BORED PILING WORK SEQUENCES

Поділитися
Вставка
  • Опубліковано 26 гру 2024

КОМЕНТАРІ •

  • @kyawmyohtet4715
    @kyawmyohtet4715 2 роки тому +2

    This helps me a lot. Thanks

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  2 роки тому

      Glad to hear it! Thank you for watching. We have uploaded a new video related to Bored Piling Works. In which, we covers each and every steps of Bored Piling Works from Setting Out to Removal of Casing.

  • @masumcee4882
    @masumcee4882 Рік тому +1

    really good one👍

  • @pilingdrill
    @pilingdrill Рік тому +1

    Good job, very helpful..

  • @sksa1995
    @sksa1995 Рік тому +1

    Great video for learning.

  • @raulverastegui3309
    @raulverastegui3309 3 роки тому +1

    Excelente Video. mil gracias por compartir conocimiento de oro

  • @こんにちは-f9e
    @こんにちは-f9e 2 місяці тому +1

    Can anyone please tell me what are those big square rocks for ? at 4:40 i often see it at construction sites stacking up so many and high up. Thanks in advance. 😊

  • @chinngan88
    @chinngan88 Рік тому +1

    Thanks for the full video. Really hard to find this kind of video on youtube.
    I have a question. I saw they welded the Rebar cage to the steel casing, what happen when they extract out the steel casing?
    I often found out on site the rebar cage fall to the bottom of the piles. What might go wrong that caused this from happening?

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  8 місяців тому

      During the extraction of the steel casing, we cut the welded rebars. So that the casing and the rebar cage will be separated and the casing could be extracted. If the poured concrete is still too wet, there may be a chance that the rebar cage can fall down to the bottom. Additional reinforcement length is usually considered above the cut-off level to avoid these issues. Even if the rebar cage goes down, it won’t affect the lapping length of the reinforcement.
      For tension piles, the rebar will be provided throughout the length of the pile. In this case, if the rebar cage is not welded to the casing, it may have a chance to move upwards due to the dynamic pressure in the confined environment.

  • @akashravindu5931
    @akashravindu5931 3 роки тому +1

    Very useful video ... thank you

  • @subashans9285
    @subashans9285 3 роки тому +2

    A very detailed explanation. Many Thanks for posting this.. if its explained with voice that would have been MORE excellent. Can you please provide info on how much time did this process take in real time productivity with the list of resources like men and machines..

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  3 роки тому +1

      Glad it was helpful! We will try to add voice explanation in our future videos.

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  3 роки тому +3

      The productivity of the piling works for the above site is 1.5, means we can do 3 piles per 2 days time. (working hours 08:30 to 18:00)
      Rock coring will kill the time, it takes around 2 for 1m rock coring.

    • @subashans9285
      @subashans9285 3 роки тому +2

      @@ProudtobeaCivilEngineer Thanks you very much once again for your response..

  • @bunsoyflor7763
    @bunsoyflor7763 2 роки тому +1

    Did they pump out the water inside the casing?

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  2 роки тому +1

      Actually it is not the water. It is stabilizing liquid (Bentonite or Polymer). Soft soils has a tendency to collapse during pile boring. To overcome this issue, the stabilizing liquids were pumped into.

    • @bunsoyflor7763
      @bunsoyflor7763 2 роки тому

      @@ProudtobeaCivilEngineer thank you, so the water inside the bore hole if there is doesn't need to be pumped out at all?

  • @indirasalvi1014
    @indirasalvi1014 3 роки тому +1

    Great .....keep it up...

  • @rahulyadav2840
    @rahulyadav2840 3 роки тому +1

    Motivation video
    Thanks for sharing 🙏👍

  • @junkyarddog7003
    @junkyarddog7003 2 роки тому +2

    Fascinating

  • @luminkyaw7771
    @luminkyaw7771 3 роки тому +2

    That is a descriptive video of making bored pile....Thanks for sharing but I got a question. Those polymer liquid is added in the hole and it will be pushed out to surface by the concrete during the process of concrete casting, won't it?. Then, what does those polymer liquid do?

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  3 роки тому

      Yes the polymer liquid will be pushed out to surface during the process of concrete casting.
      The polymer will act as a resistance shield for the soil around the bored hole. The purpose is to withstand the soft soils in the bored hole without collapsing.

  • @sundayejigah5704
    @sundayejigah5704 3 роки тому +2

    Polymer is also a drilling mud like bentonite that protect the drilling hole from collapse

  • @agniasyifadewi7996
    @agniasyifadewi7996 2 роки тому +1

    hi, may i ask for the playback speed video you use, i need it for counting the productivity of the machine by watching this video, thanks in advance

  • @zklfs94
    @zklfs94 4 роки тому +2

    Hi Thanks very much for the video. May i know what the polymer is for ? Thanks

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  3 роки тому

      @zklfs94
      The polymer is used as the stabilizing liquid for the bored pile. The same purpose as Bentonite.

  • @robertomaputi
    @robertomaputi 4 роки тому +2

    sir the rebar cage have no spacer blocks for secure concrete cover for the rebars

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  4 роки тому +1

      Kindly take a look at the video from 24:00 onwards. There are Plastic Spacers fixed to the rebar cage.

  • @syedazizulroslan7138
    @syedazizulroslan7138 2 роки тому +1

    what is the depth of prebore before insert the temporary casing?

  • @nursyafiqahshazira9386
    @nursyafiqahshazira9386 3 роки тому +1

    can we do bored piles diameter 450mm without temporary casing? and how to determine whether need to use temporary/permanent casing or not.

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  2 роки тому +2

      Basic reason of providing the casing is to prevent the soft soil from falling into the pile bore. If the casing pipe is not provided , the clay or the soft soil shall keep on falling in the excavated bore of the pile and while casting the concrete, this shall get inadvertently mixed in the cement concrete.

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  2 роки тому +4

      There are temporary casings and permanent casings.
      The temporary casing is a type of casing that is removed after the casting of concrete is complete, typically before the start of the final setting. As you must be well aware, the loose soil is generally found in the Initial layers of the Bore. So, in the case of a temporary casing, the casing is not much deep. If we have a deep temporary casing, it is very difficult to remove after the completion of casting.
      Permanent Casing is a type of casing that is concreted with the concrete and remains there for Life of the Pile. The general practice is placing the casing before pouring the concrete so that no soil gets accidentally mixed with the concrete. These kinds of casings are seen where the soil is very loose/fine & the chances of caving of the pile are more.

  • @kennethbuluran2348
    @kennethbuluran2348 2 роки тому +1

    31:25 That's not how you conduct slump test for concrete. You don't twist the slump cone while removing it.

  • @rommelmedel449
    @rommelmedel449 Рік тому +1

    project location?

  • @abxconstruction3106
    @abxconstruction3106 3 роки тому +1

    What is the thread to measure depth of concrete? How it is used?

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  2 роки тому

      It's a measuring tape. We will upload a video on this measuring tape as soon as possible. So that you can visualize it.

  • @rajasekarandhanapal7040
    @rajasekarandhanapal7040 3 роки тому +1

    Hi dear
    This is nice video good, two queries I have
    1. If the pile lenght is 15meter, what will be the casing pipe lenght and whether the casing pipe will be inserted prior to drilling the boring
    2. When the casing pipe will be removed, that is immediately after casting right ...

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  2 роки тому +2

      Thank you.
      1) The casing length depends on the soil conditions. Normally it will be provided until the hard soil layer, so that the soft soil will be resisted by casing.
      The pre-boring process will be done first roughly around 4m to 6m. After that the casing will be installed. Then the boring will be continued until the required design depth.
      2) Once the casting of pile completed, the casing will be removed prior to the final setting of concrete.

  • @indirasalvi5648
    @indirasalvi5648 3 роки тому

    Nice...Informative

  • @alamloka2626
    @alamloka2626 4 роки тому +1

    How long is the steel case used in this video?

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  4 роки тому

      The length of the used steel casing is 12m. This is mainly because of the soft nature of the geotechnical profile. The longer casing used to eliminate the collapse of the soils during boring.

  • @RAJESH-rr5ee
    @RAJESH-rr5ee 3 роки тому

    Great job.......

  • @zaza8691
    @zaza8691 3 роки тому +2

    Hi, may I ask the skip that you used for topping up during steel casing extraction, is it opened by crane or by the man down there? Or can you share some detailed photos of the skip if it doesn't trouble you. thank you very much.

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  3 роки тому +2

      @Mohd Mirza Abdul Rahman, Which crane holding the concrete bucket, the worker using the rope system to open up the bucket. It's comparatively safer.

    • @zaza8691
      @zaza8691 3 роки тому

      @@ProudtobeaCivilEngineer Oh i got it. Thank you for your explaination. Seems really good method compared to what my company is implying where the concrete bucket attached to a mancage for the worker to handle the skip. More hassle and concern on the safety part. Thank you very much for the sharing !

  • @aimangomeztv6658
    @aimangomeztv6658 3 роки тому +1

    600mm diameter?

  • @abdodaccache6857
    @abdodaccache6857 3 роки тому +1

    What is the pile diameter?

  • @markgalatians5620
    @markgalatians5620 3 роки тому +1

    May ask sir if you immediately remove the steelcast after concrete pouring

  • @rahulyadav2840
    @rahulyadav2840 3 роки тому +1

    Dear sir, is the vacancy of crawler crane operator or peeling rig operator in your company?

  • @stevetan9142
    @stevetan9142 4 роки тому +2

    This work sequence is right. However, there are many serious safety laspes. I hope such work site will have a swo by mom.

    • @sundayejigah5704
      @sundayejigah5704 3 роки тому +1

      All the job sequences are to be carried out or executed in accordance to quality and safety requirement for the project specific . I observed personnel working under a suspended load, within the swing radius of the machine which placed them in a line of fire. Such project aught to implored or lash onto the services of certified safety and quality personnel.

    • @stevetan9142
      @stevetan9142 3 роки тому

      @@sundayejigah5704 based on what u say, I guess u r not a site person. Ur theory is merely text book safety

    • @stevetan9142
      @stevetan9142 3 роки тому

      Since I talk like tt den the collapse zone also have to take into consideration lo. Am I right?

  • @vithursonsubasharan5030
    @vithursonsubasharan5030 5 років тому +2

    Informative :)

  • @waikiankhoo8746
    @waikiankhoo8746 3 роки тому

    what is the criteria for polymer viscosity check?

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  3 роки тому

      It's depends on the polymer material used. However for the above project, the viscosity of at least 60s but no higher than 100s was used as the criteria.

    • @waikiankhoo8746
      @waikiankhoo8746 3 роки тому

      @@ProudtobeaCivilEngineer thanks

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  3 роки тому

      @@waikiankhoo8746 Welcome

  • @jamongus9918
    @jamongus9918 2 роки тому +1

    arent you cutting tremie pipes during concrete pouring

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  2 роки тому +1

      The tremie pipes need to be cut during pouring. However, it's quite hard to take video which covers full activity. Thank you for your concern. Kindly view our latest video related to Bored Piling Works for full activity. From Setting Out to Casing Removal.

  • @jaidulsekh3883
    @jaidulsekh3883 4 роки тому +1

    Agar pile kajer khobor thaklay bolben dada

  • @waiztechnology2672
    @waiztechnology2672 3 роки тому +1

    informative video

  • @shaq2606
    @shaq2606 2 роки тому +1

    apa hazard yg korng nmpk kt situ? cer gtau. sbb hrtu aq ad exam sss. tp tulah keliru ah . exam yg tgok dlm vdeo

  • @soksothy6711
    @soksothy6711 3 роки тому +1

    good

  • @aimangomeztv6658
    @aimangomeztv6658 4 роки тому +3

    Interesting, can anyone bring me to the site like this😍😍

  • @luismiguelgarciacanan5245
    @luismiguelgarciacanan5245 Рік тому +1

    Me gusta piling

  • @TotalMixClub
    @TotalMixClub 4 роки тому +1

    Super big soil drill

  • @treft3853
    @treft3853 3 роки тому +1

    roughly surveyed

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  3 роки тому

      It's not roughly surveyed. Actually we did the Setting-Out of Piles with a Licensed Surveyor. He marked the center of each piles with reinforcement bars. In order to verify the distance between two piles, we just counter-check with the measurement tape.

  • @WuhanYijueMachineryCoLtd
    @WuhanYijueMachineryCoLtd 3 роки тому +2

    Hi, we are from China, we export piling machinery parts( drill teeth, drill bucket, core barrel, roller cone), welcome to inquire me!

  • @indritelezi549
    @indritelezi549 4 роки тому +1

    vibrohammer its not allowed to use near other bulding....

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  4 роки тому +1

      Normally the vibration will be measured during piling works. There is a allowable limit for vibration for each type of buildings like hospitals, commercial buildings, residential buildings etc.

    • @basurukodagoda6134
      @basurukodagoda6134 4 роки тому +1

      @@ProudtobeaCivilEngineer can u please upload a video on that too? 'measuring vibration, during construction works.'

    • @ProudtobeaCivilEngineer
      @ProudtobeaCivilEngineer  3 роки тому

      @@basurukodagoda6134 Sure, We will try to do

  • @TEMELTASCONSTRUCTION
    @TEMELTASCONSTRUCTION 4 роки тому +1

    👍

    • @terexovsa
      @terexovsa 4 роки тому +1

      We sell vibration hammer qpvibro.com/

  • @jacknordli7630
    @jacknordli7630 4 роки тому +1

    Sure it's plumb, as a matter of fact it's a little better than plumb.

  • @zackkuan9786
    @zackkuan9786 4 роки тому +1

    singapore!

  • @charanjitsingh6937
    @charanjitsingh6937 6 місяців тому

    Manual bucket 😂

  • @mohdtufail4700
    @mohdtufail4700 Рік тому +1

    Hlo sir I'm a vibro hammer operator. If you need vibro hammer operator plz contact me