdhury3837
    @nibirchowdhury3837 2 роки тому +3

    Great video Sir. Thanks for the share.

  • @phemmy2008
    @phemmy2008 Рік тому +2

    Keep up the good work

  • @affanshakirwan6354
    @affanshakirwan6354 2 роки тому +2

    Thank a lot prof

  • @zulfikarian
    @zulfikarian 9 місяців тому

    Great video. But I want to ask, if somehow actual material resources used is more than what's planned. How do we express it in tracking gant?

    • @PatJHeffernan
      @PatJHeffernan  9 місяців тому

      Hi. The tracking Gantt shows time variance compared to plan. Resource variance is tracked numerically in the database and reported separately.

  • @emirtm
    @emirtm Рік тому +1

    A little bit confused, weren't you suppose to have "baseline duration" and then change only "Actual Duration? In first instance the task "stud walls" was supposed to be completed as per the baseline but was only half way through once you changed durations

    • @PatJHeffernan
      @PatJHeffernan  Рік тому +1

      The stud wall task still took the same amount of time, but started a day late because its predecessor (demolition) was delayed in finishing. This is reflected in the tracking gantt.

  • @abubakriqbal2355
    @abubakriqbal2355 Рік тому +1

    Thanks prof

  • @Engineerselva
    @Engineerselva 6 місяців тому

    I cannot find the Task board option in my MS PROJECTS 2019. Can you help me in this?

    • @PatJHeffernan
      @PatJHeffernan  6 місяців тому

      I’m sorry, that must be frustrating. Unfortunately, I’m not setup to do troubleshooting assistance.

  • @zachguest3588
    @zachguest3588 2 роки тому

    What about a task that is split, or one that wasn't intended to be split and was performed in a split matter?

    • @PatJHeffernan
      @PatJHeffernan  2 роки тому +1

      Hi Zack... did I mention I hate splitting tasks... sometimes necessary, but normally to be avoided as it typically affects efficiency. No biggie... if you've split a task (and then baselined your project), just make the changes for the task to reflect actual (including any splits) and then mark it as complete the same as if it wasn't split. The program effectively ignores the space between the task components.