May Update - The Daughters of Mary Building Project
Вставка
- Опубліковано 9 тра 2024
- Engineering Drawings
(Aiming to submit this May)
Mechanical Drawings
- Drawings ready to submit
- Drafting construction drawings
- Finalizing equipment selection
Electrical Drawings
- Drawings ready to submit
- Drafting construction drawings
- Working with utility company to obtain the three-phase power estimate
Plumbing & Fire Drawings
- Drawings ready to submit
- Drafting construction drawings
Structural Drawings
- Completing permit set
- Drafting construction drawings
Architectural Drawings
- Finalizing column coordination set drawing
-
Finalizing permit sets
- Wall and building sections and elevations
- Window and door schedules (size and dimensions)
Civil Drawings
- Awaiting approval from the Department of Environmental Conservation
(DEC) on the flow rate and design concept for our waste water treatment
- Completed preliminary site plan for the location of buried utilities and
grading plan
- Preparing letter of intent for a pounded well to the Department of Health
Property Entrance Expansion
- Completed enlarged road
- Trenching for permanent electric
- Preparing to install gate
Great progress, Sisters. Thank you for the update.
This project and all of you, including all workers are in my prayers🙏 ❤
Amen 🙏 and thank you for updating us from Townsville Australia
We will pray for those permits to go through quickly! Blessings!
God Bless You My Sisters
Our Lord Is Always With You 🙏❤📿💒🛐
Please pray for a family who's Son was diagnosed w Lukemia just last week,he's under 11 yrs old. Thank you & God bless. Ad Maiorem Dei Gloriam.
We are so sorry to hear this news, but please be assured of our prayers for this boy and his family. May Our Lady, Health of the Sick, intercede for his complete recovery. God bless you!
@@DaughtersofMaryPress Thank you and likewise. May our Blessed Lord Jesus Christ love guide and bless y'all.