Hi Tom - love your videos, am recomending them to lots of people. Oh and I'm a different Matt Tucker than the one below :) Once you have linked the date how can you tell what other task it is linked to? I see the grey triangle but can't find out which task it was linked to.
first of all, many thanks for sharing this method. Unfortunately, the method doesn't work in my MSP (2016) even though I did exactly the same as what you teach here. This method doesn't work though, I really really like your videos about the MSP and I think they are the best ones I have ever known.
Sorry to hear that Richard, it was a but buggy in some versions, ill review and think about an alt way of getting the same results. I find when one thing does not work there is usually a different way that does. Thanks for your feedback and for watching
Great ! I have been struggling when adjusting dates. This will help a lot. Except for the visual editing (hammock activity in grey) Is there a way to know when such a constraint has been set? Thank you!
Hi Mickael, in the start date or finish date cells beside the task there should be a little triangle in one of the corners of the cell boxes. Hope that helps.
Good morning sir, Thanks for bringing such great videos .I tried adding Hammock activity following steps guided in your video. But software takes that as a critical.Please help ....
Hi Matthew, are you using paste special And clicking paste link within the Paste special box. Also when you change the duration in the driving task it takes a few seconds for it to change the hammock task
Hi Tom - love your videos, am recomending them to lots of people. Oh and I'm a different Matt Tucker than the one below :)
Once you have linked the date how can you tell what other task it is linked to? I see the grey triangle but can't find out which task it was linked to.
It should show in the predecessor’s and successors column, thanks for watching
first of all, many thanks for sharing this method. Unfortunately, the method doesn't work in my MSP (2016) even though I did exactly the same as what you teach here. This method doesn't work though, I really really like your videos about the MSP and I think they are the best ones I have ever known.
Sorry to hear that Richard, it was a but buggy in some versions, ill review and think about an alt way of getting the same results. I find when one thing does not work there is usually a different way that does. Thanks for your feedback and for watching
@@TomStephensontraining My pleasure and again really appreciate your sharing and great knowledge in MSP and project management practical know-how.
Great ! I have been struggling when adjusting dates. This will help a lot.
Except for the visual editing (hammock activity in grey) Is there a way to know when such a constraint has been set?
Thank you!
Hi Mickael, in the start date or finish date cells beside the task there should be a little triangle in one of the corners of the cell boxes. Hope that helps.
@@TomStephensontraining great, thank you for the precision
Good morning sir, Thanks for bringing such great videos .I tried adding Hammock activity following steps guided in your video. But software takes that as a critical.Please help ....
Hmm maybe time for another video on this issue. Hard to solve in comments. Thanks for the question
@@TomStephensontraining Thank you very much for reply sir.Eagerly waiting for video.
Very strange this doesn't work for me, the hammock task just stays where it is.
Hi Matthew, are you using paste special
And clicking paste link within the Paste special box. Also when you change the duration in the driving task it takes a few seconds for it to change the hammock task