- Latitude Margaritaville HH homes are built by Mintos. Watch the highlights of a How We Build Meeting (pre drywall) with one of the Mintos Superintendents and learn what a great job Mintos does when building a home.
The Yost Group is a group of dedicated Realtors in the Greater Hilton Head, SC, and Savannah, GA areas. They are experts in Real Estate with specialties in resort communities, retirement communities, and new construction. They have helped people move to the area from all over the United States. Learn how you can live in one of the most beautiful places in the World and enjoy the dream 365 days a year.
🚨 Subscribe to this channel here:
👇👇👇👇👇👇👇👇
✅ bit.ly/30M6PMG
Download our App!
👇👇👇👇👇👇👇👇
melissayost.exprealty.com/hol...
📲 843.707.6956 - Reach out Day/Night/Weekends whenever you want; we never stop working for you!!
📲 Email: theyostgroup@gmail.com
👉 linktr.ee/theyostgroup
Follow us on Instagram: TheYostGroup
Follow us on Facebook: TheYostGroup
👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇👇
SUBSCRIBE TO THIS CHANNEL HERE: bit.ly/30M6PMG
Good explanation o the building process
I had heard the Daytona area
houses were built of concrete block, but it doesn't appear so in this video.
Great informational video! Very glad you posted this! Thank you Missy!😊
Great information!!
Great video Missy and Jim...looks like our Dreamsicle!!
It is your Dreamsicle! haha
Great video, Missy. Thanks for posting!
About how long after the foundation pour is the how we build meeting?
We tell all of our clients to expect a timeline as follows in a perfect world. After slab 12 weeks (3 months) to predrywall. After drywall five months to close. At this time, we are seeing about 10 months for the entire build without major delays. There is usually about four months from contract to the start of the build. All of these times are general estimates which is why LMHH is now saying the build time is between 14 and 18 months.
Why aren’t there any cellars?
Because this is the lowcountry. Meaning that we are at or below the sea level in most places. Basements don't make sense here due to how wet the ground can be if you try to dig a basement. :-)
@@TheYostGroup Then, how can you have inground pools? So there’s no way to insert a plastic like tub into the ground with supports?
Thank you for doing this video. Do they do the cables in Watersound too for hurricanes?
You would need to check with Watersound but it is my understanding that Watersound is built like Hilton Head. It is wood construction whereas Daytona is block. So they may be different there.
They build way better than my house was built in conway sc. How long after foundation gets poured do they start building ? Mine was next day not good
That I am not sure about. But, I do know that the City must inspect before building starts so it's definitely not the next day. We usually see the trusses and wood packages within a couple weeks from the foundation being poured.
after sheet rock is installed,on average how long does it take to complete the build.
A good rule of thumb is 5 months from drywall. Of course, it is dependent on delays but closing are usually 5 to 6 months from predryall.
When the gentleman was talking about the cable installation, he mentioned Comcast twice. Is Comcast available in Latatude Margaritaville? I am on the wait list now!
In Margaritaville Hilton Head, the cable choices are Spectrum and Hargray. Comcast is available in GA I believe but not in this area.