- Sebelas Apartments by EVDEkimi. Redevelopment status 🚧 10 September
All properties FOR SALE, plans, financial indicators, renovation progress, client reviews, and much more can be found on our Instagram account @evde.kimi. Follow us!
Consultation, property selection: WhatsApp +6281338549380 or Telegram +994555901496
Today, I visited the Sebelas Apartments by EVDEkimi construction site.
The project is progressing on schedule, and here’s what has been accomplished so far:
✔️ Facade finishing is complete, and the scaffolding has been removed.
✔️ Outdoor lighting has been installed.
✔️ Pool basin plastering is finished.
✔️ Decorative woodwork for balcony ceilings and the outdoor kitchen is nearing completion.
Next steps for the upcoming two weeks:
▫️Laying granite flooring throughout all rooms
▫️Completing work on the staircases
▫️Installing door frames
▫️Setting up and connecting plumbing fixtures
▫️Installing lighting elements and LED fixtures
▫️Applying terrazzo to the pool basin and outdoor kitchen surfaces.
Sebelas Apartments complex is transforming day by day 😍 Stay tuned for more updates as we continue to progress. Follow our journey!