Thanks Master for the lecture series. Of all topics in civil engineering I have been having trouble with quantities, but with this at my fore front, I can tackle any problem at hand. Secondly make some more videos on pitched roof, gable end roof, top soil removal before foundation earth work, labor cost calculations, retaining structures, and box culvert analysis and Design. Since this is all about structural analysis and design channel. May God bless as you through that master....
sir , one doubt , we are using isolated footings only in India ,, this video method calculates for raft footing sir ,, we are not excavating for whole length of the wall instead we excavate only in footing area .
Depth of excavation for 30cm and 20cm wall are different which you have considered in depth but not while calculating length because the bottom of 20cm wall (0.7m) meet 30cm wall at 0.6m thickness not 0.9m thickness. Edit: I found that width was 0.9 due to excavation. Thanks for the video.😌
Prepare detailed estimate for the following items of work for the construction of residential building (a) RRM for foundation (75cm x 75cm) and basement50cm x 50cm , Wall thickness 20cm how can I estimate this, by assuming height of rrm and basement ??
Thanks Master for the lecture series. Of all topics in civil engineering I have been having trouble with quantities, but with this at my fore front, I can tackle any problem at hand.
Secondly make some more videos on pitched roof, gable end roof, top soil removal before foundation earth work, labor cost calculations, retaining structures, and box culvert analysis and Design. Since this is all about structural analysis and design channel.
May God bless as you through that master....
I have passed my subject by watching your video thank you so much.
Thank you sir for sharing ur knowledge with us.
It's my pleasure, we are glad this video helped you, keep watching and all the best
👍
Thanks for your patience.
You're welcome, all the best
Thank u sir,very helpful videos for understanding concept to calculate the quantity of all particular work..
You are most welcome, keep sharing and watching
Thank you soo much sir.... Love from karnataka 💓
So nice of you, All the best, keep watching and sharing
Wht a lecture.. sir , I regard u a real guru
Thank you Avijit for this respect
Tank u sir it is very helpful of exam purpose again Tanks for teaching 🙏
Always welcome, all the best, keep watching and sharing
Very helpful vedio thanks sir isi building long wall short wall vdo bhi bnao
sir , one doubt , we are using isolated footings only in India ,, this video method calculates for raft footing sir ,, we are not excavating for whole length of the wall instead we excavate only in footing area .
Great explanation Sir ❤️👌👏.....
Thanks and welcome, keep watching and sharing with your friends
Superb sir what an explanation
Great explanation sir
Thanks and welcome
Dear sir kindly share the link of part 3..
And I m really appreciate your way of explaining.. keep it up sir..
Thank you Naveen, Link of Part 3 ua-cam.com/video/eigqLHcRofg/v-deo.html
Sir plz upload the part 3. I am eagerly waiting for part 3
It is already uploaded, please check it
Thanku sir😊keep going, do more problems
Welcome, keep watching for more civil engineering videos
Is there any deduction required of Doors for DPC QUANTITY ?
depending on the placement of doors or if dpc is below the dow then no deduction but dpc is place between the door wall then yes
thanku so muc sir for these vedious
Brilliant sir jee
Part 2 👏👍
Thanks for watching, please go through part 3
Sir plese tell, Step stone masonry how 7.85 will came there on last step?
Thanku so much ..
Most welcome
super sir
Thank you so much, keep supporting
If brick work in superstructure is given diffrent for main and partition
Which value of a wall to be taken
This is already explained, main wall is 0.3m and partition wall is 0.2m
thank you sir
welcome
Cool ...
Thank you, keep sharing
Can you guide me to a video for RCC estimate..
Hello sir why ventilator is not taken in lintel deduction
Can We Change the ground level their??
Sir. what about T- Junction. Should consider it or not. Please clarify
Sir when plus joints coming in the problem what we do
Thank you sir but lwant full item of quanty estimte calculation work out :thanku sir
Sir. what Is steel quantity for RCC slab ?
And one more in dpc calculation the nominal height is .0.15m in calculation u didn't consider the value of dpc height plz explain that one
Depth of excavation for 30cm and 20cm wall are different which you have considered in depth but not while calculating length because the bottom of 20cm wall (0.7m) meet 30cm wall at 0.6m thickness not 0.9m thickness.
Edit: I found that width was 0.9 due to excavation. Thanks for the video.😌
Thank you so much for patiently watching, kindly share our content with your friends
Is the quantity of excavation = 49.7m3
door 🚪 correction in dpc ?
Sir Centerline method ellidce banye sir major axics 120 ./60
dear, excuse me , can you tell me the name of your book? thanks.
Sir, In this textbook name with author?
Varandha brick work deduction ?
Sir I am my plan copy, please send steel requirements.
Why did u take height of door (D2) 0.15 it is wrong
Sir which height we have to take
Framed structure ka estimate sir
Deductionforpartitionwalliswrong
Good explanation but writing is unclear .using bigger pen is better
Great explanation sir.
And which is the book that you are using in this video ?
What are you doing sir 😏 where is the drawing
Brick wall calculation in Cubic meters? Is this calculation comply with the SMM?
Prepare detailed estimate for the following items of work for the construction of
residential building
(a) RRM for foundation (75cm x 75cm) and basement50cm x 50cm ,
Wall thickness 20cm how can I estimate this, by assuming height of rrm and basement ??
Why ventilator is not taken in lintel deduction?
assuming we are not having a lintel for ventilator I think.
Sir hindi ma banavo video to koi ne khaber pade
Soon i will be starting Hindi Channel
Thankyou sir 🙏