Earned Schedule- An improvement to EVM Scheduling Metrics

Поділитися
Вставка
  • Опубліковано 28 жов 2024

КОМЕНТАРІ • 44

  • @benzonjhermogeno
    @benzonjhermogeno 7 місяців тому +1

    Thanks madam, it's really helpful

  • @mrrownel
    @mrrownel 6 років тому +1

    I commend you on the clarity which you spoke and the simply and effective way in which you explained.
    Excellent video! Thank you and well done!

  • @haroonmohammed4265
    @haroonmohammed4265 4 роки тому +1

    Planned Value curve in the graph for the later part of explanation is suppose to reach 1M at the planned duration, month 6 and the EV extending to the actual duration, month 9. apart from that, very informative. Thankyou.

  • @pallavisalunkhe9049
    @pallavisalunkhe9049 3 роки тому +1

    Detailed explanation. Appreciated. Thank you

  • @hammon8108
    @hammon8108 7 років тому +1

    Very detailed explanation, you made sure you speak slowly and with emphasis to important words. Good luck, looking forward to see more video.

  • @hardiyanto254
    @hardiyanto254 6 років тому +1

    Earned Schedule more make sense than Earned Value.
    Good explanation.
    Thank you

  • @chonadocumento1664
    @chonadocumento1664 7 років тому +2

    Tons of thanks! Very impressive presentation of each topic. God bless!

  • @kgpramanick636
    @kgpramanick636 6 років тому +5

    in later part, the planned curve ( green line) is also extended to meet the actual curve ( red ), in fact the green line should remain as it is.

    • @Projectcontrolacademy
      @Projectcontrolacademy  6 років тому +3

      Thanks for your attention Kg. Good observation. You are absolutely right. The PV curve should have been stopped at month 6. The calculations are right though.

    • @chin3884
      @chin3884 6 років тому

      I also got confused then.

  • @MikayilRAHIMOV
    @MikayilRAHIMOV 7 років тому +1

    Hi Shohreh,
    Appreciated your effort.Perfect!.Well explained.

  • @udathaxyz
    @udathaxyz 6 років тому +1

    Excellent explanation. Very interesting and understandable. Very well rendered.

  • @akhild69
    @akhild69 Рік тому

    We can look at introducing BAC (t) , ETC (t) & EAC(t) metrics to forecast completion times similar to Cost forecast by factoring schedule performance with time metrics

  • @waltherchambi2718
    @waltherchambi2718 2 роки тому

    Thanks for the explanation, how is the calculation of earned value of indirect cost as well owner cost, CM cost, …

  • @roganfield8955
    @roganfield8955 4 роки тому +1

    Thank you very much Ms.Shohreh!.. it is very helpful and informative..i actually encountered this dilemma in my previous work (dilemma when the spi is 1 but was already beyond the completion date).. thank you very much!.. i hope i came across this video during that time.. :) however, i just noticed the graph from your last example that the PV at the end of June does not reflect a 100% completion. Should not it be more proper to have it have its peak by End of june and flattens toward the end of september?

  • @SohamBanerjee123
    @SohamBanerjee123 4 роки тому +1

    SPI is a ratio , no question of units(say $) . Only issue is at the end it will come down to 1.

  • @jonhitchcock5070
    @jonhitchcock5070 7 років тому +2

    Good presentation. At the end of project illustration does not show the planned value curve correctly because the planned schedule value should end at six months rather than following the Earned Schedule out to nine months. The planned line should not be moving as the schedule variance begins to accumulate. If there is a way to get the information into a shorter amount of time, more concise, it would be even better.

    • @Projectcontrolacademy
      @Projectcontrolacademy  7 років тому +1

      Thanks for the correction Jon. You are absolutely right. The PV curve should have stopped at month 6. The calculations are right though.

  • @chin3884
    @chin3884 6 років тому +1

    Thank you. Very good explanation. Can you explain "earned duration"?

    • @Projectcontrolacademy
      @Projectcontrolacademy  6 років тому

      Thanks for your comment. In regards to your question, there is no term as "earned duration". The 3 key elements of Earned Schedule technique are "Earned Schedule (ES), "Actual Time (AT)", and "Planned Duration (PD)". These elements were described in the video.

  • @adinaswabi1213
    @adinaswabi1213 4 роки тому +1

    Much Appreciated your efforts in Project Management specially in Project control Management. Let me ask you, can we claim any PDUs for PMP certificate renewal against these training's?

    • @Projectcontrolacademy
      @Projectcontrolacademy  4 роки тому

      Zafar, thank you for your message. We do offer official PMI PDUs as we are a registered education provider of PMI. However, we cannot offer PMI PDUs for our UA-cam videos, as we don't have a means of assessing whether the viewer has watched the entire video or not. However, you can claim 1.5 PDUs by attending our free monthly webcasts. You can also get 10-35 PDUs upon the completion of our comprehensive training programs. You can check our website for more details. www.projectcontrolacademy.com/project-controls-training/

  • @ahmedalmassri2037
    @ahmedalmassri2037 4 роки тому +1

    great really

  • @ezsutra
    @ezsutra 2 роки тому +1

    How can you determine Earned Schedule in a spreadsheet?

    • @Projectcontrolacademy
      @Projectcontrolacademy  2 роки тому

      Yes, actually it works better in Excel and via calculations. Check earnedschedule.com/Calculator.shtml for calculators developed by the ES creator, Walter Lipke.

  • @ayushmansdiary2694
    @ayushmansdiary2694 6 років тому +1

    Hi,
    Can you pls explain me what is the difference between value of work done and earned value or budgeted cost of work performed. I'm really confused with these two terms

    • @Projectcontrolacademy
      @Projectcontrolacademy  6 років тому +1

      Ranjan, you are referring to the old EVM terminologies. Budgeted Cost for Work Performed (BCWP) also called Earned Value (EV), is the budgeted cost of work that has actually been performed. For getting more clarity on EVM, I suggest you check these EVM free training video series: projectcontroltraining.com/evmfreetraining/

    • @ayushmansdiary2694
      @ayushmansdiary2694 6 років тому +1

      Project Control Academy thank you

    • @Projectcontrolacademy
      @Projectcontrolacademy  6 років тому

      Our pleasure Ranjan.

  • @rexbk
    @rexbk 7 років тому +1

    Nice proooject. Thanks.

  • @chin3884
    @chin3884 6 років тому +1

    What is the difference between earned schedule and earned duration?

    • @Projectcontrolacademy
      @Projectcontrolacademy  6 років тому

      Thanks for your comment. In regards to your question, there is no term as "earned duration". The 3 key elements of Earned Schedule technique are "Earned Schedule (ES), "Actual Time (AT)", and "Planned Duration (PD)". These elements were described in the video.

  • @muhammadtahir7527
    @muhammadtahir7527 7 місяців тому

    I am sure the concept of earned schedule is floated by someone who has never been a scheduler on a project. The completion date is always calculated by scheduling tool (p6) which is dead precise. SPI was never intended to get the completion or end date of project. It's used as a monetary bench mark against which the work done (EV) is measured. I wonder why it's being inculded by PMI

    • @Projectcontrolacademy
      @Projectcontrolacademy  7 місяців тому

      We recommend you read the Earned Schedule book by Walter Lipke and all the case study applications of the accuracy and application of Earned Schedule in projects to get a better idea. Alternatively you can check the Earned Schedule website at www.earnedschedule.com/