Tarlo River Passive House - Sustainable House Day 2023

Поділитися
Вставка
  • Опубліковано 13 вер 2024
  • Tarlo River Passive House
    Greenwich Park, NSW
    Sitting on a 100 acre-block two hours from Sydney, this house utilizes passive house methods while being cost-efficient and creating a lower impact to the surroundings. Its unique design of three connected pavilions maximises the tranquil view of suburban Sydney.
    Learn more about this home: sustainablehou...
    Sustainable House Day 2023 allows access into Australia’s most unique and inspiring sustainable homes sustainablehou...

КОМЕНТАРІ • 9

  • @georgewhitehouse8630
    @georgewhitehouse8630 Місяць тому

    Beautiful work

  • @user-le4gj7hg4p
    @user-le4gj7hg4p Рік тому

    Thanks for sharing.

  • @sharonadlam3195
    @sharonadlam3195 Рік тому

    Gorgeous house and stunning views

  • @igorcordas651
    @igorcordas651 Рік тому

    Wanted to build something similar years back,never did. Now you inspired me.

  • @RenewAustralia
    @RenewAustralia  Рік тому

    Do you have further questions about this build? Reach out to the homeowner and read detailed sustainability credentials here: sustainablehouseday.com/listing/tarlo-river-passive-house/

  • @markfaulkner4141
    @markfaulkner4141 Рік тому

    Great building. Are you able to give an idea of cost/m2?

  • @rahabh09
    @rahabh09 Рік тому

    Beautiful house and site. Thanks for sharing. Should have been in Grand Designs Australia! :)
    What was your timeline from the start from designing to then building and moving in?
    And if possible to share where would a build like this sit on per square meter rate?

    • @DuncanHandley
      @DuncanHandley Рік тому +1

      This was not a cheap build, it came at $1.4M for 180m2 (plus about the same area again in deck). I'm sure a more traditional passive house shape with standard fittings closer to a city can be done far more economically but we are happy with the value we got for the price.
      The build took 15 months from construction certificate issue to occupation certificate, a lot of the progress was very fast (like 3 weeks for the assembly of the off site built airtight structure) but there were long delays around covid lockdowns and also timber availability.