- The Statter Harbor Moorage Improvements Project is an $8.3 million project to replace the existing concrete headwalk, gangway and utility float and the wood floats formally known as DeHart's Marina. The new floats are all concrete and will add 70 new assigned slips. The new floats will be secured by 160'-240' long steel piles that are socketed 20' into the bedrock.
The work is being completed by Pacific Pile & Marine and their subcontractors Puffin Electric and Harri Plumbing.