What is Resource Smoothing? (Resource Histogram Example)

Поділитися
Вставка
  • Опубліковано 4 жов 2024
  • What is Resource Leveling? • What is Resource Level...
    Difference between Resource Levelling and Resource Smoothing: UA-cam link: • Difference between Res...
    Crashing versus Fast Tracking: • Crashing vs Fast Tracking
    19 TIPS for setting-up the perfect project: • How to prepare, setup ...
    / @pieterrademeyer1 (Visit my Channel for Project Management topics and videos)
    This video uses an example to explain resource smoothing by delaying activities or tasks with float or slack by making use of a Gantt chart and resource histogram.
    The resource histogram and Gantt chart is used to even out the resource demand by delaying activities with float, that is activities that is not on the critical path.

КОМЕНТАРІ • 7

  • @viciwo3396
    @viciwo3396 4 місяці тому +1

    The best explanation I've watched on this topic so far.

  • @НастяБоброва-х8э
    @НастяБоброва-х8э 6 місяців тому

    Good one, very clear explanation

  • @ashokkandukury2870
    @ashokkandukury2870 4 місяці тому

    Superb

  • @JacovanWyk-x1i
    @JacovanWyk-x1i 4 місяці тому

    Hi Pieter. I watched the video, but I am unsure of wether all 4 activities with slack must be moved or can you choose between 2 activities and leave the other two with slack in their original place?

    • @pieterrademeyer1
      @pieterrademeyer1  4 місяці тому

      Yes, you can choose between B and E or D and E.