your videos are super helpful and you are a good trainer, Could you kindly make a video on how to do an Assessment for Sub contractor payment with the supporting documents and what are the key methods on identifying subcontractor especially concrete and steel.
it is the payment application that becomes the certificate when the client agrees to the application. So in preparing for certificate you prepare an application then when the application is approved it becomes a certificate.
Hello, Thanks for such an informative videos if the definition of previous is "the work done in previous month", How "Current" graph is always equals Total-Previous? for instance what about the other works done about 2 or 3 months ago? Previous should be - all the previous works done together before current month right?
Why do we deduct advance payment twice each month? For example month 1 - we deducted already AED 1339 from total amount as deduction (2), again in the row we are deducting AED 1339 again to make net payment AED9373. Can you please explain why so ? Much thanks.
Thank you Seetha for watching and for the question. Deduction 1 is the retention and deduction 2 is the recovery of advance payment. And because we deduct the previously paid which includes full advance payment amount we add again the remaining advance payment “to not deduct it”. Also remember remember we always work with the total. 👍
Dear Ahmed, Greetings Can you please let me know which course will really effects to get the whole knowledge/Information for project tendering and costing from begging to the end...
EVERYTHING HERE IS FREE, WITH NO GREED. THANK YOU AHMED
Thanks for your videos and sharing valuable information! Keep it going Sir! From our side we will support with likes!
Thank you so much ❤️🙏
Really very informative and quite helpful , Thanks a lot Mr. Adel
its really amazing keep it up please its clear and perfect thanks a lot
Thank you for watching and support 🙂
Thank you for sharing those topics. Please make video how to make certificate payment. Thank you.
There is another video covering the full project.
ua-cam.com/video/kmY8q0ARE_k/v-deo.html
@@CEPQS I already watched this video but we would like to make video certificate payment make by Consultant or owner.
Ah, now I understand 👍. Ok sure I’ll do that 👍
I have one doubt, are slab on grade and ground beams substructure?
your videos are super helpful and you are a good trainer, Could you kindly make a video on how to do an Assessment for Sub contractor payment with the supporting documents and what are the key methods on identifying subcontractor especially concrete and steel.
Good job🎉
My problem is you only explained how to prepare an interim payment application.
I didn't see how to prepare the interim payment certificate
it is the payment application that becomes the certificate when the client agrees to the application. So in preparing for certificate you prepare an application then when the application is approved it becomes a certificate.
Hello, Thanks for such an informative videos
if the definition of previous is "the work done in previous month", How "Current" graph is always equals Total-Previous? for instance what about the other works done about 2 or 3 months ago?
Previous should be - all the previous works done together before current month right?
Previous is the total as per the last month 👍
Anyone could you please explain how to find work done in percentage? What is the formula?
Great vedio sir
Thank you so much 🙏
Why do we deduct advance payment twice each month?
For example month 1 - we deducted already AED 1339 from total amount as deduction (2), again in the row we are deducting AED 1339 again to make net payment AED9373. Can you please explain why so ?
Much thanks.
Thank you Seetha for watching and for the question. Deduction 1 is the retention and deduction 2 is the recovery of advance payment. And because we deduct the previously paid which includes full advance payment amount we add again the remaining advance payment “to not deduct it”. Also remember remember we always work with the total. 👍
Anyone could please explain how to find work done in percentage?
Dear Ahmed,
Greetings
Can you please let me know which course will really effects to get the whole knowledge/Information for project tendering and costing from begging to the end...
Quantity surveying
Great video
Thank you :)
Hello Ahmed, thanks for the video. This topic confuses me. Could you please do an example to help me understand the concept?
Yes sure 😃. This will be in the next video 👍👍
Example with numbers
Don't forget to like and comment on the new video :D
sir,
when u will release 3rd course.waiting for long time,
UA-cam is taking all the time now 😃
Shukran
Thank you sir
Welcome 🙏
Very clear and more informative , can we get this in Excellsheet for practice?
Thank you Zia, I’ll check a mechanism on how to share such files easily.
Nice
`
😃