Technique for Computing Performance % Complete

Поділитися
Вставка
  • Опубліковано 25 січ 2025

КОМЕНТАРІ • 19

  • @PlanAcademy
    @PlanAcademy  2 роки тому +1

    Our NEW Progressing Course just launched!
    Check out the best Advanced P6 Training available online:
    www.planacademy.com/

  • @Ahamed.K-hc8eo
    @Ahamed.K-hc8eo Місяць тому

    superb explanation... very crystal clear ....

  • @peterwang1011
    @peterwang1011 2 роки тому +1

    WBS milestone complete seems particularly useful when WBS entirely corresponds Bill of Quantities valued against rules of credit. In this case activities reflect the site works whilst WBS mainly contributes to valuation and financial matters.

  • @vladimirrisojevic3945
    @vladimirrisojevic3945 Рік тому

    Imposed payment milestones should be applied in P6, on WBS level !? Could You please explain possible relationships between rules of credit and payment milestones!? Thanks

  • @Pacific998
    @Pacific998 3 роки тому

    i have never used WBS milestone complete..i have not seen it used any schedules at all

  • @he2018xiao-ud2zr
    @he2018xiao-ud2zr Рік тому

    how to make level automatic calculatiom completed

  • @ahmadaltayeb1983
    @ahmadaltayeb1983 2 роки тому

    Please Sir, I had a question, why percentages will not roll up to project level in primavera p6, please not that it is roll up in WBS level, and I already assign recourses, please advise.

  • @mahansor8295
    @mahansor8295 11 місяців тому

    Hi Michael,
    I have a resource - cost loaded plan , the performance % is shown zero, I have checked all the settings , could you please advise hoe to resolve the issue .
    Thank you

    • @PlanAcademy
      @PlanAcademy  11 місяців тому

      Could be a bunch of things. Is it 0% for activities or WBS? Is there progress with values in the "Actuals" fields - Actual Budgeted Cost, Actual Budgeted Units.? I would check those first.

  • @omarmdsaleem
    @omarmdsaleem 3 роки тому

    if WBS Milestones percent complete selected, will it change the activities Actuals automatically ?

  • @kaviwithshanu-pursuitofper9393
    @kaviwithshanu-pursuitofper9393 2 роки тому

    Excellent, I have small clarification, currently I'm working on Master schedule as vendor which contains both contractor and vendor wbs/activities. I update only vendor activities. So when I filter my vendor activities p6 is not summarizing performance %complete. Could you please help to summarize

  • @Aryanss5743
    @Aryanss5743 2 роки тому

    Dear Sir,
    When i update the schedule i have performance % values in activities . But in the WBS the performance % is showing as Zero. Please guide me to solve this issue. As i already refresh the schedule many times but still it is showing Zero

    • @raulrodriguez9892
      @raulrodriguez9892 Рік тому

      I am having the same issue? How did you resolve this?

    • @prasanthk1748
      @prasanthk1748 4 місяці тому

      @@raulrodriguez9892 same thing anybody guid me to solve

  • @benzonjhermogeno
    @benzonjhermogeno 10 місяців тому

    Thanks

  • @khaledAhmed-eb4be
    @khaledAhmed-eb4be Рік тому

    0%100% is useful for engineering activities updates , but the problem is settings is qpplied to entire schedule not to certain activity only .

    • @khaledAhmed-eb4be
      @khaledAhmed-eb4be Рік тому

      Custom also is ok like 75% and 100%

    • @PlanAcademy
      @PlanAcademy  Рік тому +1

      actually, you can apply this to each WBS in P6. So it's applied at the WBS level. Check the WBS screen and tabs for the settings.