How To Hide Completed Tasks In Smartsheet - 4 Of The Best Ways!

Поділитися
Вставка
  • Опубліковано 3 гру 2024

КОМЕНТАРІ • 2

  • @kritiajmani0805
    @kritiajmani0805 10 місяців тому

    How can we apply a condition for a completed task to get moved to a new sheet with date being more 30 days of being closed/completed?

    • @ProperProjectManagement
      @ProperProjectManagement  10 місяців тому

      I would set up a formula in a column that marked when the 30 days were up, for example "30 days up".. Then set up an archival rule to look for this particular "30 days up" text string.