Thanks Shaun. 0:57. Tesla Road, north side. Bottom. Stormwater drainage works. Excavator and a trench shield. 1:20. BIW. New loading platform. Not much seen going in. 1:53. Casting, north. Scaffold roof/portico re-erected over the 3 scrap bins exit doors. 2:30. Battery, roof. Left. Peeled back the membrane. Insulation seems still in place. GA/Battery entrance. Apron. Section of pavement demolished. Rebar placed, ready for concrete. GA Level 3. Centre. Concrete being pumped in through a window opening. 4:00. Westside, Giga Texas Offsite Wastewater Interceptor project. Centre. Caisson construction, no change since Brad's Saturday flyover. 4:20. GA, apron. Top. Excavator at work at the Cybertruck old exit.
@@AirwaveDynamics It's always a surprise what is going on around the site. The works at 3:57 will be worth watching. Associated works on the other side of the highway at the yellow crane, and south of the river. Plus at the water treatment plant south of the power plant.
New power supply to the data center/super computer: @ 1:48 Crews on the ground by the vaults and on the roof working to pull cables through. A lot of work remains. Wastewater Interceptor Project: @ 4:00 Caisson shaft continues to rise as they add poured in place concrete rings. The shaft will be sunk to a depth of about 40 feet. East of 130 where the other crane is, they are preparing to construct another shaft. Way off screen to the right on the other side of the river... There is site prep work for a third caisson shaft.
Greatly appreciate the higher altitude and your editing skills !
Thank you! 🤩
Love your fly overs that sound like you are in an airplane 😂
Testing out a new hovercraft for Elon😉
Thanks Shaun.
0:57. Tesla Road, north side. Bottom. Stormwater drainage works. Excavator and a trench shield.
1:20. BIW. New loading platform. Not much seen going in.
1:53. Casting, north. Scaffold roof/portico re-erected over the 3 scrap bins exit doors.
2:30. Battery, roof. Left. Peeled back the membrane. Insulation seems still in place.
GA/Battery entrance. Apron. Section of pavement demolished. Rebar placed, ready for concrete.
GA Level 3. Centre. Concrete being pumped in through a window opening.
4:00. Westside, Giga Texas Offsite Wastewater Interceptor project. Centre. Caisson construction, no change since Brad's Saturday flyover.
4:20. GA, apron. Top. Excavator at work at the Cybertruck old exit.
Appreciate the timeline and explanation of events! Wish I could obtain their schedule(s) for the week, prior to heading out.
@@AirwaveDynamics It's always a surprise what is going on around the site.
The works at 3:57 will be worth watching. Associated works on the other side of the highway at the yellow crane, and south of the river. Plus at the water treatment plant south of the power plant.
Cheers for that. Looks windy, gusty.
Thanks! Yes, very windy yesterday. Had to take off early..
New power supply to the data center/super computer:
@ 1:48 Crews on the ground by the vaults and on the roof working to pull cables through. A lot of work remains.
Wastewater Interceptor Project:
@ 4:00 Caisson shaft continues to rise as they add poured in place concrete rings. The shaft will be sunk to a depth of about 40 feet.
East of 130 where the other crane is, they are preparing to construct another shaft.
Way off screen to the right on the other side of the river... There is site prep work for a third caisson shaft.
Thanks for your contribution! Helps to know what's being depicted.
@@AirwaveDynamics You're welcome!
👋👍
When they crash test; how do they go about scrapping the vehicles?